Array ( [id] => 77874 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 三大难点攻破 晋安河入闽江“流程”将压缩到45分钟 [editor] => (二审)翁彬冰 [has_thumb] => 1 [created] => 2019-04-01 10:00:27 [createdby] => 10022 [createdip] => 192.168.12.3 [published] => 2019-04-01 10:00:27 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 940 [virtual_pv] => 451 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

晋安河与光明港是我市江北(闽江以北)城区重要的行洪排涝通道。晋安河想要汇入闽江,以往都得经由光明港拐个弯后再入江。眼下,晋安河直排闽江通道工程正聚焦930米长的新路,全力展开冲刺攻坚。31日,记者从市城投集团下属市城乡建总获悉,该项目整体工程量已完成85%,关键节点排尾路段箱涵(排水通道)提前进入开挖阶段,与闽江防洪堤也仅剩34米的箱涵待建。6月,晋安河水进入闽江的时间将从原先的2小时缩短为45分钟。

31日上午,排尾路、江滨路等处的施工现场一片繁忙,大小机械、车辆穿梭其间,为晋安河水早日直通闽江加速作业。“现在工程的三大难点都已顺利攻破,正按既定工期多点施工,力争尽早完成。”市城投集团下属市城乡建总该项目负责人告诉记者,自去年1月动工至今,基坑开挖、主体结构施工陆续推进,“容纳”晋安河水的通道已随着一节节箱涵的浇筑渐渐成形。

该负责人介绍,目前,排尾路以北400多米箱涵及排尾路以南近200米箱涵施工都处于收尾阶段,闽江防洪堤(晋安河入闽江新增出水口)破除、排尾路段箱涵施工及红星闸站的建设是3个关键性节点。

记者注意到,排尾路上,车辆在导改后的路面有序通行,而围挡内,路面开挖正在进行。“这是整个工程里最大的施工难点,路面下方,有17根电力缆线,还有一条220千伏的综合电力管廊,要确保箱涵与这些电力设施‘和平共处’。”该负责人说,早在箱涵主体结构开挖前,全方位的保护措施就已展开,缆线也被一根根仔细架在贝雷架上,电力管廊也做足防沉降保护。得益于电力部门的给力支持,51米长的排尾路段箱涵得以提前开挖。

与闽江相接的最后34米箱涵段,是晋安河水得以汇入的关键。“现在外江围堰已实现闭合,给箱涵施工创造条件。”该负责人说,随着箱涵出口段的基坑支护基本完成,基坑开挖作业即将展开。

除了“新路”的修建,为让晋安河水“跑”得更快、更有力气,工程还配建了红星闸站。今后,晋安河水被引渠段“拥抱”后,9台水泵将发挥合力,以80立方米/秒的速度,把河水快速打入通道。遇上汛期,以往部分从晋安河进入光明港的涝水就能直接汇入闽江,很快排出,减少城区积涝的时间和概率。目前,闸站已正式转入上部结构施工,整体工程量完成80%,下月底,主体结构施工就将完成,6月中下旬就能转入设备安装调试阶段。

“6月底,随着外江围堰的拆除,晋安河水就能从新通道走了!”该负责人说,通过“截弯取直”,让河水直接通过引渠段汇入红星水闸及泵站,再经由713米长、20米宽的压力箱涵(新水道),直达闽江北港,让原先2个小时的入江“流程”,缩短为45分钟,加速降低光明港上游和晋安河口水位,提升城区排涝能力。

来源:福州日报
编辑:翁彬冰 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201904\/6e33b3442de5832dc425140df1358e47.jpeg","id":"875529"}] [url] => /p/77874.html [all_pv] => 940 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 晋安 [1] => 箱涵 [2] => 闽江 [3] => 排尾 [4] => 河水 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 77835 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77835.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77835.html [published_timestamp] => 1554031495 [published] => 1554031495 [pv] => 847 [virtual_pv] => 417 [all_pv] => 847 [title] => 市领导督导检查地铁2号线围挡拆除及道路恢复景观提升工作 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/d00d05ef124cd9f7370bb756ac57c315.JPG ) [1] => Array ( [relateid] => 77829 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77829.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77829.html [published_timestamp] => 1554031294 [published] => 1554031294 [pv] => 596 [virtual_pv] => 467 [all_pv] => 596 [title] => 王宁尤猛军检查城区水系综合治理提升工作 坚持不懈推进水系治理 不断提升福州内河水质 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/4659b8391d319fbe3e6ee29e373276c4.jpeg ) [2] => Array ( [relateid] => 77811 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77811.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77811.html [published_timestamp] => 1554031030 [published] => 1554031030 [pv] => 620 [virtual_pv] => 478 [all_pv] => 620 [title] => 王宁尤猛军检查城区水系综合治理提升工作 坚持不懈推进水系治理 不断提升福州内河水质 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/cfd8ee84c64e1b561dbc999f52fe2f4a.JPG ) [3] => Array ( [relateid] => 77799 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77799.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77799.html [published_timestamp] => 1554030755 [published] => 1554030755 [pv] => 666 [virtual_pv] => 421 [all_pv] => 666 [title] => 租房没住上 反而背上了网贷 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/c51bba49b85f4513b3ebdf0cf2fd4499.jpeg ) [4] => Array ( [relateid] => 77778 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77778.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77778.html [published_timestamp] => 1554026668 [published] => 1554026668 [pv] => 519 [virtual_pv] => 407 [all_pv] => 519 [title] => 重要提醒!今起,晋安这个地铁站点有最新变化! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/5ab257682f502e4a58bdd51edcd6a3fd.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/6e33b3442de5832dc425140df1358e47.jpeg ) 1

三大难点攻破 晋安河入闽江“流程”将压缩到45分钟

2019-04-01 10:00   福视悦动  

晋安河与光明港是我市江北(闽江以北)城区重要的行洪排涝通道。晋安河想要汇入闽江,以往都得经由光明港拐个弯后再入江。眼下,晋安河直排闽江通道工程正聚焦930米长的新路,全力展开冲刺攻坚。31日,记者从市城投集团下属市城乡建总获悉,该项目整体工程量已完成85%,关键节点排尾路段箱涵(排水通道)提前进入开挖阶段,与闽江防洪堤也仅剩34米的箱涵待建。6月,晋安河水进入闽江的时间将从原先的2小时缩短为45分钟。

31日上午,排尾路、江滨路等处的施工现场一片繁忙,大小机械、车辆穿梭其间,为晋安河水早日直通闽江加速作业。“现在工程的三大难点都已顺利攻破,正按既定工期多点施工,力争尽早完成。”市城投集团下属市城乡建总该项目负责人告诉记者,自去年1月动工至今,基坑开挖、主体结构施工陆续推进,“容纳”晋安河水的通道已随着一节节箱涵的浇筑渐渐成形。

该负责人介绍,目前,排尾路以北400多米箱涵及排尾路以南近200米箱涵施工都处于收尾阶段,闽江防洪堤(晋安河入闽江新增出水口)破除、排尾路段箱涵施工及红星闸站的建设是3个关键性节点。

记者注意到,排尾路上,车辆在导改后的路面有序通行,而围挡内,路面开挖正在进行。“这是整个工程里最大的施工难点,路面下方,有17根电力缆线,还有一条220千伏的综合电力管廊,要确保箱涵与这些电力设施‘和平共处’。”该负责人说,早在箱涵主体结构开挖前,全方位的保护措施就已展开,缆线也被一根根仔细架在贝雷架上,电力管廊也做足防沉降保护。得益于电力部门的给力支持,51米长的排尾路段箱涵得以提前开挖。

与闽江相接的最后34米箱涵段,是晋安河水得以汇入的关键。“现在外江围堰已实现闭合,给箱涵施工创造条件。”该负责人说,随着箱涵出口段的基坑支护基本完成,基坑开挖作业即将展开。

除了“新路”的修建,为让晋安河水“跑”得更快、更有力气,工程还配建了红星闸站。今后,晋安河水被引渠段“拥抱”后,9台水泵将发挥合力,以80立方米/秒的速度,把河水快速打入通道。遇上汛期,以往部分从晋安河进入光明港的涝水就能直接汇入闽江,很快排出,减少城区积涝的时间和概率。目前,闸站已正式转入上部结构施工,整体工程量完成80%,下月底,主体结构施工就将完成,6月中下旬就能转入设备安装调试阶段。

“6月底,随着外江围堰的拆除,晋安河水就能从新通道走了!”该负责人说,通过“截弯取直”,让河水直接通过引渠段汇入红星水闸及泵站,再经由713米长、20米宽的压力箱涵(新水道),直达闽江北港,让原先2个小时的入江“流程”,缩短为45分钟,加速降低光明港上游和晋安河口水位,提升城区排涝能力。

来源:福州日报