Array ( [id] => 14677 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 湖东东路、通湖支路……福州城区这7条道路春节前陆续通车! [editor] => huangxiaosi [has_thumb] => 1 [created] => 2018-01-29 15:37:24 [createdby] => 10005 [createdip] => 192.168.12.9 [published] => 2018-01-29 15:37:24 [publishedby] => 10005 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 981 [virtual_pv] => 0 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 1517211729 [locker] => 10001 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

福光路(二标段)、湖东东路、通湖支路

……

临近春节,不少市政路桥项目

将迎来“通车季”

7条新改扩建道路

正在保证安全质量的前提下全力收尾

春节前陆续建成通车

为加快打造“畅通福州”,福州高度重视补齐交通出行短板。眼下,首批城区缓堵剩余项目正加速攻坚扫尾,第二批缓堵项目同步快速推进。

湖东东路全面扫尾

湖东东路隧道内隧道内各类装饰装修施工正加快扫尾,预计春节前可全面建成通车。

工人在湖东东路隧道外施工。记者叶义斌 摄

作为我市首条“穿山过河”的地下公路,该项目全长1.9公里,其中隧道长达1.6公里。通车后,湖东东路将成为我市北城区最为便捷的东西向主干道,西可至西湖,东可至鹤林新城、火车东站。湖东东路天水园小区下方、隧道上方将配建200个车位的停车场。目前,一期150个车位已建成,有望在通车时同步启用,二期50个车位在加速配建。

晋安片区将有4条新路陆续建成

红光路、福光路(二标段)、新店车辆基地市政道路(A路、B路)春节前将实现通车或部分通车。

  

红光路改造项目位于福兴投资区内,西起双福路,东至福兴大道,全长658米,宽34米,设双向4车道。目前剩红光苑小学段人行道及非机动车道尚未施工(受电杆迁改影响),预计春节前可完成建设。

  

福光路(二标段)从福新东路交叉口经湖塘路交叉口至化工路交叉口,全长700米,宽40米。因剩余拆迁影响,春节前湖塘路至化工路段主车道可实现临时双向通车。待剩余拆迁完成后将全面完善,新增一条福新东路至化工路的南北向道路,完善福兴投资区路网。

  

五四北新店片区的新店车辆基地的2条市政道路也将在春节前建成,打通坂中村至篁村路的通道、确保地铁车辆基地正常运行,解决坂中、秀峰村村民出行的拥堵问题。该项目位于秀峰路北侧,绕城高速南侧,分为A路和B路。目前,B路已基本完成施工,A路正加快沥青摊铺,人行道也在同步施工。

鼓楼仓山片区路网加快建设

春节前,三坊七巷片区西侧将新增一条过往通道——通湖支路。该道路起于白马北路,终于通湖路,长292米,宽10米。目前,道路已顺利完成路基、人行道等施工,计划2月上旬完成沥青、交通设施标志标线施工,春节前完工通车。届时,通湖支路将成为三坊七巷片区西向交通疏解的新通道。

北园路已完成段。

位于仓山区的省重点项目双湖新城北侧规划路(北园路)也将在春节前迎来阶段性进展。该项目起于已建南二环,向东经湖边村、上湖村,规划盖山路、首山路,终点接南台大道北段,全长3145米,宽48米,为城市主干道。目前该项目仅剩一处福建警察学院征地(约300米)还未完成,春节前除该段外,其余道路可实现临时通车,为片区居民出行提供便利。该项目建成后,能分流南二环、奥体周边道路和首山路的交通压力。


  来源:福州日报

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 目前,道路已顺利完成路基、人行道等施工,计划2月上旬完成沥青、交通设施标志标线施工,春节前完工通车。 [thumb] => [{"url":"\/a\/thumb\/10001\/201801\/439e4ee24cede5f75ab5c1554e3ae248.jpeg@w500_h375.jpeg","id":"72627"}] [url] => /p/14677.html [all_pv] => 981 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 湖东东路 [1] => 春节 [2] => 通车 [3] => 隧道 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 14017 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14017.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14017.html [published_timestamp] => 1516273398 [published] => 1516273398 [pv] => 851 [virtual_pv] => 0 [all_pv] => 851 [title] => 湖东东路下穿隧道春节前通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201801/5b97d511008456c49b6ac8ad7bdd8f9d.JPG@w720_h540.JPG ) [1] => Array ( [relateid] => 2322 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/2322.html [wapUrl] => http://m.fztvapp.zohi.tv/p/2322.html [published_timestamp] => 1505743366 [published] => 1505743366 [pv] => 18 [virtual_pv] => 0 [all_pv] => 18 [title] => 福州城区首条"穿山过河"地下公路 湖东东路有望2018年春节前通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201709/222ea958d0ccaf9769250a7c71fc8a8e.JPG@w640_h480.JPG ) [2] => Array ( [relateid] => 14222 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14222.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14222.html [published_timestamp] => 1516540733 [published] => 1516540733 [pv] => 908 [virtual_pv] => 0 [all_pv] => 908 [title] => 湖东东路春节前建成通车 湖东路与东二环三八路将实现快速连通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/cbb77db3435c91b4fe2e35aa4a5eb889.JPG ) [3] => Array ( [relateid] => 2292 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/2292.html [wapUrl] => http://m.fztvapp.zohi.tv/p/2292.html [published_timestamp] => 1505738878 [published] => 1505738878 [pv] => 301 [virtual_pv] => 0 [all_pv] => 301 [title] => 湖东东路下穿隧道南洞贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201709/22a3a483390e15c217176111385e07fb.JPG@w640_h480.JPG ) [4] => Array ( [relateid] => 13761 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/13761.html [wapUrl] => http://m.fztvapp.zohi.tv/p/13761.html [published_timestamp] => 1515981150 [published] => 1515981150 [pv] => 730 [virtual_pv] => 0 [all_pv] => 730 [title] => 湖东东路两端各设泵房防止积水 隧道内将设探头 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201801/0abe5dd480d2b6018a3b796fc7a9b4eb.png@w357_h267.png ) ) [article_thumb] => http://www.zohi.tv/a/thumb/10001/201801/439e4ee24cede5f75ab5c1554e3ae248.jpeg@w500_h375.jpeg ) 1

湖东东路、通湖支路……福州城区这7条道路春节前陆续通车!

2018-01-29 15:37   福视悦动  

福光路(二标段)、湖东东路、通湖支路

……

临近春节,不少市政路桥项目

将迎来“通车季”

7条新改扩建道路

正在保证安全质量的前提下全力收尾

春节前陆续建成通车

为加快打造“畅通福州”,福州高度重视补齐交通出行短板。眼下,首批城区缓堵剩余项目正加速攻坚扫尾,第二批缓堵项目同步快速推进。

湖东东路全面扫尾

湖东东路隧道内隧道内各类装饰装修施工正加快扫尾,预计春节前可全面建成通车。

工人在湖东东路隧道外施工。记者叶义斌 摄

作为我市首条“穿山过河”的地下公路,该项目全长1.9公里,其中隧道长达1.6公里。通车后,湖东东路将成为我市北城区最为便捷的东西向主干道,西可至西湖,东可至鹤林新城、火车东站。湖东东路天水园小区下方、隧道上方将配建200个车位的停车场。目前,一期150个车位已建成,有望在通车时同步启用,二期50个车位在加速配建。

晋安片区将有4条新路陆续建成

红光路、福光路(二标段)、新店车辆基地市政道路(A路、B路)春节前将实现通车或部分通车。

  

红光路改造项目位于福兴投资区内,西起双福路,东至福兴大道,全长658米,宽34米,设双向4车道。目前剩红光苑小学段人行道及非机动车道尚未施工(受电杆迁改影响),预计春节前可完成建设。

  

福光路(二标段)从福新东路交叉口经湖塘路交叉口至化工路交叉口,全长700米,宽40米。因剩余拆迁影响,春节前湖塘路至化工路段主车道可实现临时双向通车。待剩余拆迁完成后将全面完善,新增一条福新东路至化工路的南北向道路,完善福兴投资区路网。

  

五四北新店片区的新店车辆基地的2条市政道路也将在春节前建成,打通坂中村至篁村路的通道、确保地铁车辆基地正常运行,解决坂中、秀峰村村民出行的拥堵问题。该项目位于秀峰路北侧,绕城高速南侧,分为A路和B路。目前,B路已基本完成施工,A路正加快沥青摊铺,人行道也在同步施工。

鼓楼仓山片区路网加快建设

春节前,三坊七巷片区西侧将新增一条过往通道——通湖支路。该道路起于白马北路,终于通湖路,长292米,宽10米。目前,道路已顺利完成路基、人行道等施工,计划2月上旬完成沥青、交通设施标志标线施工,春节前完工通车。届时,通湖支路将成为三坊七巷片区西向交通疏解的新通道。

北园路已完成段。

位于仓山区的省重点项目双湖新城北侧规划路(北园路)也将在春节前迎来阶段性进展。该项目起于已建南二环,向东经湖边村、上湖村,规划盖山路、首山路,终点接南台大道北段,全长3145米,宽48米,为城市主干道。目前该项目仅剩一处福建警察学院征地(约300米)还未完成,春节前除该段外,其余道路可实现临时通车,为片区居民出行提供便利。该项目建成后,能分流南二环、奥体周边道路和首山路的交通压力。


  来源:福州日报