Array ( [id] => 32967 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 鳌峰洲大桥新增匝道 力争明年春节前通车 [editor] => (二审)林昱星 [has_thumb] => 1 [created] => 2018-09-09 19:12:10 [createdby] => 10006 [createdip] => 192.168.12.200 [published] => 2018-09-09 19:12:10 [publishedby] => 10006 [modified] => 2018-09-09 19:41:18 [modifiedby] => 10019 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1787 [virtual_pv] => 388 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

鳌峰洲大桥由于设计较早,缺少与周边相连的匝道,到了高峰期,南桥头区域经常出现拥堵的现象。作为福州第二批缓堵项目的鳌峰洲大桥南桥头改造工程于今年6月份启动,目前工程进展如何我们一起去看看。

上午,记者从鳌峰洲大桥南桥头施工现场了解到,港头外路的绿化移植、管线迁改等工作已经完成。总共70根桩基目前已经完成了46根,新增的人行天桥也在施工中。


采访身份 鳌峰洲大桥南桥头改造工程负责人 林捷:目前桥梁已经进入上部结构施工,北侧的人行桥已经完成钢构的吊装,开始进行附属施工,现浇梁部分我们进行鳌峰大桥的拼宽段施工。

据施工方介绍,由于鳌峰洲大桥是座老桥,桥体边缘部分厚度不足。他们在新建匝道同时,也将对匝道与原先桥体的连接部分进行加固。

鳌峰洲大桥南桥头改造工程负责人 林捷:在设计上经过省交科院的设计论证,重点对桥梁拼宽段进行加固施工,对翼缘板厚度不足的部分进行切除,太薄了切掉,换成新的桥梁伸进去。


据了解,这次鳌峰大桥南桥头的改造重点就是新建匝道,让桥上车辆可以快速进入南江滨西大道。同时,南江滨西大道的车辆也能快速驶上鳌峰大桥。还将新增四座供行人和非机动车通行的天桥。整个鳌峰大桥南桥头改造工程,将力争在2019年春节前建成。

鳌峰洲大桥南桥头改造工程负责人 林捷:在十月份我们会把人行桥钢构的部分都完成,大坪路至朝阳路EF辅路也会完成,计划是在年底完成现浇梁的施工,明年春节前我们整个项目全部建成通车。

来源:新闻110
编辑:林昱星  责编:郑雪峰

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 鳌峰洲大桥由于设计较早,缺少与周边相连的匝道,到了高峰期,南桥头区域经常出现拥堵的现象。 [thumb] => [{"url":"\/a\/thumb\/10001\/201809\/c3aa1bf0317a2bbb2cfdab4cfdd86beb.jpeg@w553_h415.jpeg","id":"251589"}] [url] => /p/32967.html [all_pv] => 1787 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 新闻110 ) [2] => Array ( [0] => 鳌峰 [1] => 大桥 [2] => 桥头 [3] => 匝道 [4] => 施工 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 32913 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32913.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32913.html [published_timestamp] => 1536465067 [published] => 1536465067 [pv] => 956 [virtual_pv] => 467 [all_pv] => 956 [title] => 福州这地方将建一处约230亩的花海公园!这条自行车道示范段已全线贯通! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/40dfcec21edcc0d546a0ef4e2c222c6a.jpeg ) [1] => Array ( [relateid] => 32907 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32907.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32907.html [published_timestamp] => 1536464981 [published] => 1536464981 [pv] => 831 [virtual_pv] => 409 [all_pv] => 831 [title] => 连江一党员涉恶 被依法依纪处理 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201809/c45aed9b8771cf3bc2756782d062cd71.jpg@w303_h227.jpg ) [2] => Array ( [relateid] => 32904 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32904.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32904.html [published_timestamp] => 1536463151 [published] => 1536463151 [pv] => 877 [virtual_pv] => 479 [all_pv] => 877 [title] => 观风亭道路工程有望下月通车 将与观风亭街相连 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/2bbdc44438b3f13f47754df0aab479b4.png ) [3] => Array ( [relateid] => 32811 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32811.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32811.html [published_timestamp] => 1536406140 [published] => 1536406140 [pv] => 206 [virtual_pv] => 423 [all_pv] => 206 [title] => 福州版"西堤春晓"景点开放 古朴典雅美不胜收 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/673c64fdf14dbba639f53bc97bfa98fc.png ) [4] => Array ( [relateid] => 32604 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32604.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32604.html [published_timestamp] => 1536369458 [published] => 1536369458 [pv] => 952 [virtual_pv] => 439 [all_pv] => 952 [title] => 12日至19日凌晨 福州机场高速公路部分路段交通管制 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201809/f9fe92c05d1cbaab6e210e283420ba3e.jpg@w441_h331.jpg ) ) [article_thumb] => http://www.zohi.tv/a/thumb/10001/201809/c3aa1bf0317a2bbb2cfdab4cfdd86beb.jpeg@w553_h415.jpeg ) 1

鳌峰洲大桥新增匝道 力争明年春节前通车

2018-09-09 19:12   新闻110  

鳌峰洲大桥由于设计较早,缺少与周边相连的匝道,到了高峰期,南桥头区域经常出现拥堵的现象。作为福州第二批缓堵项目的鳌峰洲大桥南桥头改造工程于今年6月份启动,目前工程进展如何我们一起去看看。

上午,记者从鳌峰洲大桥南桥头施工现场了解到,港头外路的绿化移植、管线迁改等工作已经完成。总共70根桩基目前已经完成了46根,新增的人行天桥也在施工中。


采访身份 鳌峰洲大桥南桥头改造工程负责人 林捷:目前桥梁已经进入上部结构施工,北侧的人行桥已经完成钢构的吊装,开始进行附属施工,现浇梁部分我们进行鳌峰大桥的拼宽段施工。

据施工方介绍,由于鳌峰洲大桥是座老桥,桥体边缘部分厚度不足。他们在新建匝道同时,也将对匝道与原先桥体的连接部分进行加固。

鳌峰洲大桥南桥头改造工程负责人 林捷:在设计上经过省交科院的设计论证,重点对桥梁拼宽段进行加固施工,对翼缘板厚度不足的部分进行切除,太薄了切掉,换成新的桥梁伸进去。


据了解,这次鳌峰大桥南桥头的改造重点就是新建匝道,让桥上车辆可以快速进入南江滨西大道。同时,南江滨西大道的车辆也能快速驶上鳌峰大桥。还将新增四座供行人和非机动车通行的天桥。整个鳌峰大桥南桥头改造工程,将力争在2019年春节前建成。

鳌峰洲大桥南桥头改造工程负责人 林捷:在十月份我们会把人行桥钢构的部分都完成,大坪路至朝阳路EF辅路也会完成,计划是在年底完成现浇梁的施工,明年春节前我们整个项目全部建成通车。

来源:新闻110