Array ( [id] => 172272 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州鼓楼小柳路遭遇通行难 市民期待合理围挡施工 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-11-07 11:44:33 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-11-07 11:44:33 [publishedby] => 10056 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 448 [virtual_pv] => 429 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [content] =>

原本双向2车道仅够通行,因为两边工地围挡“包抄”,变为了单车道,以致人车混行、经常拥堵,这几天,鼓楼区小柳路附近居民接连投诉自己的出行难题。“小柳路到底什么时候能恢复畅通?”6日,市民陈先生向媒体反映。

小柳路口一片拥堵 

每天出行路被围成“夹心饼干”

陈先生所指的问题集中在小柳路靠柳河路路口区域。6日下午,记者在现场看到,路口一侧,是围挡施工的“冠坤柒号院”项目工地,路口另一侧,是圈起的绿色围挡,路面张着“大口”,钩机停在中间,并未看到作业人员,围挡上也未张贴施工告示牌。

作为“夹心饼干”的中间地带,小柳路与柳河路交叉口处仅剩一辆小车的通行空间,一旦有小车经过,后面的车辆、行人及非机动车就得排队等候。

陈先生说,小柳路虽是一条看似不起眼的区间支路,却是周边路网中重要的“毛细血管”。除与柳河路相连,可行驶至西二环路、白马路方向外,另一头还和乌山西路相接,周边集结了多家省、市级相关单位,以及小柳小学和多个居民小区,串起市民生活、工作的主要区域。

“这条路平时交通流量就很大,这两天到了早晚高峰期就更是难了,经常排队通行。”采访中,不少市民也有和陈先生一样的感受。“要结合道路的实际通行情况,合理围挡!”记者看到,在福州市12345便民(惠企)服务平台上,也有市民就小柳路口的围挡进行反映。

完工时间尚无法确定

针对市民的诉求,6日,记者采访了围挡相关单位。

据“冠坤柒号院”项目工作人员王女士介绍,按地块规划,靠小柳路与柳河路交叉口位置的大部分小柳路区域,均属项目红线范围。为了桩基安全施工需要,工地自上月底开始在红线范围内陆续扩大围挡,包括小柳路与柳河路交叉口的部分路面。

关于目前路口的通行难问题,王女士说,他们已关注到小柳路的通行重要性,此前已将工地扩大围挡后可能占用路面的情况向鼓楼区相关部门进行沟通协调。

据鼓楼区建设投资管理中心项目监督科工作人员钟先生介绍,“冠坤柒号院”项目对面的围挡,正是考虑到市民车辆通行需要,而牵头组织相关单位先行展开的管线迁改施工。在管线迁改后,会修建通行便道,满足小柳路双向通行需求。

针对围挡施工有无向相关部门报批的问题,钟先生说,小柳路为区属道路,围挡施工已向鼓楼区城管部门报备。

据了解,按福州市建设部门规定,所有工程现场施工围挡均需张贴工程告示牌,包括三方(建设、施工、监理)责任主体、企业名称和项目负责人姓名、电话号码及项目起止日期等,便于接受社会监督和管理。

针对该迁改施工并未张贴工程告示牌、现场无人员施工的情况,钟先生也进行了回应。他说,经了解,现场未施工是因为部分施工内容未按设计图纸进行,相关单位正在协调,未张贴工程告示牌,则考虑其为小型项目,因此未及时张贴,后续将按规范操作。

提及项目完工时间,钟先生表示,因迁改涉及电力、雨污水、燃气、自来水等多家权属单位,内容较为复杂,尚无法给出确定的完工时间。


来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202011\/f65ee02992ff8247720d0a7a797b9e19.jpeg","id":"1884046"}] [url] => /p/172272.html [all_pv] => 448 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 围挡 [1] => 小柳路 [2] => 施工 [3] => 通行 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 91383 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/91383.html [wapUrl] => http://m.fztvapp.zohi.tv/p/91383.html [published_timestamp] => 1559276196 [published] => 1559276196 [pv] => 480 [virtual_pv] => 369 [all_pv] => 480 [title] => 出行请注意!地铁施工,福州这些地方近期将围挡! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/6e5af0d6939b5c70ce88fd3b040137ae.jpeg ) [1] => Array ( [relateid] => 112911 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/112911.html [wapUrl] => http://m.fztvapp.zohi.tv/p/112911.html [published_timestamp] => 1567646399 [published] => 1567646399 [pv] => 290 [virtual_pv] => 454 [all_pv] => 290 [title] => 福州将集中整治围挡和施工场地 国庆前力争焕新貌 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/7fe5f29d67644e00d2818110f4734384.jpeg ) [2] => Array ( [relateid] => 137619 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/137619.html [wapUrl] => http://m.fztvapp.zohi.tv/p/137619.html [published_timestamp] => 1577092424 [published] => 1577092424 [pv] => 99 [virtual_pv] => 432 [all_pv] => 99 [title] => 福州围挡再升级 硬芯环保还美颜 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201912/235d45f60096266839a5f4ec71cfc8eb.jpeg ) [3] => Array ( [relateid] => 120870 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/120870.html [wapUrl] => http://m.fztvapp.zohi.tv/p/120870.html [published_timestamp] => 1570611462 [published] => 1570611462 [pv] => 58 [virtual_pv] => 405 [all_pv] => 58 [title] => 路口围挡全拆除!南门兜变通畅了 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/e7c5ac61e5f333f64219ab70a5dab6b3.jpeg ) [4] => Array ( [relateid] => 118158 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/118158.html [wapUrl] => http://m.fztvapp.zohi.tv/p/118158.html [published_timestamp] => 1569550263 [published] => 1569550263 [pv] => 94 [virtual_pv] => 484 [all_pv] => 94 [title] => 榕城主干道沿线水系围挡国庆前拆除 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/cd24aeac88a201f6d863eb10e8366ad8.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202011/f65ee02992ff8247720d0a7a797b9e19.jpeg ) 1

福州鼓楼小柳路遭遇通行难 市民期待合理围挡施工

2020-11-07 11:44   福视悦动  

原本双向2车道仅够通行,因为两边工地围挡“包抄”,变为了单车道,以致人车混行、经常拥堵,这几天,鼓楼区小柳路附近居民接连投诉自己的出行难题。“小柳路到底什么时候能恢复畅通?”6日,市民陈先生向媒体反映。

小柳路口一片拥堵 

每天出行路被围成“夹心饼干”

陈先生所指的问题集中在小柳路靠柳河路路口区域。6日下午,记者在现场看到,路口一侧,是围挡施工的“冠坤柒号院”项目工地,路口另一侧,是圈起的绿色围挡,路面张着“大口”,钩机停在中间,并未看到作业人员,围挡上也未张贴施工告示牌。

作为“夹心饼干”的中间地带,小柳路与柳河路交叉口处仅剩一辆小车的通行空间,一旦有小车经过,后面的车辆、行人及非机动车就得排队等候。

陈先生说,小柳路虽是一条看似不起眼的区间支路,却是周边路网中重要的“毛细血管”。除与柳河路相连,可行驶至西二环路、白马路方向外,另一头还和乌山西路相接,周边集结了多家省、市级相关单位,以及小柳小学和多个居民小区,串起市民生活、工作的主要区域。

“这条路平时交通流量就很大,这两天到了早晚高峰期就更是难了,经常排队通行。”采访中,不少市民也有和陈先生一样的感受。“要结合道路的实际通行情况,合理围挡!”记者看到,在福州市12345便民(惠企)服务平台上,也有市民就小柳路口的围挡进行反映。

完工时间尚无法确定

针对市民的诉求,6日,记者采访了围挡相关单位。

据“冠坤柒号院”项目工作人员王女士介绍,按地块规划,靠小柳路与柳河路交叉口位置的大部分小柳路区域,均属项目红线范围。为了桩基安全施工需要,工地自上月底开始在红线范围内陆续扩大围挡,包括小柳路与柳河路交叉口的部分路面。

关于目前路口的通行难问题,王女士说,他们已关注到小柳路的通行重要性,此前已将工地扩大围挡后可能占用路面的情况向鼓楼区相关部门进行沟通协调。

据鼓楼区建设投资管理中心项目监督科工作人员钟先生介绍,“冠坤柒号院”项目对面的围挡,正是考虑到市民车辆通行需要,而牵头组织相关单位先行展开的管线迁改施工。在管线迁改后,会修建通行便道,满足小柳路双向通行需求。

针对围挡施工有无向相关部门报批的问题,钟先生说,小柳路为区属道路,围挡施工已向鼓楼区城管部门报备。

据了解,按福州市建设部门规定,所有工程现场施工围挡均需张贴工程告示牌,包括三方(建设、施工、监理)责任主体、企业名称和项目负责人姓名、电话号码及项目起止日期等,便于接受社会监督和管理。

针对该迁改施工并未张贴工程告示牌、现场无人员施工的情况,钟先生也进行了回应。他说,经了解,现场未施工是因为部分施工内容未按设计图纸进行,相关单位正在协调,未张贴工程告示牌,则考虑其为小型项目,因此未及时张贴,后续将按规范操作。

提及项目完工时间,钟先生表示,因迁改涉及电力、雨污水、燃气、自来水等多家权属单位,内容较为复杂,尚无法给出确定的完工时间。


来源:福州新闻网
编辑:强婕宁 责编:林真贞