Array ( [id] => 70674 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 滨海新城推进41条市政道路建设 9条力争4月完工 [editor] => (二审)翁彬冰 [has_thumb] => 1 [created] => 2019-02-27 15:51:43 [createdby] => 10022 [createdip] => 192.168.12.200 [published] => 2019-02-27 15:51:43 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 879 [virtual_pv] => 402 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

记者26日获悉,目前滨海新城正按照“窄马路、密路网”的规划理念,大力推进在建的41条市政道路建设,其中9条主次干道力争4月建成。

昨日上午,在悦湖路施工现场,工人正在进行路面及灯杆施工。据现场负责人介绍,悦湖路属于中国东南大数据产业园二区路网纵向次干道,为双向四车道,南起壶江路,向北延伸,止于万新路,长约1公里,宽40米,设计车速为40公里/小时,总投资约1.96亿元。目前,悦湖路第一道沥青铺设施工已经完成,后续将加快施工进度,争取4月份完成建设。

在中国东南大数据产业园内,万沙路、渡湖路一期、漳江路、金江路、新塘港路、壶江路、湖文路等多条主次干道均在同步开展路基和市政管道施工。“这些道路是滨海新城核心区路网结构的重要组成部分,我们全力以赴,力争4月份全部建好这些道路。”上述负责人说。

在加快新道路项目建设的同时,滨海新城还改造提升已有道路,进一步提升路网通达性、便捷性。其中,连接漳港高速出入口与大数据产业园的重要通道——文松路提升改造及两侧绿化带景观工程正在加快推进,将于4月底完工。

据福州滨海新城建设总指挥部相关负责人介绍,文松路设计长度4414.95米,改造宽度61.5米,总投资约4亿元。该项目起点位于漳港东山大桥北桥头,向北延伸,沿线与金滨路、万新路、壶江路、壶井路、道庆路等道路相交,过漳港高速出入口,终点位于鑫城化纤门口。道路等级为主干道,设计车速为60公里/小时。

来源:福州晚报
编辑:翁彬冰 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 道路等级为主干道,设计车速为60公里/小时。 [thumb] => [{"url":"\/a\/10001\/201902\/e1d8fbf8329720c34b286db7545e7f07.jpeg","id":"766968"}] [url] => /p/70674.html [all_pv] => 879 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 路网 [1] => 道路 [2] => 湖路 [3] => 新城 [4] => 滨海 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 70671 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/70671.html [wapUrl] => http://m.fztvapp.zohi.tv/p/70671.html [published_timestamp] => 1551253647 [published] => 1551253647 [pv] => 478 [virtual_pv] => 483 [all_pv] => 478 [title] => 福建一29岁女子发了条朋友圈,结果被拘留5日! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/9224da2e4a33e624482862a28b575995.jpeg ) [1] => Array ( [relateid] => 70668 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/70668.html [wapUrl] => http://m.fztvapp.zohi.tv/p/70668.html [published_timestamp] => 1551250506 [published] => 1551250506 [pv] => 586 [virtual_pv] => 403 [all_pv] => 586 [title] => 手机突然没信号 接下来这波操作银行卡里的钱就没了 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/a8ff3d2f93195c3916430a195caf2057.jpeg ) [2] => Array ( [relateid] => 70665 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/70665.html [wapUrl] => http://m.fztvapp.zohi.tv/p/70665.html [published_timestamp] => 1551249376 [published] => 1551249376 [pv] => 663 [virtual_pv] => 370 [all_pv] => 663 [title] => 记者探访商场现榨橙汁机 卫生状况令人担忧 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/78513aec1dd00b9264424adfe5c5bb4a.jpeg ) [3] => Array ( [relateid] => 70662 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/70662.html [wapUrl] => http://m.fztvapp.zohi.tv/p/70662.html [published_timestamp] => 1551248861 [published] => 1551248861 [pv] => 511 [virtual_pv] => 474 [all_pv] => 511 [title] => 我省花卉苗木产业产值首次突破700亿元大关 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/1c9d73866c5460d057dd11bd90cfacf1.jpeg ) [4] => Array ( [relateid] => 70653 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/70653.html [wapUrl] => http://m.fztvapp.zohi.tv/p/70653.html [published_timestamp] => 1551248398 [published] => 1551248398 [pv] => 439 [virtual_pv] => 472 [all_pv] => 439 [title] => 福建等8省市启动高考改革 方案将向社会公布 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201902/14306a7cf8efc093da9d5ac706f62718.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201902/e1d8fbf8329720c34b286db7545e7f07.jpeg ) 1

滨海新城推进41条市政道路建设 9条力争4月完工

2019-02-27 15:51   福视悦动  

记者26日获悉,目前滨海新城正按照“窄马路、密路网”的规划理念,大力推进在建的41条市政道路建设,其中9条主次干道力争4月建成。

昨日上午,在悦湖路施工现场,工人正在进行路面及灯杆施工。据现场负责人介绍,悦湖路属于中国东南大数据产业园二区路网纵向次干道,为双向四车道,南起壶江路,向北延伸,止于万新路,长约1公里,宽40米,设计车速为40公里/小时,总投资约1.96亿元。目前,悦湖路第一道沥青铺设施工已经完成,后续将加快施工进度,争取4月份完成建设。

在中国东南大数据产业园内,万沙路、渡湖路一期、漳江路、金江路、新塘港路、壶江路、湖文路等多条主次干道均在同步开展路基和市政管道施工。“这些道路是滨海新城核心区路网结构的重要组成部分,我们全力以赴,力争4月份全部建好这些道路。”上述负责人说。

在加快新道路项目建设的同时,滨海新城还改造提升已有道路,进一步提升路网通达性、便捷性。其中,连接漳港高速出入口与大数据产业园的重要通道——文松路提升改造及两侧绿化带景观工程正在加快推进,将于4月底完工。

据福州滨海新城建设总指挥部相关负责人介绍,文松路设计长度4414.95米,改造宽度61.5米,总投资约4亿元。该项目起点位于漳港东山大桥北桥头,向北延伸,沿线与金滨路、万新路、壶江路、壶井路、道庆路等道路相交,过漳港高速出入口,终点位于鑫城化纤门口。道路等级为主干道,设计车速为60公里/小时。

来源:福州晚报
编辑:翁彬冰 责编:林真贞