Array ( [id] => 22726 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 观风亭路至华林路段断头路将打通 预计8月底通车 [editor] => 彭季红 [has_thumb] => 1 [created] => 2018-05-31 20:59:33 [createdby] => 10029 [createdip] => 192.168.12.19 [published] => 2018-05-31 20:59:33 [publishedby] => 10029 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1528 [virtual_pv] => 391 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 3 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>


记者从市建委了解到,正在施工的观风亭路(冶山路至华林路)段道路工程建设进展顺利,施工方将把现有观风亭路向北"拉长"400多米,打通原先的"断头"路。项目力争8月底建成通车。

记者在观风亭路(冶山路至华林路)段看到,现场机器轰鸣,一派繁忙。观风亭路新建段从冶山路延伸至华林路,全长408米,宽28米,设双向2车道。据了解,项目与鼓台水系中重要的内河屏东河平行,市建委及相关部门多方协调,将河道治理与道路建设合二为一,并加大人力物力投入,力争8月底建成通车。

观风亭路(冶山路至华林路)段道路工程负责人林昊:我们现在是全线河道在施工,为了赶在上下游同步通水,现在主要精力在做驳岸改造,靠近冶山路这一头地基淤泥层比较厚,我们根据设计做了拉森钢板桩,在基底进行了软基处理。

观风亭路(冶山路至华林路)段工程位于市中心,交通流量大,周边居民区多。因此,施工方在合理安排施工时间的同时,采取多项措施防尘减噪,减少对周边居民的影响。

观风亭路(冶山路至华林路)段道路工程负责人林昊:一个我们尽量安排在白天施工,夜间我们安排噪音比较小的施工,有些施工难免要在夜间施工,一个我们办理了夜间施工许可证,还有我们走访了居民做了一些解释工作,现在工程做到这个程度跟周边居民的理解是分不开的。

来源:福州新闻
编辑:彭季红   责编:黄晓思

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 观风亭路至华林路段断头路将打通 预计8月底通车 [thumb] => [{"url":"\/a\/10001\/201805\/d3debd43298324eb71402ca6c81cfe1c.JPG","id":"147027"}] [url] => /p/22726.html [all_pv] => 1528 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 观风 [1] => 华林路 [2] => 山路 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 22692 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22692.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22692.html [published_timestamp] => 1527748684 [published] => 1527748684 [pv] => 774 [virtual_pv] => 446 [all_pv] => 774 [title] => 最新!地铁2号线建成这样了!离通车更近了! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/f77d964f49d5e51d7494e207d70cee88.jpeg ) [1] => Array ( [relateid] => 22673 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22673.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22673.html [published_timestamp] => 1527736521 [published] => 1527736521 [pv] => 940 [virtual_pv] => 403 [all_pv] => 940 [title] => 融媒体视点|鼓岭国家级旅游度假区揭牌 成为我省唯一国家级旅游度假区 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/6abb824ef52ed634c44007c909f82835.JPG ) [2] => Array ( [relateid] => 22626 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22626.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22626.html [published_timestamp] => 1527662847 [published] => 1527662847 [pv] => 646 [virtual_pv] => 409 [all_pv] => 646 [title] => 鼓楼今年内启动17个项目征迁 三年旧改一年实施 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/72114ee83e70b6b87dd4f8ebfd069f2f.jpeg ) [3] => Array ( [relateid] => 22625 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22625.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22625.html [published_timestamp] => 1527662605 [published] => 1527662605 [pv] => 1220 [virtual_pv] => 392 [all_pv] => 1220 [title] => 福州雨夜治水战犹酣 一线建设者挥洒干事创业激情 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/3332c40aa7a2fda21e8e5e0e7e63ed0c.jpeg ) [4] => Array ( [relateid] => 22598 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/22598.html [wapUrl] => http://m.fztvapp.zohi.tv/p/22598.html [published_timestamp] => 1527642063 [published] => 1527642063 [pv] => 1146 [virtual_pv] => 448 [all_pv] => 1146 [title] => 福州:雨夜治水战犹酣 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/325229d585e8ade1ec72162a768efc95.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201805/d3debd43298324eb71402ca6c81cfe1c.JPG ) 1

观风亭路至华林路段断头路将打通 预计8月底通车

2018-05-31 20:59   福州新闻  


记者从市建委了解到,正在施工的观风亭路(冶山路至华林路)段道路工程建设进展顺利,施工方将把现有观风亭路向北"拉长"400多米,打通原先的"断头"路。项目力争8月底建成通车。

记者在观风亭路(冶山路至华林路)段看到,现场机器轰鸣,一派繁忙。观风亭路新建段从冶山路延伸至华林路,全长408米,宽28米,设双向2车道。据了解,项目与鼓台水系中重要的内河屏东河平行,市建委及相关部门多方协调,将河道治理与道路建设合二为一,并加大人力物力投入,力争8月底建成通车。

观风亭路(冶山路至华林路)段道路工程负责人林昊:我们现在是全线河道在施工,为了赶在上下游同步通水,现在主要精力在做驳岸改造,靠近冶山路这一头地基淤泥层比较厚,我们根据设计做了拉森钢板桩,在基底进行了软基处理。

观风亭路(冶山路至华林路)段工程位于市中心,交通流量大,周边居民区多。因此,施工方在合理安排施工时间的同时,采取多项措施防尘减噪,减少对周边居民的影响。

观风亭路(冶山路至华林路)段道路工程负责人林昊:一个我们尽量安排在白天施工,夜间我们安排噪音比较小的施工,有些施工难免要在夜间施工,一个我们办理了夜间施工许可证,还有我们走访了居民做了一些解释工作,现在工程做到这个程度跟周边居民的理解是分不开的。

来源:福州新闻
编辑:彭季红   责编:黄晓思