Array ( [id] => 49599 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 国货互通立交改造工程提速推进 预计明年9月通车 [editor] => 林佳佳 [has_thumb] => 1 [created] => 2018-11-22 19:14:20 [createdby] => 10071 [createdip] => 192.168.12.13 [published] => 2018-11-22 19:14:20 [publishedby] => 10071 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1202 [virtual_pv] => 412 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为我市第二批缓堵项目,国货互通立交改造工程自8月动工以来,进展顺利,新增的4条匝道陆续进入桩基施工阶段。

记者在现场看到,桩基、栈桥搭设等多个工作面正同时进行。由于新建的四条匝道桩基大部分位于光明港内,需要进行水上作业,施工难度较大。经多方论证,施工方将原先的箱梁施工改为少支架钢套箱施工,这样既能减少水上作业的风险,也能保证施工进度。

市市政建设开发有限公司国货互通立交改造工程项目负责人陈明跃:保证支架的稳定性,通过连续的支撑把桥(匝道)慢慢建起来,钢套箱是先预制一个箱体,把它放置在打完的桩基上面。

该项目预计明年九月完工通车。届时,将实现三环辅路与机场高速、鼓山大桥的快速连接,可有效缓解进出城区的交通压力。

来源:福州新闻
编辑:林佳佳 责编:郑雪峰

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 作为我市第二批缓堵项目,国货互通立交改造工程自8月动工以来,进展顺利,新增的4条匝道陆续进入桩基施工阶段。 [thumb] => [{"url":"\/a\/10001\/201811\/b0c0cc5ef59b5798cbc1690952296277.jpeg","id":"452256"}] [url] => /p/49599.html [all_pv] => 1202 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 桩基 [1] => 匝道 [2] => 施工 [3] => 钢套 [4] => 国货 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 49542 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/49542.html [wapUrl] => http://m.fztvapp.zohi.tv/p/49542.html [published_timestamp] => 1542871520 [published] => 1542871520 [pv] => 1048 [virtual_pv] => 479 [all_pv] => 1048 [title] => 滨海新城加速度 | 海峡青少年活动中心又“长高”了 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201811/6a72a41f2685cc5b025bbc4bccbc8c46.jpg@w437_h328.jpg ) [1] => Array ( [relateid] => 49524 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/49524.html [wapUrl] => http://m.fztvapp.zohi.tv/p/49524.html [published_timestamp] => 1542869925 [published] => 1542869925 [pv] => 581 [virtual_pv] => 468 [all_pv] => 581 [title] => 福州老字号民天食品下月搬迁至闽清 产能扩大8倍 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/64205572c1c0649093aa0a3b8a87f5de.jpeg ) [2] => Array ( [relateid] => 49485 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/49485.html [wapUrl] => http://m.fztvapp.zohi.tv/p/49485.html [published_timestamp] => 1542865831 [published] => 1542865831 [pv] => 344 [virtual_pv] => 390 [all_pv] => 344 [title] => 福建福清核电站累计安全发电770亿千瓦时 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/7f16788986b350b23f2799cf762a1dbe.jpeg ) [3] => Array ( [relateid] => 49404 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/49404.html [wapUrl] => http://m.fztvapp.zohi.tv/p/49404.html [published_timestamp] => 1542848756 [published] => 1542848756 [pv] => 897 [virtual_pv] => 455 [all_pv] => 897 [title] => 南台大道南段主线下月贯通 6个治堵项目迎重大进展 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/9a563811d6b8270bb2cebc6b3828286e.jpeg ) [4] => Array ( [relateid] => 49332 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/49332.html [wapUrl] => http://m.fztvapp.zohi.tv/p/49332.html [published_timestamp] => 1542795039 [published] => 1542795039 [pv] => 744 [virtual_pv] => 403 [all_pv] => 744 [title] => 屏山公园改造提速 有望元旦前重装迎客 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/4942b4c9eb7f2d803e0d8e227af74016.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/201811/b0c0cc5ef59b5798cbc1690952296277.jpeg ) 1

国货互通立交改造工程提速推进 预计明年9月通车

2018-11-22 19:14   福州新闻  

作为我市第二批缓堵项目,国货互通立交改造工程自8月动工以来,进展顺利,新增的4条匝道陆续进入桩基施工阶段。

记者在现场看到,桩基、栈桥搭设等多个工作面正同时进行。由于新建的四条匝道桩基大部分位于光明港内,需要进行水上作业,施工难度较大。经多方论证,施工方将原先的箱梁施工改为少支架钢套箱施工,这样既能减少水上作业的风险,也能保证施工进度。

市市政建设开发有限公司国货互通立交改造工程项目负责人陈明跃:保证支架的稳定性,通过连续的支撑把桥(匝道)慢慢建起来,钢套箱是先预制一个箱体,把它放置在打完的桩基上面。

该项目预计明年九月完工通车。届时,将实现三环辅路与机场高速、鼓山大桥的快速连接,可有效缓解进出城区的交通压力。

来源:福州新闻
编辑:林佳佳 责编:郑雪峰