Array ( [id] => 62046 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 杨桥路江滨节点改造提速 力争上半年通车 [editor] => 何洋泓 [has_thumb] => 1 [created] => 2019-01-17 19:20:50 [createdby] => 10110 [createdip] => 192.168.12.11 [published] => 2019-01-17 19:20:50 [publishedby] => 10110 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 1081 [virtual_pv] => 439 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 5 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [content] =>

作为城区第二批治堵重大项目之一,杨桥路江滨节点改造工程备受关注。为全力打造"畅通福州",杨桥路江滨节点改造工程不断提速,目前工程量已经近半,力争今年上半年建成通车。

据了解,杨桥西路是主城区车辆前往闽侯荆溪、甘蔗和上街等地的重要通道。因为车流量较大,每每到了高峰期杨桥路江滨路口总会出现车辆滞的情况。为了缓解这一状况,此次杨桥路江滨节点改造工程将新建一条左转匝道和一座高架桥,起到快速疏散出城车流的作用。

杨桥路江滨节点改造工程项目经理苏雄丰:按照该项目建设方案长245米的江滨西大道,往洪山桥方向的左转B匝道桥和长560米的杨桥路上跨江滨大道的A线出城高架桥是项目两大核心工程

据施工方介绍,目前整体工程量已经完成近半。其中,往洪山桥方向的左转B匝道桥将在春节后开始吊装,整体工程力争今年上半年完成,并实现通车。

杨桥路江滨节点改造工程项目经理苏雄丰:B匝道建设速度比较快,已完成12根桩基中的8根,桥梁主体钢结构部分也在工厂内加工完成。春节后工厂钢结构将陆续抵运现场,展开吊装施工 A线高架桥即将展开江滨西大道落地区域的桩基施工,须在西区水厂门口约300米实施围挡。目前已经全面完成围挡,转入桩基施工。

需要注意的是围挡期间西往东车辆禁止在路口掉头。同时,作为该项目的一部分,西区水厂和洪山小学附近将新建两座人行天桥横跨杨桥西路,方便附近居民、学生过街。

来源:新闻110
编辑:何洋泓 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201901\/f6531a8196e92c0d264eef00fb44f5b8.jpeg","id":"629898"}] [url] => /p/62046.html [all_pv] => 1081 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 新闻110 ) [2] => Array ( [0] => 江滨 [1] => 杨桥 [2] => 节点 [3] => 匝道 [4] => 桩基 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 61998 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/61998.html [wapUrl] => http://m.fztvapp.zohi.tv/p/61998.html [published_timestamp] => 1547708427 [published] => 1547708427 [pv] => 733 [virtual_pv] => 423 [all_pv] => 733 [title] => 仓山区项目攻坚 火力全开成效显著 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/61912a7f7e47369a7f1f64ad9d1a9177.jpeg ) [1] => Array ( [relateid] => 61995 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/61995.html [wapUrl] => http://m.fztvapp.zohi.tv/p/61995.html [published_timestamp] => 1547708152 [published] => 1547708152 [pv] => 794 [virtual_pv] => 395 [all_pv] => 794 [title] => 【大美福州】慢慢爱上仓山,直到地老天荒! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/3296252ab14b3addd02e2bfa6202a082.jpeg ) [2] => Array ( [relateid] => 61923 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/61923.html [wapUrl] => http://m.fztvapp.zohi.tv/p/61923.html [published_timestamp] => 1547695543 [published] => 1547695543 [pv] => 600 [virtual_pv] => 477 [all_pv] => 600 [title] => 福州鼓楼布置调试新春街景 小年夜全面试亮灯 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/9e60b9947cc294920a8c248d66f54372.jpeg ) [3] => Array ( [relateid] => 61911 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/61911.html [wapUrl] => http://m.fztvapp.zohi.tv/p/61911.html [published_timestamp] => 1547691752 [published] => 1547691752 [pv] => 1460 [virtual_pv] => 412 [all_pv] => 1460 [title] => 再升级!鼓山千年登山道将配备花径水涧 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/f690b98c9c74329a8a7e43bace8d7ca4.jpeg ) [4] => Array ( [relateid] => 61884 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/61884.html [wapUrl] => http://m.fztvapp.zohi.tv/p/61884.html [published_timestamp] => 1547690336 [published] => 1547690336 [pv] => 732 [virtual_pv] => 422 [all_pv] => 732 [title] => 交警支队发布交通出行提示 春节期间出行注意避开高峰 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/5185584d6becb5b7a7050bde6f9dde7e.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201901/f6531a8196e92c0d264eef00fb44f5b8.jpeg ) 1

杨桥路江滨节点改造提速 力争上半年通车

2019-01-17 19:20   新闻110  

作为城区第二批治堵重大项目之一,杨桥路江滨节点改造工程备受关注。为全力打造"畅通福州",杨桥路江滨节点改造工程不断提速,目前工程量已经近半,力争今年上半年建成通车。

据了解,杨桥西路是主城区车辆前往闽侯荆溪、甘蔗和上街等地的重要通道。因为车流量较大,每每到了高峰期杨桥路江滨路口总会出现车辆滞的情况。为了缓解这一状况,此次杨桥路江滨节点改造工程将新建一条左转匝道和一座高架桥,起到快速疏散出城车流的作用。

杨桥路江滨节点改造工程项目经理苏雄丰:按照该项目建设方案长245米的江滨西大道,往洪山桥方向的左转B匝道桥和长560米的杨桥路上跨江滨大道的A线出城高架桥是项目两大核心工程

据施工方介绍,目前整体工程量已经完成近半。其中,往洪山桥方向的左转B匝道桥将在春节后开始吊装,整体工程力争今年上半年完成,并实现通车。

杨桥路江滨节点改造工程项目经理苏雄丰:B匝道建设速度比较快,已完成12根桩基中的8根,桥梁主体钢结构部分也在工厂内加工完成。春节后工厂钢结构将陆续抵运现场,展开吊装施工 A线高架桥即将展开江滨西大道落地区域的桩基施工,须在西区水厂门口约300米实施围挡。目前已经全面完成围挡,转入桩基施工。

需要注意的是围挡期间西往东车辆禁止在路口掉头。同时,作为该项目的一部分,西区水厂和洪山小学附近将新建两座人行天桥横跨杨桥西路,方便附近居民、学生过街。

来源:新闻110
编辑:何洋泓 责编:林真贞