Array ( [id] => 22204 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 金港河主河道有望9月贯通 将与两条内河“接头” [editor] => 郑林钰 [has_thumb] => 1 [created] => 2018-05-24 11:37:11 [createdby] => 10030 [createdip] => 192.168.12.19 [published] => 2018-05-24 11:37:11 [publishedby] => 10030 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 984 [virtual_pv] => 418 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为金山奥体片区的一条重要河道,金港河在治理之初就受到广泛关注。在去年底顺利摘下“黑帽”基础上,为实现这条断头河的全域治理,今年以来,河道贯通加快推进。记者23日随市领导督导检查城区水系治理进展时了解到,规划的2.2公里金港河主河道开挖进展顺利,仅剩约120米河段待挖。预计9月底,该河道主体就能实现贯通,和洋洽河、台屿河“三水”相连,让河水动起来。

最后120米河段计划下月开挖

23日上午,记者来到摩卡生活馆旁的金港河施工现场。围挡内,一台大型桩机正在作业。“这是河道开挖前的基础工作,打支护桩。”市建委驻点工作组相关负责人告诉记者。

据了解,金港河原有河道仅580米,打通断头、连通水系是消除黑臭的根本。要实现和洋洽河、台屿河水系连通,必须开挖新河道。经前期奋力攻坚,在取得居民的理解支持后,和园小区段、景园小区段、融信西班牙小区段的新河道已完成开挖,仅剩最后摩卡生活馆旁的约120米河段待挖。

“为早日贯通河道,我们现在是‘小雨不停工,大雨间断干,无雨全力干,夜间挑灯干’。”该负责人介绍,因开挖段离居民区近,原驳岸支护结构施工噪声较大,为最大限度保证安全,让施工不扰民,他们引进新的打桩机,为开挖段上双排“防护”。新支护工艺不仅低噪音、无振动、无泥浆污染,施工效率还很高,让工期缩短一半。

按目前进度,下月中旬该河段支护就能全部完成,达到养护周期后,全面转入开挖阶段,最终形成15米宽的新河道,跨过榕港路、金港路,与金港河金港公园段、和园小区段、景园小区段及洋洽河串联。

“最后的‘堡垒’攻克后,预计9月底就能实现2.2公里河道主体贯通,使3条河的河水实现交换,让水清起来、多起来、动起来。”该负责人说。

新建生态驳岸实现缓坡入水

在开挖河道连通水系的基础上,金港河采取生态修复等方式,实现生态治理。

“除了不具备放坡条件的融信西班牙及摩卡生活馆河段,其余700多米河段都是敞口式河道。”该河道相关技术负责人告诉记者,按《福州市内河驳岸标准样式导则》要求,考虑到融信西班牙及摩卡生活馆用地情况,流经上述两个小区的河道宽度保证15米,沿河布设直立式驳岸,剩余具备条件的河道宽度为20米至30米,均采用最为生态的自然缓坡入水型驳岸,实现缓坡入水。为最大限度实现亲水功能,自然放坡驳岸不设防护栏杆,通过植物防护及预留安全距离等措施,实现临河安全防护。

记者了解到,为早日实现水清河畅,金港河治理分六大区域同步展开,截污系统已基本形成。金港河万达段、和园小区段、景园小区段,还在进行生态修复,通过种植水生植物等手段给水体增氧,让河水动起来。

来源:福州日报
编辑:郑林钰   责编:余玉金

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 该河道相关技术负责人告诉记者,按《福州市内河驳岸标准样式导则》要求,考虑到融信西班牙及摩卡生活馆用地情况,流经上述两个小区的河道宽度保证15米,沿河布设直立式驳岸,剩余具备条件的河道宽度为20米至30米,均采用最为生态的自然缓坡入水型驳岸,实现缓坡入水。 [thumb] => [{"url":"\/a\/10001\/201805\/c059fbdb922e1e2662e48e7910bfb760.jpeg","id":"139728"}] [url] => /p/22204.html [all_pv] => 984 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 金港河 [1] => 河道 [2] => 开挖 [3] => 驳岸 ) ) [menu] => [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 22188 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22188.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22188.html [published_timestamp] => 1527120306 [published] => 1527120306 [pv] => 448 [virtual_pv] => 473 [all_pv] => 448 [title] => 金港河主河道有望9月贯通 将与两条内河“接头” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/d4298b08facfe9c53bd8133e2043039b.jpeg ) [1] => Array ( [relateid] => 22186 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22186.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22186.html [published_timestamp] => 1527119350 [published] => 1527119350 [pv] => 506 [virtual_pv] => 402 [all_pv] => 506 [title] => 福州:重修能 有内美 高素质 高颜值 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/4b277af06198d5b69d95c70b8c2fc114.jpeg ) [2] => Array ( [relateid] => 22168 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22168.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22168.html [published_timestamp] => 1527073806 [published] => 1527073806 [pv] => 47 [virtual_pv] => 368 [all_pv] => 47 [title] => 因地制宜"求创新" 盾构施工"埋入"超大截污管  [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/f413f6be4ab2298bfa98476a1b78ebc9.JPG ) [3] => Array ( [relateid] => 22166 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22166.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22166.html [published_timestamp] => 1527073602 [published] => 1527073602 [pv] => 431 [virtual_pv] => 422 [all_pv] => 431 [title] => 旧西客站及周边旧屋区改造项目征迁工作进入尾声 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/0602c44d382620000331cd39ee434d00.JPG ) [4] => Array ( [relateid] => 22155 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22155.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22155.html [published_timestamp] => 1527064731 [published] => 1527064731 [pv] => 938 [virtual_pv] => 370 [all_pv] => 938 [title] => 高新区轮船港黑臭水体治理开始了,3个星期消除臭味! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/2f09e0a6443c07d7b6022d6f382fb2a9.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201805/c059fbdb922e1e2662e48e7910bfb760.jpeg ) 1

金港河主河道有望9月贯通 将与两条内河“接头”

2018-05-24 11:37   福视悦动  

作为金山奥体片区的一条重要河道,金港河在治理之初就受到广泛关注。在去年底顺利摘下“黑帽”基础上,为实现这条断头河的全域治理,今年以来,河道贯通加快推进。记者23日随市领导督导检查城区水系治理进展时了解到,规划的2.2公里金港河主河道开挖进展顺利,仅剩约120米河段待挖。预计9月底,该河道主体就能实现贯通,和洋洽河、台屿河“三水”相连,让河水动起来。

最后120米河段计划下月开挖

23日上午,记者来到摩卡生活馆旁的金港河施工现场。围挡内,一台大型桩机正在作业。“这是河道开挖前的基础工作,打支护桩。”市建委驻点工作组相关负责人告诉记者。

据了解,金港河原有河道仅580米,打通断头、连通水系是消除黑臭的根本。要实现和洋洽河、台屿河水系连通,必须开挖新河道。经前期奋力攻坚,在取得居民的理解支持后,和园小区段、景园小区段、融信西班牙小区段的新河道已完成开挖,仅剩最后摩卡生活馆旁的约120米河段待挖。

“为早日贯通河道,我们现在是‘小雨不停工,大雨间断干,无雨全力干,夜间挑灯干’。”该负责人介绍,因开挖段离居民区近,原驳岸支护结构施工噪声较大,为最大限度保证安全,让施工不扰民,他们引进新的打桩机,为开挖段上双排“防护”。新支护工艺不仅低噪音、无振动、无泥浆污染,施工效率还很高,让工期缩短一半。

按目前进度,下月中旬该河段支护就能全部完成,达到养护周期后,全面转入开挖阶段,最终形成15米宽的新河道,跨过榕港路、金港路,与金港河金港公园段、和园小区段、景园小区段及洋洽河串联。

“最后的‘堡垒’攻克后,预计9月底就能实现2.2公里河道主体贯通,使3条河的河水实现交换,让水清起来、多起来、动起来。”该负责人说。

新建生态驳岸实现缓坡入水

在开挖河道连通水系的基础上,金港河采取生态修复等方式,实现生态治理。

“除了不具备放坡条件的融信西班牙及摩卡生活馆河段,其余700多米河段都是敞口式河道。”该河道相关技术负责人告诉记者,按《福州市内河驳岸标准样式导则》要求,考虑到融信西班牙及摩卡生活馆用地情况,流经上述两个小区的河道宽度保证15米,沿河布设直立式驳岸,剩余具备条件的河道宽度为20米至30米,均采用最为生态的自然缓坡入水型驳岸,实现缓坡入水。为最大限度实现亲水功能,自然放坡驳岸不设防护栏杆,通过植物防护及预留安全距离等措施,实现临河安全防护。

记者了解到,为早日实现水清河畅,金港河治理分六大区域同步展开,截污系统已基本形成。金港河万达段、和园小区段、景园小区段,还在进行生态修复,通过种植水生植物等手段给水体增氧,让河水动起来。

来源:福州日报