Array ( [id] => 39126 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 节日里的坚守:东南快速通道万新路复线工程采用新技术配建综合管廊 [editor] => 钟月迎 [has_thumb] => 1 [created] => 2018-10-07 19:34:09 [createdby] => 10068 [createdip] => 192.168.12.11 [published] => 2018-10-07 19:34:09 [publishedby] => 10068 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 2578 [virtual_pv] => 378 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 83 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

国庆黄金周,许多人在景区享受假日时光时,有一群人还坚守一线,铆足干劲,全力推进缓解交通拥堵、水系综合治理、老旧小区整治等重大项目、重点工程建设。他们将"黄金周"变成"攻坚周",为城市建设添砖加瓦,展现出良好的干事创业精气神。

在福州东南快速通道万新路复线段,为保证进度,项目国庆假期不停工,采用新技术新理念,全力推进综合管廊及道路路基建设。

在位于长乐漳港的万新路复线段施工现场,工人们正在进行管廊钢筋作业。该综合管廊全长约5公里,将在地下修一条集电力、通信、给排水、燃气等各类管线于一体的隧道。由于项目位于海边,地下水丰富,地质条件复杂,因此施工方采用井点降水的方式将管廊中的海水排空,同时加大人员设备投入,使工期比预计缩短了一半。目前,该建设技术正在申请研究课题,争创地方标准。

中交二航局万新路A2标段项目副经理任芮林:通过井点降水将整个地面水位降到我们的管廊底标高以下,保持整个施工过程中是干的施工环境,从而达到钢筋避免被海水浸泡的效果。

福州新区项目建设管理办公室副总监吴强:正常的像我们这么大的一个管廊(钢筋部分),双仓室的,我们要三天正常的工序,现在是基本上缩短1.5天,通过加大劳动力和工人娴熟性,加快工序的衔接。

据了解,万新路复线段是福州东南快速通道的一部分,全线总长约7.89公里,总投资20.3亿元。项目预计2021年完工通车,届时可进一步完善滨海新城的路网。

中交二航局万新路A2标段项目副经理任芮林:国庆期间为响应福州市"百日冲刺"我们采取多点同时施工,保证一个点完成20米的管廊,总计现场投入100多人,后场钢筋制作30人,总计完成80米。

来源:福州新闻
编辑:钟月迎  责编:郑雪峰

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 他们将"黄金周"变成"攻坚周",为城市建设添砖加瓦。 [thumb] => [{"url":"\/a\/10001\/201810\/0b76eba9d69d9bd922532101efe65970.JPG","id":"311922"}] [url] => /p/39126.html [all_pv] => 2578 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 管廊 [1] => 新路 [2] => 钢筋 [3] => 福州 [4] => 复线 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 39105 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39105.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39105.html [published_timestamp] => 1538904445 [published] => 1538904445 [pv] => 1085 [virtual_pv] => 460 [all_pv] => 1085 [title] => 重磅!央行降低存款准备金率1个百分点 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/9432bbd68a49ff233f2f5e0ba475e9f7.jpeg ) [1] => Array ( [relateid] => 39102 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39102.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39102.html [published_timestamp] => 1538904341 [published] => 1538904341 [pv] => 1096 [virtual_pv] => 476 [all_pv] => 1096 [title] => 平潭海洋国际中心会展中心积极推进项目建设 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/3480e3d8efeab84f2b55d83248d59552.jpeg ) [2] => Array ( [relateid] => 39099 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39099.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39099.html [published_timestamp] => 1538899069 [published] => 1538899069 [pv] => 1082 [virtual_pv] => 450 [all_pv] => 1082 [title] => 【大美福州】老仓山洋房 别致之美 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/00b7f300f02d748128d9aeb2c0f558be.jpeg ) [3] => Array ( [relateid] => 39093 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39093.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39093.html [published_timestamp] => 1538896538 [published] => 1538896538 [pv] => 1082 [virtual_pv] => 428 [all_pv] => 1082 [title] => 共享厨房亮相福州大学食堂 学生争相体验下厨乐趣 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/e86a0fc06ce7e4c15f6313126ed9acec.JPG ) [4] => Array ( [relateid] => 39090 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39090.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39090.html [published_timestamp] => 1538895956 [published] => 1538895956 [pv] => 771 [virtual_pv] => 454 [all_pv] => 771 [title] => 福州闽侯举办“老物件”展 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/f32337581cf7cb908cdb9c577823c004.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201810/0b76eba9d69d9bd922532101efe65970.JPG ) 1

节日里的坚守:东南快速通道万新路复线工程采用新技术配建综合管廊

2018-10-07 19:34   福州新闻  

国庆黄金周,许多人在景区享受假日时光时,有一群人还坚守一线,铆足干劲,全力推进缓解交通拥堵、水系综合治理、老旧小区整治等重大项目、重点工程建设。他们将"黄金周"变成"攻坚周",为城市建设添砖加瓦,展现出良好的干事创业精气神。

在福州东南快速通道万新路复线段,为保证进度,项目国庆假期不停工,采用新技术新理念,全力推进综合管廊及道路路基建设。

在位于长乐漳港的万新路复线段施工现场,工人们正在进行管廊钢筋作业。该综合管廊全长约5公里,将在地下修一条集电力、通信、给排水、燃气等各类管线于一体的隧道。由于项目位于海边,地下水丰富,地质条件复杂,因此施工方采用井点降水的方式将管廊中的海水排空,同时加大人员设备投入,使工期比预计缩短了一半。目前,该建设技术正在申请研究课题,争创地方标准。

中交二航局万新路A2标段项目副经理任芮林:通过井点降水将整个地面水位降到我们的管廊底标高以下,保持整个施工过程中是干的施工环境,从而达到钢筋避免被海水浸泡的效果。

福州新区项目建设管理办公室副总监吴强:正常的像我们这么大的一个管廊(钢筋部分),双仓室的,我们要三天正常的工序,现在是基本上缩短1.5天,通过加大劳动力和工人娴熟性,加快工序的衔接。

据了解,万新路复线段是福州东南快速通道的一部分,全线总长约7.89公里,总投资20.3亿元。项目预计2021年完工通车,届时可进一步完善滨海新城的路网。

中交二航局万新路A2标段项目副经理任芮林:国庆期间为响应福州市"百日冲刺"我们采取多点同时施工,保证一个点完成20米的管廊,总计现场投入100多人,后场钢筋制作30人,总计完成80米。