Array ( [id] => 123156 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州滨海新城一沥青混凝土路面修复进入尾声 [editor] => (实习)陈洁 [has_thumb] => 1 [created] => 2019-10-19 10:28:58 [createdby] => 10176 [createdip] => 192.168.12.14 [published] => 2019-10-19 10:28:58 [publishedby] => 10176 [modified] => 2019-10-19 11:08:14 [modifiedby] => 10176 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 501 [virtual_pv] => 416 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

17日,记者获悉,长乐G228线K4592+870-K4623+025沥青混凝土路面修复工程(一期)建设已进入尾声。

当天上午,在该项目施工现场,只见沥青路面已经铺就,道路笔直宽敞。长乐公路事业发展中心相关负责人介绍,该项目起于G228线K4592+8705文武砂镇东山村,终于K4623+025松下镇山前村福清交界。

据介绍,G228线现为福州滨海新城范围内交通大动脉,承载着重要的交通通行功能,随着交通量及重车的增加,在多年行车影响下,沿线红绿灯叉路口沥青路面出现车辙、网裂等病害、路面车道分界线磨耗、部分车路口道口标柱缺失。长乐公路事业发展中心组织开展修复工作,进行试点3处路口沥青路面整治、沿线车道分界线标线重划、交安设施完善等。

“该工程工期60天,8月30日正式动工,目前项目施工已接近尾声。”上述负责人介绍,项目已完成沥青混凝土路面铣刨重铺约17000平方米,标线重划10000平方米,剩余2厘米超薄磨耗沥青层3500平方米涉及到科技技术改革探索,正在与相关专家进行研究论证。项目目前仍在进行标线施划和安保设施完善,请过往车辆通行期间减速慢行。


来源:福州日报
编辑:陈洁 责编:庄颖


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 项目施工现场,沥青路面已经铺就,道路笔直宽敞。 [thumb] => [{"url":"\/a\/10001\/201910\/81df8068d6363f239ee7393809cba11c.jpeg","id":"1322526"}] [url] => /p/123156.html [all_pv] => 501 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 沥青路面 [1] => G228 [2] => 标线 [3] => 长乐 [4] => 沥青 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 51204 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/51204.html [wapUrl] => http://m.fztvapp.zohi.tv/p/51204.html [published_timestamp] => 1543547592 [published] => 1543547592 [pv] => 610 [virtual_pv] => 395 [all_pv] => 610 [title] => G228线长乐段改造 路面工程明年1月底前有望完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/86758fc3fb4e3c67ec2b2f4ef93cad3b.jpeg ) [1] => Array ( [relateid] => 25650 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/25650.html [wapUrl] => http://m.fztvapp.zohi.tv/p/25650.html [published_timestamp] => 1531232348 [published] => 1531232348 [pv] => 140 [virtual_pv] => 388 [all_pv] => 140 [title] => 长乐:滨海新城228国道项目启动应急预案 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/fa930eb92fc16dbe815a3bfd58842551.png ) [2] => Array ( [relateid] => 13783 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/13783.html [wapUrl] => http://m.fztvapp.zohi.tv/p/13783.html [published_timestamp] => 1515997811 [published] => 1515997811 [pv] => 883 [virtual_pv] => 0 [all_pv] => 883 [title] => 与山水同生 筑绿色公路 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/4c2f2acbcfae815ac44142645f0d51a0.JPG ) [3] => Array ( [relateid] => 79746 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79746.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79746.html [published_timestamp] => 1554808709 [published] => 1554808709 [pv] => 653 [virtual_pv] => 431 [all_pv] => 653 [title] => 228国道长乐外文武围垦堤至下沙段路堤结合工程:路堤景"三位一体" 为滨海新城建设添彩 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/13d9af75fd7b0625ec16e10936b81519.JPG ) [4] => Array ( [relateid] => 102918 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/102918.html [wapUrl] => http://m.fztvapp.zohi.tv/p/102918.html [published_timestamp] => 1563941525 [published] => 1563941525 [pv] => 129 [virtual_pv] => 478 [all_pv] => 129 [title] => 这条路“白改黑”完成,回家更舒服了 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/f846180260ba7c3dc7e6cbf0dbaac3ec.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201910/81df8068d6363f239ee7393809cba11c.jpeg ) 1

福州滨海新城一沥青混凝土路面修复进入尾声

2019-10-19 10:28   福视悦动  

17日,记者获悉,长乐G228线K4592+870-K4623+025沥青混凝土路面修复工程(一期)建设已进入尾声。

当天上午,在该项目施工现场,只见沥青路面已经铺就,道路笔直宽敞。长乐公路事业发展中心相关负责人介绍,该项目起于G228线K4592+8705文武砂镇东山村,终于K4623+025松下镇山前村福清交界。

据介绍,G228线现为福州滨海新城范围内交通大动脉,承载着重要的交通通行功能,随着交通量及重车的增加,在多年行车影响下,沿线红绿灯叉路口沥青路面出现车辙、网裂等病害、路面车道分界线磨耗、部分车路口道口标柱缺失。长乐公路事业发展中心组织开展修复工作,进行试点3处路口沥青路面整治、沿线车道分界线标线重划、交安设施完善等。

“该工程工期60天,8月30日正式动工,目前项目施工已接近尾声。”上述负责人介绍,项目已完成沥青混凝土路面铣刨重铺约17000平方米,标线重划10000平方米,剩余2厘米超薄磨耗沥青层3500平方米涉及到科技技术改革探索,正在与相关专家进行研究论证。项目目前仍在进行标线施划和安保设施完善,请过往车辆通行期间减速慢行。


来源:福州日报
编辑:陈洁 责编:庄颖