Array ( [id] => 71784 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 淮安路加速攻坚 预计6月底通车 [editor] => (二审)翁彬冰 [has_thumb] => 1 [created] => 2019-03-04 19:20:11 [createdby] => 10022 [createdip] => 192.168.12.200 [published] => 2019-03-04 19:20:11 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1069 [virtual_pv] => 476 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 1 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为淮安半岛目前最重要的东西向通道,淮安路目前正展开最后600米攻坚,预计6月底可全面完工通车。

记者在现场看到,施工方正集中多台大型设备对道路山体进行土方开挖。淮安路全长约1.6公里,其中近1公里道路之前已建成,这段未通车路段原是一条狭小的村道,为确保道路平坦,施工人员需要沿着眼前这座山体往下挖。长约600米的路段,最深处得下挖20米,需要清运土方20万立方米。

市城乡建总淮安路项目现场负责人郭聪:最主要难点在20万方土方的外运,目前采取人歇机器不歇,20万土方计划在5月初全部运完成,后面进行道路建设,道路包括管道施工、路面施工、道路的附属结构施工。

淮安路预计今年6月底完工通车。届时,将打通淮安半岛到上下店路的交通瓶颈,方便来往车辆进出市区以及西北三环。

市城乡建总淮安路项目现场负责人郭聪:原来绕行(三环)大概开车要十几分钟,如果这条路打通的话,五分钟就可以到,极大方便了周边的居民。

来源:福州新闻
编辑:翁彬冰 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201903\/476d5493408343f7d2f69a667f185195.JPG","id":"782823"}] [url] => /p/71784.html [all_pv] => 1069 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 淮安 [1] => 20 [2] => 土方 [3] => 道路 [4] => 施工 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 71751 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71751.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71751.html [published_timestamp] => 1551695144 [published] => 1551695144 [pv] => 1596 [virtual_pv] => 448 [all_pv] => 1596 [title] => 速度围观!晋安河游船增设夜游项目,还有特别福利! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/38a2d9e1e6e91b12f5cffaf33f6bdf3c.png ) [1] => Array ( [relateid] => 71748 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71748.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71748.html [published_timestamp] => 1551693274 [published] => 1551693274 [pv] => 426 [virtual_pv] => 455 [all_pv] => 426 [title] => 春运40天,市道管处护送旅客“一路好运” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/d61dd990c85f7e6aaef1e55f33751bff.jpeg ) [2] => Array ( [relateid] => 71745 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71745.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71745.html [published_timestamp] => 1551693017 [published] => 1551693017 [pv] => 459 [virtual_pv] => 467 [all_pv] => 459 [title] => 暖心!长乐有人每年都在这个时候给85岁以上的宗亲老人发钱,已连续八年! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/59e4955734230df3f239234c8db3adf2.png ) [3] => Array ( [relateid] => 71739 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71739.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71739.html [published_timestamp] => 1551690518 [published] => 1551690518 [pv] => 498 [virtual_pv] => 407 [all_pv] => 498 [title] => 福州公开选聘20名青少年校园足球教练员 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/9036e1c54dc592076fd505917529f2d6.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201903/476d5493408343f7d2f69a667f185195.JPG ) 1

淮安路加速攻坚 预计6月底通车

2019-03-04 19:20   福州新闻  

作为淮安半岛目前最重要的东西向通道,淮安路目前正展开最后600米攻坚,预计6月底可全面完工通车。

记者在现场看到,施工方正集中多台大型设备对道路山体进行土方开挖。淮安路全长约1.6公里,其中近1公里道路之前已建成,这段未通车路段原是一条狭小的村道,为确保道路平坦,施工人员需要沿着眼前这座山体往下挖。长约600米的路段,最深处得下挖20米,需要清运土方20万立方米。

市城乡建总淮安路项目现场负责人郭聪:最主要难点在20万方土方的外运,目前采取人歇机器不歇,20万土方计划在5月初全部运完成,后面进行道路建设,道路包括管道施工、路面施工、道路的附属结构施工。

淮安路预计今年6月底完工通车。届时,将打通淮安半岛到上下店路的交通瓶颈,方便来往车辆进出市区以及西北三环。

市城乡建总淮安路项目现场负责人郭聪:原来绕行(三环)大概开车要十几分钟,如果这条路打通的话,五分钟就可以到,极大方便了周边的居民。