Array ( [id] => 42798 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁5号线首台盾构机始发!其他线路也在加快建设! [editor] => (二审)余玉金 [has_thumb] => 1 [created] => 2018-10-23 18:46:42 [createdby] => 10004 [createdip] => 192.168.12.4 [published] => 2018-10-23 18:46:42 [publishedby] => 10004 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1369 [virtual_pv] => 448 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

重磅!福州地铁5号线首个盾构区间正式始发,6号线又有两个区间单线洞通,福州地铁正在火热建设中!

5号线首台盾构机始发

10月19日,中国铁建十二局负责建设的福州地铁5号线高仕路站~螺洲站(高螺区间)右线盾构机“致远一号”始发。这是福州地铁5号线一期工程始发的首台盾构,标志着地铁5号线建设进入了一个全新的阶段!

根据资料显示,高螺区间单线全长约622米,本次盾构始发后,预计将于年底实现洞通。

执行完该区间盾构后,该盾构机还将继续执行高仕路站~城锦路站,以及城锦路站~城南区间风井~福州火车南站站的右线盾构任务。

6号线两个区间“洞通”

近日福州地铁6号线

又有两个区间实现了单线洞通

10月14日,福州地铁6号线壶井站~万寿站区间右线盾构机到达壶井站南侧的接收井,比原计划提前近半个月贯通。该区间全长920.93米,于今年6月10日始发,主要下穿菜地、鱼塘、民房、国创规划用地,区间与规划万沙河斜交,线路纵断面大体呈“V”字坡,且地层为涌水涌沙高发地段。

10月18日早晨,地铁6号线航城站~郑和站区间右线顺利贯通。该区间全长1257.86米,于2月28日顺利始发,先后近距离侧穿(下穿)河道、多个商业及居住区,克服了地质沉降及涌水等困难。区间左线计划于10月30日进行接收,并将继续执行郑和站~十洋站区间掘进任务。

此外,10月15日上午,6号线十洋站至吴航站区间右线盾构也已经顺利始发。

想不到吧!福州地铁正在默默提速!

为福州地铁和建设者们点赞!加油!!!


来源:重磅福州
编辑:余玉金  责编:郑雪峰

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 福州地铁正在火热建设中! [thumb] => [{"url":"\/a\/10001\/201810\/abcfdfe5fa3ef8fef09b032beceb3ec0.jpeg","id":"348348"}] [url] => /p/42798.html [all_pv] => 1369 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 区间 [2] => 盾构 [3] => 始发 [4] => 地铁 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 42795 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42795.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42795.html [published_timestamp] => 1540291182 [published] => 1540291182 [pv] => 1126 [virtual_pv] => 462 [all_pv] => 1126 [title] => 厉害了!第16届省运会,福州田径队迎来“开门红” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201810/cfc50538314ffc0e5a0e07efac4fff05.png@w317_h237.png ) [1] => Array ( [relateid] => 42792 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42792.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42792.html [published_timestamp] => 1540290974 [published] => 1540290974 [pv] => 2280 [virtual_pv] => 466 [all_pv] => 2280 [title] => 20年保洁路,他“扫”出一大摞荣誉证书 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/841dbdd534adc3b639b76736f8e68ea8.png ) [2] => Array ( [relateid] => 42789 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42789.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42789.html [published_timestamp] => 1540290844 [published] => 1540290844 [pv] => 858 [virtual_pv] => 451 [all_pv] => 858 [title] => 魁岐片区水系下月启动截污景观绿化 明年再现水清河静景美 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/4befa2ff20ba2ad2c7a4fd42b67949d4.jpeg ) [3] => Array ( [relateid] => 42786 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42786.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42786.html [published_timestamp] => 1540290407 [published] => 1540290407 [pv] => 1754 [virtual_pv] => 368 [all_pv] => 1754 [title] => 想去体验港珠澳大桥的福州朋友 这10件事你要知道! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/3030782cdb4aeabd019ba0eff8eb5981.jpeg ) [4] => Array ( [relateid] => 42783 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42783.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42783.html [published_timestamp] => 1540289502 [published] => 1540289502 [pv] => 888 [virtual_pv] => 419 [all_pv] => 888 [title] => 刷爆朋友圈!晋安交警的这番话,全福州人都点赞! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/d3b07654f64fd0ef34f952b1aaf104fe.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/201810/abcfdfe5fa3ef8fef09b032beceb3ec0.jpeg ) 1

福州地铁5号线首台盾构机始发!其他线路也在加快建设!

2018-10-23 18:46   福视悦动  

重磅!福州地铁5号线首个盾构区间正式始发,6号线又有两个区间单线洞通,福州地铁正在火热建设中!

5号线首台盾构机始发

10月19日,中国铁建十二局负责建设的福州地铁5号线高仕路站~螺洲站(高螺区间)右线盾构机“致远一号”始发。这是福州地铁5号线一期工程始发的首台盾构,标志着地铁5号线建设进入了一个全新的阶段!

根据资料显示,高螺区间单线全长约622米,本次盾构始发后,预计将于年底实现洞通。

执行完该区间盾构后,该盾构机还将继续执行高仕路站~城锦路站,以及城锦路站~城南区间风井~福州火车南站站的右线盾构任务。

6号线两个区间“洞通”

近日福州地铁6号线

又有两个区间实现了单线洞通

10月14日,福州地铁6号线壶井站~万寿站区间右线盾构机到达壶井站南侧的接收井,比原计划提前近半个月贯通。该区间全长920.93米,于今年6月10日始发,主要下穿菜地、鱼塘、民房、国创规划用地,区间与规划万沙河斜交,线路纵断面大体呈“V”字坡,且地层为涌水涌沙高发地段。

10月18日早晨,地铁6号线航城站~郑和站区间右线顺利贯通。该区间全长1257.86米,于2月28日顺利始发,先后近距离侧穿(下穿)河道、多个商业及居住区,克服了地质沉降及涌水等困难。区间左线计划于10月30日进行接收,并将继续执行郑和站~十洋站区间掘进任务。

此外,10月15日上午,6号线十洋站至吴航站区间右线盾构也已经顺利始发。

想不到吧!福州地铁正在默默提速!

为福州地铁和建设者们点赞!加油!!!


来源:重磅福州