Array ( [id] => 123537 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 长平高速公路全线贯通 [editor] => (技术)简小华 [has_thumb] => 1 [created] => 2019-10-21 09:24:31 [createdby] => 10019 [createdip] => 192.168.12.7 [published] => 2019-10-21 09:24:31 [publishedby] => 10019 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 439 [virtual_pv] => 404 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

松下跨海特大桥最后一跨箱梁完成浇筑。

昨日,长平高速公路松下跨海特大桥最后一跨现浇箱梁顺利完成浇筑,标志着该桥双幅顺利贯通。这也意味着长平高速公路全线贯通。

昨日10时,在松下跨海特大桥和平潭公铁大桥连接处,一台10多米高的天泵将长长的“手臂”悬垂在箱梁的钢筋模架上方,工人扶着管子,将喷射而出的混凝土均匀地浇注在模架内,并用机械进行平整等操作。

据中交一公局厦门公司长平高速CPA3项目部副总工刘诗泽介绍,这是松下特大桥最后一跨的右幅箱梁。这跨箱梁的顺利浇筑,意味着松下跨海特大桥全线贯通。

松下跨海特大桥作为长平高速公路控制性工程,全长1.4公里,从2016年1月开工至今历经46个月。

9月29日,长平高速一期项目(前塘枢纽互通—松下枢纽互通)已经通车。据介绍,松下跨海特大桥顺利贯通,意味着二期(松下枢纽互通—松下跨海特大桥)主体工程建设完成,接下来将进行防撞墙、风屏障等附属工程的施工,预计于12月完成,力争年底实现全线通车目标。

长平高速公路项目是国高网京台高速公路的延伸线,也是平潭第二进岛通道。项目全长21.703公里,起于长乐古槐镇,与福州绕城高速公路东南段前塘互通相连,终于平潭海坛海峡长乐岸,与在建的平潭公铁大桥相接,项目为双向六车道高速公路,设计行车速度100公里/小时。

长平高速公路建成通车后可实现1小时进岛,比目前节省半小时,进一步密切滨海新城和平潭综合实验区的岛城联系,促进沿线及平潭的经济发展,加速闽东北协同发展。


来源:福州日报
编辑:简晓华 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201910\/3f6d27e625acc32604fb8c5b70901036.jpeg","id":"1329822"}] [url] => /p/123537.html [all_pv] => 439 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 松下 [1] => 大桥 [2] => 跨海 [3] => 长平 [4] => 平潭 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 28019 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/28019.html [wapUrl] => http://m.fztvapp.zohi.tv/p/28019.html [published_timestamp] => 1533870572 [published] => 1533870572 [pv] => 1080 [virtual_pv] => 473 [all_pv] => 1080 [title] => 长平高速松下跨海特大桥桩基完工 明年下半年通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201808/24b8e1bbd7e81cdfb89e900943578695.jpeg@w720_h540.jpeg ) [1] => Array ( [relateid] => 25227 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/25227.html [wapUrl] => http://m.fztvapp.zohi.tv/p/25227.html [published_timestamp] => 1530839771 [published] => 1530839771 [pv] => 1098 [virtual_pv] => 413 [all_pv] => 1098 [title] => 长平高速全线隧道贯通,平潭将纳入福州1小时生活圈 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/8ee5b6c073979a6ba86a4f80442b25d1.jpeg ) [2] => Array ( [relateid] => 25238 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/25238.html [wapUrl] => http://m.fztvapp.zohi.tv/p/25238.html [published_timestamp] => 1530850320 [published] => 1530850320 [pv] => 746 [virtual_pv] => 470 [all_pv] => 746 [title] => 长平高速全线隧道贯通 平潭将纳入福州1小时生活圈 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/69a3b926a26015e71df98c8186941acb.jpeg ) [3] => Array ( [relateid] => 25422 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/25422.html [wapUrl] => http://m.fztvapp.zohi.tv/p/25422.html [published_timestamp] => 1531053839 [published] => 1531053839 [pv] => 598 [virtual_pv] => 435 [all_pv] => 598 [title] => 长平高速建设按下"快进键" 松下和江田收费站主体结构封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/a8334fb9844f28b454c24748fbe5e66c.JPG ) [4] => Array ( [relateid] => 39741 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39741.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39741.html [published_timestamp] => 1539152863 [published] => 1539152863 [pv] => 1077 [virtual_pv] => 380 [all_pv] => 1077 [title] => 福厦高铁泉州湾跨海大桥主栈桥顺利贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/e4a891a6cabea92fa7063341ff6c7e37.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201910/3f6d27e625acc32604fb8c5b70901036.jpeg ) 1

长平高速公路全线贯通

2019-10-21 09:24   福视悦动  

松下跨海特大桥最后一跨箱梁完成浇筑。

昨日,长平高速公路松下跨海特大桥最后一跨现浇箱梁顺利完成浇筑,标志着该桥双幅顺利贯通。这也意味着长平高速公路全线贯通。

昨日10时,在松下跨海特大桥和平潭公铁大桥连接处,一台10多米高的天泵将长长的“手臂”悬垂在箱梁的钢筋模架上方,工人扶着管子,将喷射而出的混凝土均匀地浇注在模架内,并用机械进行平整等操作。

据中交一公局厦门公司长平高速CPA3项目部副总工刘诗泽介绍,这是松下特大桥最后一跨的右幅箱梁。这跨箱梁的顺利浇筑,意味着松下跨海特大桥全线贯通。

松下跨海特大桥作为长平高速公路控制性工程,全长1.4公里,从2016年1月开工至今历经46个月。

9月29日,长平高速一期项目(前塘枢纽互通—松下枢纽互通)已经通车。据介绍,松下跨海特大桥顺利贯通,意味着二期(松下枢纽互通—松下跨海特大桥)主体工程建设完成,接下来将进行防撞墙、风屏障等附属工程的施工,预计于12月完成,力争年底实现全线通车目标。

长平高速公路项目是国高网京台高速公路的延伸线,也是平潭第二进岛通道。项目全长21.703公里,起于长乐古槐镇,与福州绕城高速公路东南段前塘互通相连,终于平潭海坛海峡长乐岸,与在建的平潭公铁大桥相接,项目为双向六车道高速公路,设计行车速度100公里/小时。

长平高速公路建成通车后可实现1小时进岛,比目前节省半小时,进一步密切滨海新城和平潭综合实验区的岛城联系,促进沿线及平潭的经济发展,加速闽东北协同发展。


来源:福州日报