Array ( [id] => 80142 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁5号线最新进展 [editor] => (二审)林昱星 [has_thumb] => 1 [created] => 2019-04-11 12:57:37 [createdby] => 10006 [createdip] => 192.168.12.6 [published] => 2019-04-11 12:57:37 [publishedby] => 10006 [modified] => 2019-04-11 13:15:33 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 1325 [virtual_pv] => 416 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 2 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

按线网规划,福州地铁5号线为西北至东南走向。一期工程起于荆溪新城站,终于福州火车南站站。全长约27.7公里,设站20座,途经闽侯、金山、义序、荆溪新城等,连接奥体中心、福州南站。有望在帝封江站与长乐机场城际铁路换乘。一期预计2021年9月30日前通车试运行。具体线路图如下:



截至3月31日,除火车南站外,其余19个站已动工,3个站主体封顶,9个站正进行主体结构施工。

3月24日,高仕路站至螺洲镇站区间,成功实现左线贯通。该区间成为5号线首个实现双向贯通的区间。车辆采购项目招标已经发布,5号线一期工程将采购22列(共132辆)辆电动客车。



据介绍,5号线高仕路站至螺洲镇站区间由中铁十二局集团一公司承建。今年1月19日,该区间右线顺利贯通,成为5号线首个实现贯通的作业区间。目前,该区间又成功实现左线贯通。至此,该区间左右线均已完成掘进,成为全线首个双向贯通的区间。此外,“福州市轨道交通5号线一期工程车辆采购项目”招标公告已经公布。就5号线一期工程车辆采购项目,进行国内公开招标。



根据公告,5号线一期工程将采购22列(共132辆)辆电动客车,主要规格为“B2”型电动客车。项目最高限价为人民币82104万元(综合单价622万/辆,含牵引系统),首列车的交货日期为2020年12月(暂定)。

福州地铁5号线建成后,将与1、2、4号线在城市中心区形成“十字+环”的布局,连接荆溪组团、金山片区、义序片区、南台岛东部片区、福州南站等城市重点发展区域,对于支撑南台岛发展,加强外围组团与中心城区联系,实现轨道交通网络整体效益具有重要作用。

来源:福视悦动微信公众号
编辑:黄鑫 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201904\/e4ee429d5914bf63ac667a351515bbaa.jpeg","id":"909366"}] [url] => /p/80142.html [all_pv] => 1325 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 福州 [2] => 地铁 [3] => 南站 [4] => 贯通 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 80124 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80124.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80124.html [published_timestamp] => 1554952006 [published] => 1554952006 [pv] => 610 [virtual_pv] => 439 [all_pv] => 610 [title] => 融媒体视点丨网络遗产能不能继承? [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201904/9ac6eb47cde4e179929ac6f05a0ddc46.jpg@w960_h540.jpg ) [1] => Array ( [relateid] => 80118 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80118.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80118.html [published_timestamp] => 1554951221 [published] => 1554951221 [pv] => 572 [virtual_pv] => 377 [all_pv] => 572 [title] => 福建平潭“蓝眼泪”如期而至 如“阿凡达”般震撼 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/920c044c03c4dc8267e6d40a3dd3a67e.jpeg ) [2] => Array ( [relateid] => 80115 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80115.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80115.html [published_timestamp] => 1554950547 [published] => 1554950547 [pv] => 506 [virtual_pv] => 473 [all_pv] => 506 [title] => 助力垃圾分类 志愿者在行动 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/134e7508f81baf3b9201a0576c103485.jpeg ) [3] => Array ( [relateid] => 80109 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80109.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80109.html [published_timestamp] => 1554950104 [published] => 1554950104 [pv] => 488 [virtual_pv] => 477 [all_pv] => 488 [title] => 东湖数字小镇加紧施工 多个路桥项目月底建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/e380c1931ef59af3ea7cd799b9ba7888.jpeg ) [4] => Array ( [relateid] => 80100 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80100.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80100.html [published_timestamp] => 1554948491 [published] => 1554948491 [pv] => 709 [virtual_pv] => 413 [all_pv] => 709 [title] => 两岸媒体聚焦“台农在福州”:一起听台农讲福州故事 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/540f48287ecd26c7e8dd76207dc8a25a.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/e4ee429d5914bf63ac667a351515bbaa.jpeg ) 1

福州地铁5号线最新进展

2019-04-11 12:57   福视悦动  

按线网规划,福州地铁5号线为西北至东南走向。一期工程起于荆溪新城站,终于福州火车南站站。全长约27.7公里,设站20座,途经闽侯、金山、义序、荆溪新城等,连接奥体中心、福州南站。有望在帝封江站与长乐机场城际铁路换乘。一期预计2021年9月30日前通车试运行。具体线路图如下:



截至3月31日,除火车南站外,其余19个站已动工,3个站主体封顶,9个站正进行主体结构施工。

3月24日,高仕路站至螺洲镇站区间,成功实现左线贯通。该区间成为5号线首个实现双向贯通的区间。车辆采购项目招标已经发布,5号线一期工程将采购22列(共132辆)辆电动客车。



据介绍,5号线高仕路站至螺洲镇站区间由中铁十二局集团一公司承建。今年1月19日,该区间右线顺利贯通,成为5号线首个实现贯通的作业区间。目前,该区间又成功实现左线贯通。至此,该区间左右线均已完成掘进,成为全线首个双向贯通的区间。此外,“福州市轨道交通5号线一期工程车辆采购项目”招标公告已经公布。就5号线一期工程车辆采购项目,进行国内公开招标。



根据公告,5号线一期工程将采购22列(共132辆)辆电动客车,主要规格为“B2”型电动客车。项目最高限价为人民币82104万元(综合单价622万/辆,含牵引系统),首列车的交货日期为2020年12月(暂定)。

福州地铁5号线建成后,将与1、2、4号线在城市中心区形成“十字+环”的布局,连接荆溪组团、金山片区、义序片区、南台岛东部片区、福州南站等城市重点发展区域,对于支撑南台岛发展,加强外围组团与中心城区联系,实现轨道交通网络整体效益具有重要作用。

来源:福视悦动微信公众号
编辑:黄鑫 责编:林真贞