Array ( [id] => 79311 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 工业北路延伸线工程进展顺利 文林山隧道开始掘进 预计明年完工 [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-04-07 19:21:58 [createdby] => 10052 [createdip] => 192.168.12.8 [published] => 2019-04-07 19:21:58 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 2 [pv] => 2691 [virtual_pv] => 391 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 43 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为福州城区第二批治堵重大项目和省重点工程之一,工业北路延伸线工程建设进展顺利,靠近梅峰路的文林山隧道口施工已结束。目前,全长近2公里的隧道开始掘进,预计明年上半年贯通。

记者在位于梅峰山地公园附近的施工现场看到,几台大型设备正加紧作业。目前,该工程文林山隧道洞口施工已全部完成,施工方正在进行隧道掘进开挖工作。据介绍,由于隧道下穿临近梅峰山地公园,附近居民区多。因此,保障施工安全,防止人为施工因素造成地质灾害,成为施工方首要解决的问题。

工业北路延伸线工程项目部副经理 孙玉伟:在下穿过梅峰公园景观水池的时候,我们(采用)超前管幕(支撑),超前管幕长度达到90米,在国内都是比较领先的,最大优点就是能保护山地公园景观水池的原状,能确保将来我们隧道开挖之后,景观水池不渗漏,还能保证不下沉。

据了解,工业北路延伸线工程分南北两段,此次先行动建的为南段部分,南起工业路与杨桥路交叉口,沿工业路往北延伸,通过隧道穿越文林山,全长1.841公里。其中,文林山隧道长1.1公里,设有"一小两大"的三洞隧道,除了2个单向4车道的机动车隧道外,还将建设1个供行人和非机动车通行的慢行隧道,预计2020年完工。届时将有助于分流西二环车辆,直接缓解象山隧道、尤溪洲大桥的交通压力。

来源:福州新闻
编辑:王蕾 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201904\/391f8a9eb8026693f449fd9d4fb525f9.JPG","id":"897882"}] [url] => /p/79311.html [all_pv] => 2691 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 隧道 [1] => 文林 [2] => 梅峰 [3] => 延伸线 [4] => 施工 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 79194 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79194.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79194.html [published_timestamp] => 1554603356 [published] => 1554603356 [pv] => 782 [virtual_pv] => 482 [all_pv] => 782 [title] => 逾千公里绿道“串”起幸福新生活 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/d989e3c66193b3614ea1851cd0f8b8d4.jpg ) [1] => Array ( [relateid] => 79176 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79176.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79176.html [published_timestamp] => 1554600175 [published] => 1554600175 [pv] => 474 [virtual_pv] => 457 [all_pv] => 474 [title] => 闽侯县社会福利中心力争4月底竣工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/6141e1592ec626710a6459b42ebb9bfd.jpeg ) [2] => Array ( [relateid] => 79167 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79167.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79167.html [published_timestamp] => 1554599704 [published] => 1554599704 [pv] => 701 [virtual_pv] => 427 [all_pv] => 701 [title] => 南二环新增大树约一万棵 林荫快速通道月底基本建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/9ef6e4f83f6352eb20f00cbaa8de336d.jpeg ) [3] => Array ( [relateid] => 79140 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79140.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79140.html [published_timestamp] => 1554549626 [published] => 1554549626 [pv] => 868 [virtual_pv] => 437 [all_pv] => 868 [title] => 福州今年将完成1100公里管网升级 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/580834ba25448ec83a7acecb499700bd.jpeg ) [4] => Array ( [relateid] => 79128 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79128.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79128.html [published_timestamp] => 1554549106 [published] => 1554549106 [pv] => 733 [virtual_pv] => 430 [all_pv] => 733 [title] => 滨海新城教育配套加速推进 多所学校9月投用 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/3650809f84b86a026ea355879e462023.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/391f8a9eb8026693f449fd9d4fb525f9.JPG ) 1

工业北路延伸线工程进展顺利 文林山隧道开始掘进 预计明年完工

2019-04-07 19:21   福州新闻  

作为福州城区第二批治堵重大项目和省重点工程之一,工业北路延伸线工程建设进展顺利,靠近梅峰路的文林山隧道口施工已结束。目前,全长近2公里的隧道开始掘进,预计明年上半年贯通。

记者在位于梅峰山地公园附近的施工现场看到,几台大型设备正加紧作业。目前,该工程文林山隧道洞口施工已全部完成,施工方正在进行隧道掘进开挖工作。据介绍,由于隧道下穿临近梅峰山地公园,附近居民区多。因此,保障施工安全,防止人为施工因素造成地质灾害,成为施工方首要解决的问题。

工业北路延伸线工程项目部副经理 孙玉伟:在下穿过梅峰公园景观水池的时候,我们(采用)超前管幕(支撑),超前管幕长度达到90米,在国内都是比较领先的,最大优点就是能保护山地公园景观水池的原状,能确保将来我们隧道开挖之后,景观水池不渗漏,还能保证不下沉。

据了解,工业北路延伸线工程分南北两段,此次先行动建的为南段部分,南起工业路与杨桥路交叉口,沿工业路往北延伸,通过隧道穿越文林山,全长1.841公里。其中,文林山隧道长1.1公里,设有"一小两大"的三洞隧道,除了2个单向4车道的机动车隧道外,还将建设1个供行人和非机动车通行的慢行隧道,预计2020年完工。届时将有助于分流西二环车辆,直接缓解象山隧道、尤溪洲大桥的交通压力。

来源:福州新闻
编辑:王蕾 责编:林真贞