Array ( [id] => 134520 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁1号线、4号线、5号线、6号线最新进展来了! [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2019-12-08 13:38:17 [createdby] => 10056 [createdip] => 120.35.7.76 [published] => 2019-12-08 13:38:17 [publishedby] => 10056 [modified] => 2019-12-08 16:34:18 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1290 [virtual_pv] => 470 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

好消息!就在最近!福州地铁多条在建项目再传新进展,接下来我们一同来看看!

1号线二期计划明年底建成通车

据福建发改委微信,截至11月份,1号线二期工程全线盾构区间已实现双线贯通,4个车站主体结构已实现全部封顶,安平站、三江口站附属结构已完成,梁厝站、下洋站附属结构正在施工,全线道床施工累计已达3.3公里。

梁厝站航拍图

1号线二期工程全长4.95公里,起于福州火车南站,终于三江口站,设车站4座,均为地下站,其中梁厝站、下洋站可与6号线实现换乘,全线计划将于2020年底建成通车。

5号线金山站北区主体结构顺利封顶

据中铁上海局城轨分公司微信,11月30日,福州地铁5号线金山站北区主体结构顺利完成封顶。

金山站北区从6月19日基坑见底起到11月30日顶板顺利封顶,共历时165天,其间,参建人员克服了一系列困难,顺利完成金山站北区主体结构施工任务。

4号线化工路-福新东路区间右线盾构顺利始发

据中交二航局工程装备分公司微信,11月21日,福州地铁4号线化工路-福新东路右线盾构机顺利始发。

另据隧道地基微信,11月底,福州地铁4号线省立医院-塔头区间顶管井开工建设,并于11月24日完成了首幅地墙的浇筑。

6号线下洋-营前区间桥梁工程主体结构全部完成

据中铁八局城轨分公司官网,12月6日,随着连续梁最后一车混凝土浇注完毕,福州市轨道交通工程首个高架区间——6号线下洋-营前高架区间桥梁工程主体结构全部完成。


另据中铁十七局六公司微信,11月20日,福州地铁6号线梁厝站-下洋站上行线盾构区间顺利始发。

据介绍,该盾构区间,右线全长675.8m上跨1号线二期工程梁下区间上行线,下穿文保建筑岐阳书院,侧穿马尾大桥桩基等结构物。

明年起 每年开通一条新线路

明年起至2023年,福州地铁将力争每年新开通一条地铁线路,确保在2023年年底前1号线二期、6号线、5号线一期、4号线一期可通车试运营。

届时,福州地铁预计可满足每小时输送9.7万人次的运力,满足每日170万~200万人次的出行需求。

在建线路概况

1号线二期:为1号线延伸段,经南湖、海峡艺术中心、终至三江口站,全长约4.95公里,设4个站。

6号线:从潘墩站至万寿站,起于海峡国际会展中心,经福泉高速、东部新城、道庆洲大桥、203省道、海峡路、郑和路、东鹤路,止于万寿站,连接东部新城、长乐主城区、滨海新城等组团,全长约32.35公里,设16个站。

5号线一期:从荆溪新城站至福州南站站,起于闽侯荆溪新城,沿闽江南岸金山路、上下店路敷设,经闽江大道、建新北路、金洲北路、金洲南路、盘屿路、义序路、螺福路、福峡路、环岛路,止于福州南站,全长27.3 km,共设20个站。

4号线一期:从橘园站至帝封江站,起于金山花溪北路,至洪塘路下穿闽江,经杨桥路、东街、东大路、塔头路、横屿路、江边洲路、高浦路、螺洲路,止于帝封江站,全长28.4km,共设23个站。

有福之州,幸福穿梭,期待家门口更多地铁线路的建成!


来源:福州日报、福建发改委、各施工单位、福州地铁微信
编辑:强婕宁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201912\/8770cb0ad61d3cb847bd78af7032e626.jpeg","id":"1481427"}] [url] => /p/134520.html [all_pv] => 1290 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 福州 [1] => 地铁 [2] => 区间 [3] => 4号线 [4] => 5号线 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 119622 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/119622.html [wapUrl] => http://m.fztvapp.zohi.tv/p/119622.html [published_timestamp] => 1570086889 [published] => 1570086889 [pv] => 501 [virtual_pv] => 370 [all_pv] => 501 [title] => 福州地铁1号线二期、4号线、5号线、6号线又有新进展 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/7b8f87d3ab1d2138a011470ac1a71368.jpeg ) [1] => Array ( [relateid] => 76857 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/76857.html [wapUrl] => http://m.fztvapp.zohi.tv/p/76857.html [published_timestamp] => 1553667181 [published] => 1553667181 [pv] => 508 [virtual_pv] => 425 [all_pv] => 508 [title] => 螺洲片区再迎好消息:地铁5号线首个区间双向贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/05174c1d1b5647b3fccdf71980c56449.jpeg ) [2] => Array ( [relateid] => 77496 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77496.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77496.html [published_timestamp] => 1553910022 [published] => 1553910022 [pv] => 159 [virtual_pv] => 381 [all_pv] => 159 [title] => 福州地铁又传好消息!2号线、5号线最新进展是…… [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/4b076f08b3917193f3012785ec221286.jpeg ) [3] => Array ( [relateid] => 129648 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/129648.html [wapUrl] => http://m.fztvapp.zohi.tv/p/129648.html [published_timestamp] => 1573959137 [published] => 1573959137 [pv] => 102 [virtual_pv] => 448 [all_pv] => 102 [title] => 福州地铁5号线又迎多个新进展!涉及这些站点 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201911/77b9f8775282d491519bb21e2a54e3cb.jpeg ) [4] => Array ( [relateid] => 44067 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/44067.html [wapUrl] => http://m.fztvapp.zohi.tv/p/44067.html [published_timestamp] => 1540806755 [published] => 1540806755 [pv] => 911 [virtual_pv] => 482 [all_pv] => 911 [title] => 福州地铁6号线首个盾构区间实现双线贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/c20bda1970fdc7e53969b252b1857d91.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/201912/8770cb0ad61d3cb847bd78af7032e626.jpeg ) 1

福州地铁1号线、4号线、5号线、6号线最新进展来了!

2019-12-08 13:38   福视悦动  

好消息!就在最近!福州地铁多条在建项目再传新进展,接下来我们一同来看看!

1号线二期计划明年底建成通车

据福建发改委微信,截至11月份,1号线二期工程全线盾构区间已实现双线贯通,4个车站主体结构已实现全部封顶,安平站、三江口站附属结构已完成,梁厝站、下洋站附属结构正在施工,全线道床施工累计已达3.3公里。

梁厝站航拍图

1号线二期工程全长4.95公里,起于福州火车南站,终于三江口站,设车站4座,均为地下站,其中梁厝站、下洋站可与6号线实现换乘,全线计划将于2020年底建成通车。

5号线金山站北区主体结构顺利封顶

据中铁上海局城轨分公司微信,11月30日,福州地铁5号线金山站北区主体结构顺利完成封顶。

金山站北区从6月19日基坑见底起到11月30日顶板顺利封顶,共历时165天,其间,参建人员克服了一系列困难,顺利完成金山站北区主体结构施工任务。

4号线化工路-福新东路区间右线盾构顺利始发

据中交二航局工程装备分公司微信,11月21日,福州地铁4号线化工路-福新东路右线盾构机顺利始发。

另据隧道地基微信,11月底,福州地铁4号线省立医院-塔头区间顶管井开工建设,并于11月24日完成了首幅地墙的浇筑。

6号线下洋-营前区间桥梁工程主体结构全部完成

据中铁八局城轨分公司官网,12月6日,随着连续梁最后一车混凝土浇注完毕,福州市轨道交通工程首个高架区间——6号线下洋-营前高架区间桥梁工程主体结构全部完成。


另据中铁十七局六公司微信,11月20日,福州地铁6号线梁厝站-下洋站上行线盾构区间顺利始发。

据介绍,该盾构区间,右线全长675.8m上跨1号线二期工程梁下区间上行线,下穿文保建筑岐阳书院,侧穿马尾大桥桩基等结构物。

明年起 每年开通一条新线路

明年起至2023年,福州地铁将力争每年新开通一条地铁线路,确保在2023年年底前1号线二期、6号线、5号线一期、4号线一期可通车试运营。

届时,福州地铁预计可满足每小时输送9.7万人次的运力,满足每日170万~200万人次的出行需求。

在建线路概况

1号线二期:为1号线延伸段,经南湖、海峡艺术中心、终至三江口站,全长约4.95公里,设4个站。

6号线:从潘墩站至万寿站,起于海峡国际会展中心,经福泉高速、东部新城、道庆洲大桥、203省道、海峡路、郑和路、东鹤路,止于万寿站,连接东部新城、长乐主城区、滨海新城等组团,全长约32.35公里,设16个站。

5号线一期:从荆溪新城站至福州南站站,起于闽侯荆溪新城,沿闽江南岸金山路、上下店路敷设,经闽江大道、建新北路、金洲北路、金洲南路、盘屿路、义序路、螺福路、福峡路、环岛路,止于福州南站,全长27.3 km,共设20个站。

4号线一期:从橘园站至帝封江站,起于金山花溪北路,至洪塘路下穿闽江,经杨桥路、东街、东大路、塔头路、横屿路、江边洲路、高浦路、螺洲路,止于帝封江站,全长28.4km,共设23个站。

有福之州,幸福穿梭,期待家门口更多地铁线路的建成!


来源:福州日报、福建发改委、各施工单位、福州地铁微信
编辑:强婕宁 责编:林真贞