Array ( [id] => 71565 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 奥体颐养中心项目明年上半年建成 [editor] => (一审)阮根城 [has_thumb] => 1 [created] => 2019-03-03 19:02:57 [createdby] => 10037 [createdip] => 220.250.18.204 [published] => 2019-03-03 19:02:57 [publishedby] => 10037 [modified] => 2019-03-03 20:29:24 [modifiedby] => 10042 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1311 [virtual_pv] => 422 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 15 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为我市首个

融入装配及海绵元素的

养老建筑项目

奥体颐养中心建设进展顺利

预计明年上半年建成

奥体颐养中心位于

仓山区杨周路宝山路口

项目建设用地15.3亩

建筑面积2.3万平方米

设计床位463张

总投资约3亿元

项目建造装配率达到30%

可大大减少建筑垃圾以及噪音污染

按照海绵城市和绿色建筑要求

设置了立体绿化、植草沟

下沉式绿地、雨水花园

地下蓄水模块

广场与道路会采用

透水混凝土和透水砖铺设

实现雨水在区域内的

自然积存、渗透和净化

项目设有酒店式大堂接待区

配套医疗区、居住护理区

娱乐活动区、立体式公园景观区等

并将融入智能化技术

实现医养结合

提升养老体验

市建发集团奥体颐养中心项目经理 林思远

计划今年5月份完成地下室施工,9月份完成结构封顶,明年3月完成装修工程,年6月竣工验收


来源:福州新闻
编辑:陈伟 责编:方佳佳 新媒体责编:真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 属于我市首个融入装配及海绵元素的养老建筑项目 [thumb] => [{"url":"\/a\/thumb\/10001\/201903\/998eed64483878f73a97e594ed46a2c0.jpeg@w1440_h1080.jpeg","id":"779949"}] [url] => /p/71565.html [all_pv] => 1311 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 奥体 [1] => 颐养 [2] => 责编 [3] => 透水 [4] => 项目 ) ) [menu] => 109 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 71544 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71544.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71544.html [published_timestamp] => 1551602528 [published] => 1551602528 [pv] => 445 [virtual_pv] => 445 [all_pv] => 445 [title] => 下周,暴雨! 雷电大风!强对流天气! 要强势霸屏了 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/f130ece066f0d16eff8adef7a349350c.jpeg ) [1] => Array ( [relateid] => 71541 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71541.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71541.html [published_timestamp] => 1551602291 [published] => 1551602291 [pv] => 616 [virtual_pv] => 419 [all_pv] => 616 [title] => 想购买“3D硬金”饰品?这3件事要提前了解清楚 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/9c87b49b0b7a5094a1a82b3cfe01d9e7.jpeg ) [2] => Array ( [relateid] => 71538 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71538.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71538.html [published_timestamp] => 1551602146 [published] => 1551602146 [pv] => 520 [virtual_pv] => 477 [all_pv] => 520 [title] => 对校园欺凌说“不”,鼓楼区这样做 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/a2b29f33e63eb6ddfb58f34ba25797f0.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/thumb/10001/201903/998eed64483878f73a97e594ed46a2c0.jpeg@w1440_h1080.jpeg ) 1

奥体颐养中心项目明年上半年建成

2019-03-03 19:02   福州新闻  

作为我市首个

融入装配及海绵元素的

养老建筑项目

奥体颐养中心建设进展顺利

预计明年上半年建成

奥体颐养中心位于

仓山区杨周路宝山路口

项目建设用地15.3亩

建筑面积2.3万平方米

设计床位463张

总投资约3亿元

项目建造装配率达到30%

可大大减少建筑垃圾以及噪音污染

按照海绵城市和绿色建筑要求

设置了立体绿化、植草沟

下沉式绿地、雨水花园

地下蓄水模块

广场与道路会采用

透水混凝土和透水砖铺设

实现雨水在区域内的

自然积存、渗透和净化

项目设有酒店式大堂接待区

配套医疗区、居住护理区

娱乐活动区、立体式公园景观区等

并将融入智能化技术

实现医养结合

提升养老体验

市建发集团奥体颐养中心项目经理 林思远

计划今年5月份完成地下室施工,9月份完成结构封顶,明年3月完成装修工程,年6月竣工验收


来源:福州新闻