Array ( [id] => 42774 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁5号线首台盾构机始发!其他线路也在加快建设! [editor] => (二审)余玉金 [has_thumb] => 1 [created] => 2018-10-23 17:48:35 [createdby] => 10004 [createdip] => 192.168.12.4 [published] => 2018-10-23 17:48:35 [publishedby] => 10004 [modified] => 2018-10-23 18:40:05 [modifiedby] => 10004 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 1628 [virtual_pv] => 451 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

重磅!福州地铁5号线首个盾构区间正式始发,6号线又有两个区间单线洞通,福州地铁正在火热建设中!

5号线首台盾构机始发

10月19日,中国铁建十二局负责建设的福州地铁5号线高仕路站~螺洲站(高螺区间)右线盾构机“致远一号”始发。这是福州地铁5号线一期工程始发的首台盾构,标志着地铁5号线建设进入了一个全新的阶段!

根据资料显示,高螺区间单线全长约622米,本次盾构始发后,预计将于年底实现洞通。

执行完该区间盾构后,该盾构机还将继续执行高仕路站~城锦路站,以及城锦路站~城南区间风井~福州火车南站站的右线盾构任务。

6号线两个区间“洞通”

近日福州地铁6号线

又有两个区间实现了单线洞通

10月14日,福州地铁6号线壶井站~万寿站区间右线盾构机到达壶井站南侧的接收井,比原计划提前近半个月贯通。该区间全长920.93米,于今年6月10日始发,主要下穿菜地、鱼塘、民房、国创规划用地,区间与规划万沙河斜交,线路纵断面大体呈“V”字坡,且地层为涌水涌沙高发地段。

10月18日早晨,地铁6号线航城站~郑和站区间右线顺利贯通。该区间全长1257.86米,于2月28日顺利始发,先后近距离侧穿(下穿)河道、多个商业及居住区,克服了地质沉降及涌水等困难。区间左线计划于10月30日进行接收,并将继续执行郑和站~十洋站区间掘进任务。

此外,10月15日上午,6号线十洋站至吴航站区间右线盾构也已经顺利始发。

想不到吧!福州地铁正在默默提速!

为福州地铁和建设者们点赞!加油!!!

来源:重磅福州
编辑:余玉金  责编:郑雪峰

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 福州地铁正在火热建设中! [thumb] => [{"url":"\/a\/10001\/201810\/fcbb0aff02adc90b78ea4c25a83dc0dc.jpeg","id":"348045"}] [url] => /p/42774.html [all_pv] => 1628 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 区间 [2] => 盾构 [3] => 始发 [4] => 地铁 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 42741 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42741.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42741.html [published_timestamp] => 1540283160 [published] => 1540283160 [pv] => 880 [virtual_pv] => 424 [all_pv] => 880 [title] => “抓项目促发展”专项行动综合考评 晋安区拿下全市第一 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/354c52b11b26a1ea9204d8e56f3d9bb2.jpeg ) [1] => Array ( [relateid] => 42735 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42735.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42735.html [published_timestamp] => 1540274578 [published] => 1540274578 [pv] => 12 [virtual_pv] => 443 [all_pv] => 12 [title] => 从昔日荒山到福州名胜 福道“进化之路”在继续 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/4c938fbc615f4350100e4acf21f8bd9a.jpeg ) [2] => Array ( [relateid] => 42732 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42732.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42732.html [published_timestamp] => 1540274404 [published] => 1540274404 [pv] => 651 [virtual_pv] => 425 [all_pv] => 651 [title] => 福州开展政策性粮食库存数量和质量大清查工作 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/63e180bca989afe396b0d25acde0217a.png ) [3] => Array ( [relateid] => 42729 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42729.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42729.html [published_timestamp] => 1540274152 [published] => 1540274152 [pv] => 2353 [virtual_pv] => 456 [all_pv] => 2353 [title] => 超强台风“玉兔”生成!福州天气,两次大反转! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/7bb1ae7b6012882bf7c1923fc1413d56.jpeg ) [4] => Array ( [relateid] => 42720 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42720.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42720.html [published_timestamp] => 1540273308 [published] => 1540273308 [pv] => 840 [virtual_pv] => 466 [all_pv] => 840 [title] => 福州车主注意!只因这个行为 9月以来近百人被罚! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/dc06629adbfc9bcfb6bc394ea2adf332.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201810/fcbb0aff02adc90b78ea4c25a83dc0dc.jpeg ) 1

福州地铁5号线首台盾构机始发!其他线路也在加快建设!

2018-10-23 17:48   福视悦动  

重磅!福州地铁5号线首个盾构区间正式始发,6号线又有两个区间单线洞通,福州地铁正在火热建设中!

5号线首台盾构机始发

10月19日,中国铁建十二局负责建设的福州地铁5号线高仕路站~螺洲站(高螺区间)右线盾构机“致远一号”始发。这是福州地铁5号线一期工程始发的首台盾构,标志着地铁5号线建设进入了一个全新的阶段!

根据资料显示,高螺区间单线全长约622米,本次盾构始发后,预计将于年底实现洞通。

执行完该区间盾构后,该盾构机还将继续执行高仕路站~城锦路站,以及城锦路站~城南区间风井~福州火车南站站的右线盾构任务。

6号线两个区间“洞通”

近日福州地铁6号线

又有两个区间实现了单线洞通

10月14日,福州地铁6号线壶井站~万寿站区间右线盾构机到达壶井站南侧的接收井,比原计划提前近半个月贯通。该区间全长920.93米,于今年6月10日始发,主要下穿菜地、鱼塘、民房、国创规划用地,区间与规划万沙河斜交,线路纵断面大体呈“V”字坡,且地层为涌水涌沙高发地段。

10月18日早晨,地铁6号线航城站~郑和站区间右线顺利贯通。该区间全长1257.86米,于2月28日顺利始发,先后近距离侧穿(下穿)河道、多个商业及居住区,克服了地质沉降及涌水等困难。区间左线计划于10月30日进行接收,并将继续执行郑和站~十洋站区间掘进任务。

此外,10月15日上午,6号线十洋站至吴航站区间右线盾构也已经顺利始发。

想不到吧!福州地铁正在默默提速!

为福州地铁和建设者们点赞!加油!!!

来源:重磅福州
编辑:余玉金  责编:郑雪峰