Array ( [id] => 13991 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁建设最新进展!4号线今年全线站点启动围挡建设,23个站点是…… [editor] => 翁 [has_thumb] => 1 [created] => 2018-01-18 10:49:17 [createdby] => 10022 [createdip] => 27.44.1.163 [published] => 2018-01-18 10:49:17 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 677 [virtual_pv] => 0 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 0 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

福州地铁建设又有新进展!

一起来看看!

今日,我市召开地铁4号线开工建设动员部署会,围绕市委、市政府既定的一期工程2022年3月31日前通车试运行目标,对涉及的290余项前期工程任务责任清单进行详细部署,并要求今年底前,分批次完成站点(含场段)征迁交地任务,全线所有站点开始围挡建设。4号线一期全长28.4公里,起于橘园站,终于帝封江站,途经金山、鼓楼、晋安、台江、仓山等片区,连接了金山工业集中区、洪山科技园、东街商业中心、东二环泰禾广场综合体、鳌峰金融中心、东部办公区、海峡国际会展中心等主城区重要区域,建成后将与1、2、5号线在城市中心区形成“十字+环”的布局。

4号线一期线路全部采用地下敷设方式,全线共设23座车站,设一段(螺洲车辆段)一场(洪塘停车场),2座主变电站。车辆采用6节B型车编组。

记者了解到,在相关部门的全力配合下,目前4号线土建施工、监理招标已顺利完成,征迁工作陆续启动,交通疏解、施工占道、树木迁移等也陆续报批,各施工、监理单位陆续进场开展前期工程建设。计划首批开工的池边站、化工路站、江边村站、会展中心站及林浦站5个站点已完成绿化树木移植,各站点场地标准化建设同步开展。

在进一步夯实完善目标任务和工期节点的基础上,我市对4号线各项前期工程形成细化责任清单。清单针对4号线每个站点、停车场、车辆段的征迁交地、管线迁改、苗木移植等各项前期建设内容,均详细列出了需完成的工作内容、完成时间、责任单位及责任人。我市将结合一线考察干部机制,强化督导考核,落实奖惩机制,全力保障地铁加快建设。

相关链接:

福州地铁线路的进展情况如何?

预计何时建成?

一起来看看!

地铁1号线(二期)

1号线二期线路长4.95公里,由北至南分设安平站、梁厝站、下洋站及三江口站4个站点,其中梁厝站、下洋站为1、6号线的换乘站,三江口站为1号线的终点站。

地铁1号线(二期)力争2020年国庆前建成试运行。

地铁2号线

地铁2号线线路全长约30.623公里,共设22座车站,沿线为东西方向,途经闽江、乌龙江。

苏洋站—沙堤站—上街站—金屿站—福州大学站—董屿站—厚庭站(8号线)—桔园洲站—洪湾站—金山站(5号线)—金祥站—祥坂站—宁化站—西洋站—南门兜站(1号线)—水部站—紫阳站(3号线)—五里亭站—前屿站(4号线)—上洋站—鼓山站—下岐楼站

地铁2号线计划于明年1月31日前全线试运行。

地铁6号线

6号线起点站会展中心站至终点站机场站,线路全长约40.869km。全线共设车站19座,其中高架站1座,地下站18座;全线设车辆段和停车场各1座。

会展中心站—林浦站—芦岐站—梁厝站—下洋站—营前站—航城站—郑和站—十洋站—鳌头站—鹤上站—沙京站—莲花站—滨海新城站—壶井站—万寿站—尚迁站—漳港站—机场站。

全线计划于2020年12月31日前建成试运行。

地铁5号线

5号线一期20个站点:荆溪新城站、农林大学站、洪塘路站、金林路站、金华路站、金山站、金环路站、浦上大道站、建新南路站、凤山路站、福湾路站、齐安路站、吴山站、当埔路站、欢乐谷站、帝封江站、螺洲镇站、高仕路站、城锦路站、福州南站站

福州市委市政府提出,5号线一期工程的目标要求是2021年9月30日前通车试运行。

6线站点同时建设

2022年形成主体线网

今年,福州地铁1号线二期、2号线及6号线等3条线将继续加紧建设,5号线、4号线及福州至长乐机场轨道交通各站点也将陆续开工,福州地铁将迎来6条线均有站点同时建设的高速发展阶段。

预计从2019年起,福州每年将开通一条地铁线路,直至2022年,福州地铁主体线网将形成。届时,预计近四成市民出行将以搭乘地铁为主,地铁将成为福州城市发展的驱动器。


来源:福州日报

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 6线站点同时建设 2022年形成主体线网今年,福州地铁1号线二期、2号线及6号线等3条线将继续加紧建设,5号线、4号线及福州至长乐机场轨道交通各站点也将陆续开工,福州地铁将迎来6条线均有站点同时建设的高速发展阶段。 [thumb] => [{"url":"\/a\/10001\/201801\/59e15e188e96e9e242f21d66eeb871de.jpeg","id":"67958"}] [url] => /p/13991.html [all_pv] => 677 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 地铁 [1] => 站点 [2] => 全线 [3] => 试运行 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 13973 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/13973.html [wapUrl] => http://m.fztvapp.zohi.tv/p/13973.html [published_timestamp] => 1516240276 [published] => 1516240276 [pv] => 503 [virtual_pv] => 0 [all_pv] => 503 [title] => 地铁4号线一期加快前期工程进度 今年底全线站点启动围挡建设,2022年3月31日前通车试运行 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/42d62413c273eeb4cff1b13ac1442e01.jpeg ) [1] => Array ( [relateid] => 12923 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/12923.html [wapUrl] => http://m.fztvapp.zohi.tv/p/12923.html [published_timestamp] => 1514943217 [published] => 1514943217 [pv] => 488 [virtual_pv] => 0 [all_pv] => 488 [title] => 地铁2号线18个车站主体封顶 计划明年1月底前全线试运行 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/6858bc65e9bee2b8b06328b77919a7b0.jpeg ) [2] => Array ( [relateid] => 7697 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/7697.html [wapUrl] => http://m.fztvapp.zohi.tv/p/7697.html [published_timestamp] => 1510209382 [published] => 1510209382 [pv] => 44 [virtual_pv] => 0 [all_pv] => 44 [title] => 地铁5号线明年9月底前全线开建,2021年9月30日前通车试运行! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201711/ce7e7f1406c57cecad933b1ef7c438e5.jpeg ) [3] => Array ( [relateid] => 11582 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/11582.html [wapUrl] => http://m.fztvapp.zohi.tv/p/11582.html [published_timestamp] => 1513339126 [published] => 1513339126 [pv] => 210 [virtual_pv] => 0 [all_pv] => 210 [title] => 福州地铁5号线三站点开始动工 一期共20个站点 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201712/38044c6baa63ce7d013d94881bff098c.JPG@w720_h540.JPG ) [4] => Array ( [relateid] => 12986 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/12986.html [wapUrl] => http://m.fztvapp.zohi.tv/p/12986.html [published_timestamp] => 1514989105 [published] => 1514989105 [pv] => 459 [virtual_pv] => 0 [all_pv] => 459 [title] => 只剩一年了!福州地铁2号线试运营倒计时,22个站点的进展是…… [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/ced3b9be2bc42430505dd3f47b008f48.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201801/59e15e188e96e9e242f21d66eeb871de.jpeg ) 1

福州地铁建设最新进展!4号线今年全线站点启动围挡建设,23个站点是……

2018-01-18 10:49   福视悦动  

福州地铁建设又有新进展!

一起来看看!

今日,我市召开地铁4号线开工建设动员部署会,围绕市委、市政府既定的一期工程2022年3月31日前通车试运行目标,对涉及的290余项前期工程任务责任清单进行详细部署,并要求今年底前,分批次完成站点(含场段)征迁交地任务,全线所有站点开始围挡建设。4号线一期全长28.4公里,起于橘园站,终于帝封江站,途经金山、鼓楼、晋安、台江、仓山等片区,连接了金山工业集中区、洪山科技园、东街商业中心、东二环泰禾广场综合体、鳌峰金融中心、东部办公区、海峡国际会展中心等主城区重要区域,建成后将与1、2、5号线在城市中心区形成“十字+环”的布局。

4号线一期线路全部采用地下敷设方式,全线共设23座车站,设一段(螺洲车辆段)一场(洪塘停车场),2座主变电站。车辆采用6节B型车编组。

记者了解到,在相关部门的全力配合下,目前4号线土建施工、监理招标已顺利完成,征迁工作陆续启动,交通疏解、施工占道、树木迁移等也陆续报批,各施工、监理单位陆续进场开展前期工程建设。计划首批开工的池边站、化工路站、江边村站、会展中心站及林浦站5个站点已完成绿化树木移植,各站点场地标准化建设同步开展。

在进一步夯实完善目标任务和工期节点的基础上,我市对4号线各项前期工程形成细化责任清单。清单针对4号线每个站点、停车场、车辆段的征迁交地、管线迁改、苗木移植等各项前期建设内容,均详细列出了需完成的工作内容、完成时间、责任单位及责任人。我市将结合一线考察干部机制,强化督导考核,落实奖惩机制,全力保障地铁加快建设。

相关链接:

福州地铁线路的进展情况如何?

预计何时建成?

一起来看看!

地铁1号线(二期)

1号线二期线路长4.95公里,由北至南分设安平站、梁厝站、下洋站及三江口站4个站点,其中梁厝站、下洋站为1、6号线的换乘站,三江口站为1号线的终点站。

地铁1号线(二期)力争2020年国庆前建成试运行。

地铁2号线

地铁2号线线路全长约30.623公里,共设22座车站,沿线为东西方向,途经闽江、乌龙江。

苏洋站—沙堤站—上街站—金屿站—福州大学站—董屿站—厚庭站(8号线)—桔园洲站—洪湾站—金山站(5号线)—金祥站—祥坂站—宁化站—西洋站—南门兜站(1号线)—水部站—紫阳站(3号线)—五里亭站—前屿站(4号线)—上洋站—鼓山站—下岐楼站

地铁2号线计划于明年1月31日前全线试运行。

地铁6号线

6号线起点站会展中心站至终点站机场站,线路全长约40.869km。全线共设车站19座,其中高架站1座,地下站18座;全线设车辆段和停车场各1座。

会展中心站—林浦站—芦岐站—梁厝站—下洋站—营前站—航城站—郑和站—十洋站—鳌头站—鹤上站—沙京站—莲花站—滨海新城站—壶井站—万寿站—尚迁站—漳港站—机场站。

全线计划于2020年12月31日前建成试运行。

地铁5号线

5号线一期20个站点:荆溪新城站、农林大学站、洪塘路站、金林路站、金华路站、金山站、金环路站、浦上大道站、建新南路站、凤山路站、福湾路站、齐安路站、吴山站、当埔路站、欢乐谷站、帝封江站、螺洲镇站、高仕路站、城锦路站、福州南站站

福州市委市政府提出,5号线一期工程的目标要求是2021年9月30日前通车试运行。

6线站点同时建设

2022年形成主体线网

今年,福州地铁1号线二期、2号线及6号线等3条线将继续加紧建设,5号线、4号线及福州至长乐机场轨道交通各站点也将陆续开工,福州地铁将迎来6条线均有站点同时建设的高速发展阶段。

预计从2019年起,福州每年将开通一条地铁线路,直至2022年,福州地铁主体线网将形成。届时,预计近四成市民出行将以搭乘地铁为主,地铁将成为福州城市发展的驱动器。


来源:福州日报