Array ( [id] => 81852 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 闽侯二桥南北两岸同时施工 预计8月完成栈桥平台搭设 [editor] => (二审)林昱星 [has_thumb] => 1 [created] => 2019-04-19 09:45:24 [createdby] => 10006 [createdip] => 192.168.12.200 [published] => 2019-04-19 09:45:24 [publishedby] => 10006 [modified] => 2019-04-19 10:09:54 [modifiedby] => 10019 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 769 [virtual_pv] => 486 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

记者昨日从闽侯县获悉,闽侯近年来单体投资最大的民生工程——闽侯二桥,目前南北岸均已启动施工,预计8月完成栈桥及钻孔平台搭设。

闽侯二桥起于316国道竹岐段,止于县城滨城大道,全长3.535公里。大桥设置南北互通,北岸互通与闽侯县城北滨江路连接,南岸互通接竹岐新区滨江路。

闽侯县交通局相关负责人介绍,该桥是闽侯首座双塔斜拉桥,桥梁建设采用水滴型双塔斜拉桥方案,设计标准为城市主干道,主线设计速度60公里/小时,双向六车道并设人行道和非机动车道。值得一提的是,大桥主跨最大跨径达280米,通航标准达到内河航道Ⅳ级,通航净高大于8米,便于通航。

“整个项目工期为32个月。”施工单位中交二航局相关负责人黄耀文告诉记者,他们将结合闽侯二桥工程特点、地质条件和环境,对项目建设的各个节点进行统筹安排,将采取南北两岸同时施工、流水作业的推进方式,同时将在水上搭设临时栈桥和钻孔平台。

记者昨日在现场看到,项目北岸围挡施工已完成,堆场平整,周转材料转运顺利,工人正配合机械开展施工栈道建设。南岸围挡内施工同步启动。

黄耀文介绍,根据计划,预计今年8月完成栈桥及钻孔平台搭设,并开始主桥桩基施工;2020年11月完成主塔封顶;2021年7月完成主桥合龙;2021年12月完成桥面、交安、机电及绿化施工。

“闽侯二桥是连接县城、荆溪镇和竹岐新区的全新跨江通道。”闽侯县交通局相关负责人表示,闽侯二桥建成通车后,可实现和地铁的快速对接,提升闽侯交通服务水平。


来源:福州日报
编辑:林昱星 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 预计8月完成栈桥及钻孔平台搭设 [thumb] => [{"url":"\/a\/10001\/201904\/c632409146f81a106e26cd577c51e5c3.jpeg","id":"937233"}] [url] => /p/81852.html [all_pv] => 769 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 闽侯 [1] => 二桥 [2] => 施工 [3] => 闽侯县 [4] => 搭设 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 81816 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81816.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81816.html [published_timestamp] => 1555637162 [published] => 1555637162 [pv] => 442 [virtual_pv] => 461 [all_pv] => 442 [title] => 2019年“数字党建”高峰论坛27日在榕举办 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/330067480d3d415fb7de23a00335eade.jpeg ) [1] => Array ( [relateid] => 81801 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81801.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81801.html [published_timestamp] => 1555588709 [published] => 1555588709 [pv] => 372 [virtual_pv] => 415 [all_pv] => 372 [title] => 踏青首选!飞瀑、虹桥...市区这座公园藏着最美春色 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/e979219c70661154fc1a172c4cc312bb.jpeg ) [2] => Array ( [relateid] => 81795 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81795.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81795.html [published_timestamp] => 1555588563 [published] => 1555588563 [pv] => 278 [virtual_pv] => 471 [all_pv] => 278 [title] => 鼓楼举办纳税人学堂 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/fbb4931458642008c26c64aacb5b8559.JPG ) [3] => Array ( [relateid] => 81789 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81789.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81789.html [published_timestamp] => 1555588533 [published] => 1555588533 [pv] => 526 [virtual_pv] => 436 [all_pv] => 526 [title] => 台籍教师吕英志:教书育人 追梦榕城 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/0ff4c1946f2669925c448e6e3ee71374.JPG ) [4] => Array ( [relateid] => 81783 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/81783.html [wapUrl] => http://m.fztvapp.zohi.tv/p/81783.html [published_timestamp] => 1555588413 [published] => 1555588413 [pv] => 359 [virtual_pv] => 450 [all_pv] => 359 [title] => 第二届数字中国建设峰会各项筹备工作进展顺利 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/6fb9a7e9fd0626272d28a349d654acae.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/201904/c632409146f81a106e26cd577c51e5c3.jpeg ) 1

闽侯二桥南北两岸同时施工 预计8月完成栈桥平台搭设

2019-04-19 09:45   福视悦动  

记者昨日从闽侯县获悉,闽侯近年来单体投资最大的民生工程——闽侯二桥,目前南北岸均已启动施工,预计8月完成栈桥及钻孔平台搭设。

闽侯二桥起于316国道竹岐段,止于县城滨城大道,全长3.535公里。大桥设置南北互通,北岸互通与闽侯县城北滨江路连接,南岸互通接竹岐新区滨江路。

闽侯县交通局相关负责人介绍,该桥是闽侯首座双塔斜拉桥,桥梁建设采用水滴型双塔斜拉桥方案,设计标准为城市主干道,主线设计速度60公里/小时,双向六车道并设人行道和非机动车道。值得一提的是,大桥主跨最大跨径达280米,通航标准达到内河航道Ⅳ级,通航净高大于8米,便于通航。

“整个项目工期为32个月。”施工单位中交二航局相关负责人黄耀文告诉记者,他们将结合闽侯二桥工程特点、地质条件和环境,对项目建设的各个节点进行统筹安排,将采取南北两岸同时施工、流水作业的推进方式,同时将在水上搭设临时栈桥和钻孔平台。

记者昨日在现场看到,项目北岸围挡施工已完成,堆场平整,周转材料转运顺利,工人正配合机械开展施工栈道建设。南岸围挡内施工同步启动。

黄耀文介绍,根据计划,预计今年8月完成栈桥及钻孔平台搭设,并开始主桥桩基施工;2020年11月完成主塔封顶;2021年7月完成主桥合龙;2021年12月完成桥面、交安、机电及绿化施工。

“闽侯二桥是连接县城、荆溪镇和竹岐新区的全新跨江通道。”闽侯县交通局相关负责人表示,闽侯二桥建成通车后,可实现和地铁的快速对接,提升闽侯交通服务水平。