Array ( [id] => 79746 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 228国道长乐外文武围垦堤至下沙段路堤结合工程:路堤景"三位一体" 为滨海新城建设添彩 [editor] => (二审)翁彬冰 [has_thumb] => 1 [created] => 2019-04-09 19:18:29 [createdby] => 10022 [createdip] => 192.168.12.3 [published] => 2019-04-09 19:18:29 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1048 [virtual_pv] => 431 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 3 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

228国道长乐外文武围垦堤至下沙段路堤结合工程,是连接文武砂镇及江田镇的重要道路工程。项目包括公路和水利工程、配套园林景观等,整体工程预计2020年9月完工。

在项目的关键性节点工程----11孔排洪闸施工现场,施工人员正在加紧水闸桩基等下部结构施工。由于项目属于海上作业,受潮汐和季节影响较大,为了赶在6月台风季来临前完成水闸下部施工,项目部通过科学排班,不间断施工,力争在枯水期完成任务。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目副经理王炎山:我们总工期是按两个枯水期来施工,现在为了提前完成228项目的施工任务,以前原计划的两个枯水期施工,压缩到一个枯水期,至少能节约半年的施工工期。在(建设)过程中,我们也是加强巡视和监控,确保水闸优质安全高效的完成施工任务。

此外,项目还要对原有长近4000米的外文武海堤进行改造升级。施工方通过创新工艺,使用液压系统对加固海堤使用的预制件进行位移,在不造成植被破坏的同时,加快了制作速度,节约了场地空间。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目经理马春:我们没有用门吊,没有用大型起重设备吊车来进行移位,只是靠液压系统的移位,(预制件)直接出来之后,直接吊装到现场,我这种是移动式的,所以对整个滨海新城沿海的防护林,我们没有占用更多的场地。

该项目全长约5.42Km,起点接已建成的228国道南北澳至外文武围垦堤段,终点与下沙路衔接,设计时速60公里。项目还包含防风林、绿化带、木栈道等景观工程,将进一步完善当地路网,打造滨海新城黄金海岸线。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目副经理王炎山:建设完成以后就是一个海滨公园,以前如果说没有这条路,要在陆路绕行15公里,现在就是短短的五公里,连接了文武砂和江田,一个是休闲娱乐,再一个是推动整个滨海新城发展。

来源:福州新闻
编辑:翁彬冰 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201904\/13d9af75fd7b0625ec16e10936b81519.JPG","id":"903036"}] [url] => /p/79746.html [all_pv] => 1048 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 228 [1] => 下沙 [2] => 施工 [3] => 文武 [4] => 路堤 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 79716 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79716.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79716.html [published_timestamp] => 1554807757 [published] => 1554807757 [pv] => 664 [virtual_pv] => 410 [all_pv] => 664 [title] => 滨海新城将添黄金海岸线 明年9月完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/0c7c8e02b9e05f68c05e6272e59d5155.jpeg ) [1] => Array ( [relateid] => 79584 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79584.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79584.html [published_timestamp] => 1554776155 [published] => 1554776155 [pv] => 425 [virtual_pv] => 380 [all_pv] => 425 [title] => 这是吃货们春天必吃的甜品,一起学起来! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/2217f606ca18d255f8a0d3a927e38159.jpeg ) [2] => Array ( [relateid] => 79572 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79572.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79572.html [published_timestamp] => 1554774850 [published] => 1554774850 [pv] => 472 [virtual_pv] => 434 [all_pv] => 472 [title] => 永泰欧乐堡水上世界拟6月开放 引进设施50多台套 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/df55cf50dec81c38f44eb7f1d39f87c2.jpeg ) [3] => Array ( [relateid] => 79569 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79569.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79569.html [published_timestamp] => 1554774638 [published] => 1554774638 [pv] => 519 [virtual_pv] => 382 [all_pv] => 519 [title] => 马尾罗星儿童学园进入装修阶段 计划今年9月开园 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/1fa180da15d49730e8c20a8f92958e5a.jpeg ) [4] => Array ( [relateid] => 79566 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/79566.html [wapUrl] => http://m.fztvapp.zohi.tv/p/79566.html [published_timestamp] => 1554774268 [published] => 1554774268 [pv] => 439 [virtual_pv] => 470 [all_pv] => 439 [title] => 有福之州绿道美打造城市园林 让市民尽享山水美景 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/3516ba3f19cc031ba677830b16cc9e6f.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/13d9af75fd7b0625ec16e10936b81519.JPG ) 1

228国道长乐外文武围垦堤至下沙段路堤结合工程:路堤景"三位一体" 为滨海新城建设添彩

2019-04-09 19:18   福州新闻  

228国道长乐外文武围垦堤至下沙段路堤结合工程,是连接文武砂镇及江田镇的重要道路工程。项目包括公路和水利工程、配套园林景观等,整体工程预计2020年9月完工。

在项目的关键性节点工程----11孔排洪闸施工现场,施工人员正在加紧水闸桩基等下部结构施工。由于项目属于海上作业,受潮汐和季节影响较大,为了赶在6月台风季来临前完成水闸下部施工,项目部通过科学排班,不间断施工,力争在枯水期完成任务。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目副经理王炎山:我们总工期是按两个枯水期来施工,现在为了提前完成228项目的施工任务,以前原计划的两个枯水期施工,压缩到一个枯水期,至少能节约半年的施工工期。在(建设)过程中,我们也是加强巡视和监控,确保水闸优质安全高效的完成施工任务。

此外,项目还要对原有长近4000米的外文武海堤进行改造升级。施工方通过创新工艺,使用液压系统对加固海堤使用的预制件进行位移,在不造成植被破坏的同时,加快了制作速度,节约了场地空间。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目经理马春:我们没有用门吊,没有用大型起重设备吊车来进行移位,只是靠液压系统的移位,(预制件)直接出来之后,直接吊装到现场,我这种是移动式的,所以对整个滨海新城沿海的防护林,我们没有占用更多的场地。

该项目全长约5.42Km,起点接已建成的228国道南北澳至外文武围垦堤段,终点与下沙路衔接,设计时速60公里。项目还包含防风林、绿化带、木栈道等景观工程,将进一步完善当地路网,打造滨海新城黄金海岸线。

228国道长乐外文武围垦堤至下沙段路堤结合工程项目副经理王炎山:建设完成以后就是一个海滨公园,以前如果说没有这条路,要在陆路绕行15公里,现在就是短短的五公里,连接了文武砂和江田,一个是休闲娱乐,再一个是推动整个滨海新城发展。

来源:福州新闻
编辑:翁彬冰 责编:庄颖