Array ( [id] => 26056 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 农村生活污水治理交出半年“成绩单” 闽清连江晋安居前三 [editor] => 郑林钰 [has_thumb] => 1 [created] => 2018-07-15 08:01:37 [createdby] => 10030 [createdip] => 112.5.236.74 [published] => 2018-07-15 08:01:37 [publishedby] => 10030 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1214 [virtual_pv] => 438 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

近日,我市对10个县(市)区和高新区上半年农村生活污水治理工作开展市级督查考评。经综合考评,上半年农村污水治理工作前3名依次为:闽清县、连江县、晋安区。

“按省、市下达的年度任务要求,考评小组逐条对照《福州市2018年农村生活污水治理考核评分标准》,对10个县(市)区和高新区相关项目深入抽检,逐项考核打分。”市建委相关负责人告诉记者,上半年各县(市)区农村生活污水治理各项工作全面启动,并取得阶段性成效。

据了解,9个列入省为民办实事的乡镇污水处理设施项目均已建设完成,除闽侯县尚干镇污水管网正加快接驳至青口新区污水处理厂外,其余均投入试运行。乡镇生活污水处理设施提升改造项目中,闽清县下祝乡项目已提前完成并投入试运行。

截至6月底,乡镇污水处理设施配套管网建设,174公里的任务已完成99.03公里,完成率56.91%;三格化粪池新建改造,57596户(含2017年提前完成的6538户)新建改造的任务已完工35790户,完工率62.14%,其中仓山区完工率达100%。

688个行政村污水治理按“一村一策”要求生成具体整治项目清单。截至目前,已有132个村完成治理,491个村正在治理。

今年,新的PPP项目持续实施。闽清县城区污水管网、梅溪、白金污水处理厂配套管网、泵站及乡镇污水处理站(含配套干管)委托运营项目已落地;晋安区北峰山区3个乡镇15个村集中式污水处理设施建设、运营PPP项目正在资格预审招标阶段。

中央和省级环保督察涉及的长乐区金峰镇莲柄港(陈塘港)河沿岸污水直排问题也在加快整改,目前主河道一期截污工程7.07公里已完成,潭头污水厂已建成配套主干管28.35公里,莲柄港流域水质有明显好转。

此外,针对省环保督察及省住建厅通报的“部分乡镇污水处理设施配套管网建设滞后、设施未正常运行”问题,福清市、闽侯县等各县(市)区已启动相关整改工作,确保按期完成。

“考评发现的问题,最迟要在11月底完成整改。”市建委相关负责人说,针对部分污水处理设施建设不规范、已建设施未正常运行等问题,要选取适宜的治理技术路线,确保按期保质保量完成任务,同时建立长效运行机制,完善第三方治理体系。

来源:福州日报
编辑:严玮瑫   责编:范晓婕

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 市建委相关负责人说,针对部分污水处理设施建设不规范、已建设施未正常运行等问题,要选取适宜的治理技术路线,确保按期保质保量完成任务,同时建立长效运行机制,完善第三方治理体系 [thumb] => [{"url":"\/a\/10001\/201807\/d458a1c232e31d680346e769431a10dc.jpeg","id":"192028"}] [url] => /p/26056.html [all_pv] => 1214 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 污水 [1] => 污水处理 [2] => 治理 [3] => 乡镇 [4] => 设施 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 26038 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26038.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26038.html [published_timestamp] => 1531572883 [published] => 1531572883 [pv] => 841 [virtual_pv] => 385 [all_pv] => 841 [title] => 流花溪景观提升月底完成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/3c5632ccc98df5aacdc6c0fbfd8e5d7d.JPG ) [1] => Array ( [relateid] => 26035 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26035.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26035.html [published_timestamp] => 1531572333 [published] => 1531572333 [pv] => 1105 [virtual_pv] => 451 [all_pv] => 1105 [title] => 市委常委会召开会议 传达学习贯彻习近平总书记重要讲话和重要指示精神 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/1cb1d1a273b03c9b8232d29b07583177.JPG ) [2] => Array ( [relateid] => 26034 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26034.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26034.html [published_timestamp] => 1531572168 [published] => 1531572168 [pv] => 1080 [virtual_pv] => 446 [all_pv] => 1080 [title] => 省调研督导组来榕调研督导上半年综治(平安建设)工作 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/5b66467c9fd46472b117c92f789fad83.JPG ) [3] => Array ( [relateid] => 26032 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26032.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26032.html [published_timestamp] => 1531571750 [published] => 1531571750 [pv] => 1502 [virtual_pv] => 389 [all_pv] => 1502 [title] => 马尾琅岐:风光互补照明系统显优势 台风天照亮出行路 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/4078d3caa9ee2c03c667b43abd3a05ea.JPG ) [4] => Array ( [relateid] => 25997 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/25997.html [wapUrl] => http://m.fztvapp.zohi.tv/p/25997.html [published_timestamp] => 1531548702 [published] => 1531548702 [pv] => 745 [virtual_pv] => 373 [all_pv] => 745 [title] => 福州医保局:发现骗取医保线索可举报 将立即查办 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/9f8111b3ad55a4d19452530a6497c460.jpg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201807/d458a1c232e31d680346e769431a10dc.jpeg ) 1

农村生活污水治理交出半年“成绩单” 闽清连江晋安居前三

2018-07-15 08:01   福视悦动  

近日,我市对10个县(市)区和高新区上半年农村生活污水治理工作开展市级督查考评。经综合考评,上半年农村污水治理工作前3名依次为:闽清县、连江县、晋安区。

“按省、市下达的年度任务要求,考评小组逐条对照《福州市2018年农村生活污水治理考核评分标准》,对10个县(市)区和高新区相关项目深入抽检,逐项考核打分。”市建委相关负责人告诉记者,上半年各县(市)区农村生活污水治理各项工作全面启动,并取得阶段性成效。

据了解,9个列入省为民办实事的乡镇污水处理设施项目均已建设完成,除闽侯县尚干镇污水管网正加快接驳至青口新区污水处理厂外,其余均投入试运行。乡镇生活污水处理设施提升改造项目中,闽清县下祝乡项目已提前完成并投入试运行。

截至6月底,乡镇污水处理设施配套管网建设,174公里的任务已完成99.03公里,完成率56.91%;三格化粪池新建改造,57596户(含2017年提前完成的6538户)新建改造的任务已完工35790户,完工率62.14%,其中仓山区完工率达100%。

688个行政村污水治理按“一村一策”要求生成具体整治项目清单。截至目前,已有132个村完成治理,491个村正在治理。

今年,新的PPP项目持续实施。闽清县城区污水管网、梅溪、白金污水处理厂配套管网、泵站及乡镇污水处理站(含配套干管)委托运营项目已落地;晋安区北峰山区3个乡镇15个村集中式污水处理设施建设、运营PPP项目正在资格预审招标阶段。

中央和省级环保督察涉及的长乐区金峰镇莲柄港(陈塘港)河沿岸污水直排问题也在加快整改,目前主河道一期截污工程7.07公里已完成,潭头污水厂已建成配套主干管28.35公里,莲柄港流域水质有明显好转。

此外,针对省环保督察及省住建厅通报的“部分乡镇污水处理设施配套管网建设滞后、设施未正常运行”问题,福清市、闽侯县等各县(市)区已启动相关整改工作,确保按期完成。

“考评发现的问题,最迟要在11月底完成整改。”市建委相关负责人说,针对部分污水处理设施建设不规范、已建设施未正常运行等问题,要选取适宜的治理技术路线,确保按期保质保量完成任务,同时建立长效运行机制,完善第三方治理体系。