Array ( [id] => 79542 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁6号线又有新进展啦!看这里…… [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-04-08 19:26:47 [createdby] => 10052 [createdip] => 192.168.12.8 [published] => 2019-04-08 19:26:47 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 891 [virtual_pv] => 422 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 1 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

地铁6号线又传来好消息!位于郑和西路和会堂路交叉口西侧的福州地铁6号线2标郑和站,主体结构顺利封顶!

郑和站位于郑和西路和会堂路交叉口西侧,沿郑和西路呈东西向布置,为地下二层双柱三跨岛式车站,长292m,标准段宽21.7m,联络线连接位置宽30.65m,建筑面积为17101.34㎡,深约16.93-19.21m,设2组风亭、3个出入口,1个消防出入口。

郑和站

据了解,项目部通过合理优化配置资源,克服周边环境复杂、施工难度大、工期紧、安全预控风险高等诸多困难,边建点边施工。在施工过程中,坚持高标准文明施工管理工作,在场地内出入口处设置了车辆冲洗设施、环境监控系统、雾炮机、围挡喷淋系统等设施,并种植相应的绿化,创造园林式施工环境。

在安全管理上,项目部本着“安全第一,预防为主,综合治理”的安全生产方针,“全员、全过程、全方位、全天候”的安全管理原则,在车站设置安全体验馆、VR体验教育基地、多媒体教育室等,提高作业人员安全意识。经过大家持之以恒的努力,提前完成了既定节点工期目标。

郑和站的顺利封顶,不仅为后期施工奠定良好基础,也加速了福州地铁6号线的施工建设进程。

来源:最美长乐
编辑:王蕾 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 地铁6号线又传来好消息! [thumb] => [{"url":"\/a\/10001\/201904\/e2a508871408a5e874b952c6a9f4daf1.jpeg","id":"900666"}] [url] => /p/79542.html [all_pv] => 891 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 郑和 [1] => 施工 [2] => 号线 [3] => 安全 [4] => 西路 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 79512 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79512.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79512.html [published_timestamp] => 1554720877 [published] => 1554720877 [pv] => 256 [virtual_pv] => 449 [all_pv] => 256 [title] => 大雾袭福建沿海 多条闽台海上客运航线停航 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/8c766ee8215d2776ee5bcc1df97b1ad1.jpeg ) [1] => Array ( [relateid] => 79509 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79509.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79509.html [published_timestamp] => 1554720559 [published] => 1554720559 [pv] => 262 [virtual_pv] => 447 [all_pv] => 262 [title] => 中国·福州物联网产业创新发展中心月底完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/0a12c10add7c89afa68e5667de0af38c.jpeg ) [2] => Array ( [relateid] => 79506 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79506.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79506.html [published_timestamp] => 1554720139 [published] => 1554720139 [pv] => 611 [virtual_pv] => 420 [all_pv] => 611 [title] => 鼓楼区楼宇经济信息化系统上线 楼宇停车位信息一目了然 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/15f379e569ffb39c18d9fe533109c011.jpeg ) [3] => Array ( [relateid] => 79503 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79503.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79503.html [published_timestamp] => 1554720122 [published] => 1554720122 [pv] => 531 [virtual_pv] => 375 [all_pv] => 531 [title] => 新建商品房转移登记 3天搞定 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/1659a6e5b6f4a39b383ed7b84f7ec3a5.jpeg ) [4] => Array ( [relateid] => 79500 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79500.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79500.html [published_timestamp] => 1554719884 [published] => 1554719884 [pv] => 3541 [virtual_pv] => 424 [all_pv] => 3541 [title] => 福州四城区新建小区将建标准化泵房 可远程监控水质 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/67fa971d7d3915cb41877d9494818210.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/e2a508871408a5e874b952c6a9f4daf1.jpeg ) 1

福州地铁6号线又有新进展啦!看这里……

2019-04-08 19:26   福视悦动  

地铁6号线又传来好消息!位于郑和西路和会堂路交叉口西侧的福州地铁6号线2标郑和站,主体结构顺利封顶!

郑和站位于郑和西路和会堂路交叉口西侧,沿郑和西路呈东西向布置,为地下二层双柱三跨岛式车站,长292m,标准段宽21.7m,联络线连接位置宽30.65m,建筑面积为17101.34㎡,深约16.93-19.21m,设2组风亭、3个出入口,1个消防出入口。

郑和站

据了解,项目部通过合理优化配置资源,克服周边环境复杂、施工难度大、工期紧、安全预控风险高等诸多困难,边建点边施工。在施工过程中,坚持高标准文明施工管理工作,在场地内出入口处设置了车辆冲洗设施、环境监控系统、雾炮机、围挡喷淋系统等设施,并种植相应的绿化,创造园林式施工环境。

在安全管理上,项目部本着“安全第一,预防为主,综合治理”的安全生产方针,“全员、全过程、全方位、全天候”的安全管理原则,在车站设置安全体验馆、VR体验教育基地、多媒体教育室等,提高作业人员安全意识。经过大家持之以恒的努力,提前完成了既定节点工期目标。

郑和站的顺利封顶,不仅为后期施工奠定良好基础,也加速了福州地铁6号线的施工建设进程。