Array ( [id] => 34878 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州城区排水管网改扩建工程“五路并进” [editor] => 林佳佳 [has_thumb] => 1 [created] => 2018-09-17 10:36:32 [createdby] => 10071 [createdip] => 192.168.12.13 [published] => 2018-09-17 10:36:32 [publishedby] => 10071 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 966 [virtual_pv] => 455 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

我市城区水系“卷地毯”施工持续推进,已有14条河道开放。为保持治水成效,让地下排水管网健康运行、污水处理率稳步升级,按市委、市政府部署,城区全长2500公里的排水管网改扩建工程也同步推进。记者从市建委获悉,目前,五大片区项目包已全面进场施工,完成383.37公里的管网修复。

据市建委相关负责人介绍,依托先期排查情况,四城区排水管网修复工程今年4月起开展,共分洋里、祥坂、金山、连坂、浮村5个片区。修复工作涉及排水户排查建档、源头纳污及市政排水管网修复改造三大块内容。据了解,排查建档方面,目前已完成14951户,其中包括重点排水户1030户。源头纳污方面,根据排查出的雨污混接情况进行设计,5个片区均已开展部分路段的源头改造工作,目前已完成10.547公里。管网修复方面,截至目前,5家建设单位已完成383.37公里的修复工作。

按计划,今年底前,四城区将完成1000公里雨污水管网修复、改造,完成半数以上生活小区、企事业单位、沿街店面等排水户接驳口改造;2019年12月31日前,基本完成四城区雨污水管网修复改造,为实现水清河畅和城市内在品质提升助力。

来源:福州新闻网
编辑:林佳佳  责编:卢明铭

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 我市城区水系“卷地毯”施工持续推进,已有14条河道开放。 [thumb] => [{"url":"\/a\/10001\/201809\/5f143c2e408203298342716bbbf7cc67.jpeg","id":"268563"}] [url] => /p/34878.html [all_pv] => 966 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 修复 [1] => 管网 [2] => 城区 [3] => 排查 [4] => 完成 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 34860 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/34860.html [wapUrl] => http://m.fztvapp.zohi.tv/p/34860.html [published_timestamp] => 1537151245 [published] => 1537151245 [pv] => 801 [virtual_pv] => 397 [all_pv] => 801 [title] => 福建00后女生手绘城市图:1米长卷筹备3年 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/7e454bde7f465b60792d3aadb5218d2a.gif ) [1] => Array ( [relateid] => 34851 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/34851.html [wapUrl] => http://m.fztvapp.zohi.tv/p/34851.html [published_timestamp] => 1537150004 [published] => 1537150004 [pv] => 755 [virtual_pv] => 486 [all_pv] => 755 [title] => 福州市交通执法支队回应网约车等热点问题 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/cab230d9e2cc83ef9a4d4a1693b203a1.jpeg ) [2] => Array ( [relateid] => 34848 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/34848.html [wapUrl] => http://m.fztvapp.zohi.tv/p/34848.html [published_timestamp] => 1537149664 [published] => 1537149664 [pv] => 1156 [virtual_pv] => 405 [all_pv] => 1156 [title] => 融媒体视点丨《王者荣耀》健康系统全面升级 怎么玩才健康 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201809/0cbc7983c207977810f04f58eb828e06.JPG@w720_h540.JPG ) [3] => Array ( [relateid] => 34833 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/34833.html [wapUrl] => http://m.fztvapp.zohi.tv/p/34833.html [published_timestamp] => 1537148373 [published] => 1537148373 [pv] => 971 [virtual_pv] => 388 [all_pv] => 971 [title] => 福州首周受理共有产权房申请超200件 这些问题要注意 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/b0454f2b1537c5d882b4e5fc11fa55a1.jpeg ) [4] => Array ( [relateid] => 34830 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/34830.html [wapUrl] => http://m.fztvapp.zohi.tv/p/34830.html [published_timestamp] => 1537147657 [published] => 1537147657 [pv] => 1487 [virtual_pv] => 454 [all_pv] => 1487 [title] => 鼓楼全力打造最优“人才生态圈” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/64209b6476529b75b673a3c5e0dc6a8c.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201809/5f143c2e408203298342716bbbf7cc67.jpeg ) 1

福州城区排水管网改扩建工程“五路并进”

2018-09-17 10:36   福视悦动  

我市城区水系“卷地毯”施工持续推进,已有14条河道开放。为保持治水成效,让地下排水管网健康运行、污水处理率稳步升级,按市委、市政府部署,城区全长2500公里的排水管网改扩建工程也同步推进。记者从市建委获悉,目前,五大片区项目包已全面进场施工,完成383.37公里的管网修复。

据市建委相关负责人介绍,依托先期排查情况,四城区排水管网修复工程今年4月起开展,共分洋里、祥坂、金山、连坂、浮村5个片区。修复工作涉及排水户排查建档、源头纳污及市政排水管网修复改造三大块内容。据了解,排查建档方面,目前已完成14951户,其中包括重点排水户1030户。源头纳污方面,根据排查出的雨污混接情况进行设计,5个片区均已开展部分路段的源头改造工作,目前已完成10.547公里。管网修复方面,截至目前,5家建设单位已完成383.37公里的修复工作。

按计划,今年底前,四城区将完成1000公里雨污水管网修复、改造,完成半数以上生活小区、企事业单位、沿街店面等排水户接驳口改造;2019年12月31日前,基本完成四城区雨污水管网修复改造,为实现水清河畅和城市内在品质提升助力。

来源:福州新闻网
编辑:林佳佳  责编:卢明铭