Array ( [id] => 84588 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 机场高速下国货互通环岛新匝道今日通车 [editor] => (二审)庄颖 [has_thumb] => 1 [created] => 2019-05-01 13:39:29 [createdby] => 10125 [createdip] => 117.29.100.70 [published] => 2019-05-01 13:39:29 [publishedby] => 10125 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 881 [virtual_pv] => 412 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 2 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

机场高速下国货互通环岛新匝道今日通车。

昨日,记者从市城乡建设局获悉,作为城区第二批治堵项目和2019年为民办实事项目,国货互通立交改造工程首条“长辫”——机场高速下国货互通环岛今日通车。年内,剩余3条匝道也将陆续建成,让该互通更通达、更便捷。

2010年,国货互通立交建成通车。这条连接机场高速公路的枢纽互通,与远洋路、鼓山大桥(二环、三环联络线)形成高架的“快快联系”。为增强该互通立交与地面三环辅路间的联系,最大程度方便市民出行,我市启动国货互通立交改造,为其新添4条“长辫”。

今日首条匝道开放通行

昨日上午,记者来到国货互通环岛旁的改造项目现场。为确保如期通车,新匝道的面层沥青铺设、标线施划、卫生清扫等收尾工作有条不紊地推进。“桥梁检测工作即将展开,确保安全放心通行。”市建发集团下属福州市政建设开发公司该项目负责人陈明跃说。

据了解,这条新“辫子”长573米,为单向2车道,设计时速40公里。为确保匝道在第二届数字中国建设峰会前实现通车,市城乡建设局、市建发集团及市政建设开发公司紧盯目标节点,加速展开攻坚,确保每一节点进度均按既定目标全面推进。

“项目紧邻全省最大的污水厂洋里污水处理厂,但匝道施工需要对厂区专线电缆进行迁改,确保厂内污水处理工作不受影响,是我们工作的重中之重。”陈明跃说,他们与公司管线部工作人员密切配合,与相关单位多次协商优化方案,在市城乡建设局等上级部门的协调推进下,确保电缆迁改与厂区的污水处理工作携手并进。

除了各类繁复的迁改工作,该匝道施工还与内河“相遇”。面对整治后呈现新貌的洋里溪,以保护生态为核心原则,该段匝道从原本的现浇混凝土施工转为钢箱梁架设,从河上飞跨。“既能避免在河中打桩影响水质及生态,又能提高施工效率,一举两得。”陈明跃说。

今日,这条新匝道就将开放迎客。它的建成,能让从机场高速方向的来车快速进入国货互通环岛,通过环岛,实现与远洋路、鳌峰路、福马路等方向的互联互通,让“空中”与地面出行都能一路通达。

整体工程年底全面建成

“服役”近9年,国货互通与远洋路、鼓山大桥等“牵手”并行,架起出行快速路。因和地面三环辅路的“联系”较少,导致地面辅路车流均需绕行远洋路、福光路掉头后,方可进入该枢纽互通,一定程度上加剧了远洋路、福光路的交通压力。

“这4条新建匝道,就针对这一短板,完善国货交通节点功能,实现地面与高架交通流快速、有序转换。”陈明跃说,除今日通车的匝道外,鼓山大桥下国货互通环岛(长552米)、国货互通环岛上鼓山大桥(长303米)及国货互通环岛上机场高速(长804米)等3条匝道均已展开施工,桩基、承台等作业同步推进。

剩余新匝道施工同样不轻松。眼下整体工程量已完成60%,年底前可陆续开放通行。今后,这4条新匝道将成为三环辅路上下机场高速及鼓山大桥的便捷通道,让国货互通环岛互联互通的作用进一步完善。同时,缓解远洋路、福光路、福马路等周边路网的交通压力,盘活区域路网。

除新匝道外,长544米的桥下辅路年底前将建成。该辅路起于江滨中大道,止于鳌峰路。此外,同步建设2座非机动车天桥,连接鼓山大桥与鳌港路,完善鼓山大桥的通行功能。


来源:福州日报
编辑:简晓华 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 今日,这条新匝道就将开放迎客。 [thumb] => [{"url":"\/a\/10001\/201905\/90fe782f809f57dc794ef7e0f8f79271.jpeg","id":"983526"}] [url] => /p/84588.html [all_pv] => 881 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 匝道 [1] => 互通 [2] => 国货 [3] => 环岛 [4] => 鼓山 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 84579 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84579.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84579.html [published_timestamp] => 1556673772 [published] => 1556673772 [pv] => 440 [virtual_pv] => 415 [all_pv] => 440 [title] => 5月1日起!福州这些公交线路将调整! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/f599415b5efabea017b035a688bde7c3.jpeg ) [1] => Array ( [relateid] => 84546 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84546.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84546.html [published_timestamp] => 1556670068 [published] => 1556670068 [pv] => 429 [virtual_pv] => 389 [all_pv] => 429 [title] => 今日通车!福州又一重大缓堵项目即将完工! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/24bcffcd8cf9846759ca492969e06cd8.jpeg ) [2] => Array ( [relateid] => 84537 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84537.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84537.html [published_timestamp] => 1556669705 [published] => 1556669705 [pv] => 568 [virtual_pv] => 473 [all_pv] => 568 [title] => 福州地铁1号线、2号线“五一”加开列车时刻表来啦! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/70fa9994901c1f92ebff462d26eefcc2.jpeg ) [3] => Array ( [relateid] => 84474 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84474.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84474.html [published_timestamp] => 1556623122 [published] => 1556623122 [pv] => 214 [virtual_pv] => 393 [all_pv] => 214 [title] => 我市又一批道路建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/437b0b94134d55e6690d84821285aa2f.JPG ) [4] => Array ( [relateid] => 84405 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84405.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84405.html [published_timestamp] => 1556606101 [published] => 1556606101 [pv] => 732 [virtual_pv] => 442 [all_pv] => 732 [title] => 【大美福州】五一小长假去哪玩?这些打卡点不要错过 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/bc46cbb2c6aecb52a1af6f1dbe39caf0.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201905/90fe782f809f57dc794ef7e0f8f79271.jpeg ) 1

机场高速下国货互通环岛新匝道今日通车

2019-05-01 13:39   福视悦动  

机场高速下国货互通环岛新匝道今日通车。

昨日,记者从市城乡建设局获悉,作为城区第二批治堵项目和2019年为民办实事项目,国货互通立交改造工程首条“长辫”——机场高速下国货互通环岛今日通车。年内,剩余3条匝道也将陆续建成,让该互通更通达、更便捷。

2010年,国货互通立交建成通车。这条连接机场高速公路的枢纽互通,与远洋路、鼓山大桥(二环、三环联络线)形成高架的“快快联系”。为增强该互通立交与地面三环辅路间的联系,最大程度方便市民出行,我市启动国货互通立交改造,为其新添4条“长辫”。

今日首条匝道开放通行

昨日上午,记者来到国货互通环岛旁的改造项目现场。为确保如期通车,新匝道的面层沥青铺设、标线施划、卫生清扫等收尾工作有条不紊地推进。“桥梁检测工作即将展开,确保安全放心通行。”市建发集团下属福州市政建设开发公司该项目负责人陈明跃说。

据了解,这条新“辫子”长573米,为单向2车道,设计时速40公里。为确保匝道在第二届数字中国建设峰会前实现通车,市城乡建设局、市建发集团及市政建设开发公司紧盯目标节点,加速展开攻坚,确保每一节点进度均按既定目标全面推进。

“项目紧邻全省最大的污水厂洋里污水处理厂,但匝道施工需要对厂区专线电缆进行迁改,确保厂内污水处理工作不受影响,是我们工作的重中之重。”陈明跃说,他们与公司管线部工作人员密切配合,与相关单位多次协商优化方案,在市城乡建设局等上级部门的协调推进下,确保电缆迁改与厂区的污水处理工作携手并进。

除了各类繁复的迁改工作,该匝道施工还与内河“相遇”。面对整治后呈现新貌的洋里溪,以保护生态为核心原则,该段匝道从原本的现浇混凝土施工转为钢箱梁架设,从河上飞跨。“既能避免在河中打桩影响水质及生态,又能提高施工效率,一举两得。”陈明跃说。

今日,这条新匝道就将开放迎客。它的建成,能让从机场高速方向的来车快速进入国货互通环岛,通过环岛,实现与远洋路、鳌峰路、福马路等方向的互联互通,让“空中”与地面出行都能一路通达。

整体工程年底全面建成

“服役”近9年,国货互通与远洋路、鼓山大桥等“牵手”并行,架起出行快速路。因和地面三环辅路的“联系”较少,导致地面辅路车流均需绕行远洋路、福光路掉头后,方可进入该枢纽互通,一定程度上加剧了远洋路、福光路的交通压力。

“这4条新建匝道,就针对这一短板,完善国货交通节点功能,实现地面与高架交通流快速、有序转换。”陈明跃说,除今日通车的匝道外,鼓山大桥下国货互通环岛(长552米)、国货互通环岛上鼓山大桥(长303米)及国货互通环岛上机场高速(长804米)等3条匝道均已展开施工,桩基、承台等作业同步推进。

剩余新匝道施工同样不轻松。眼下整体工程量已完成60%,年底前可陆续开放通行。今后,这4条新匝道将成为三环辅路上下机场高速及鼓山大桥的便捷通道,让国货互通环岛互联互通的作用进一步完善。同时,缓解远洋路、福光路、福马路等周边路网的交通压力,盘活区域路网。

除新匝道外,长544米的桥下辅路年底前将建成。该辅路起于江滨中大道,止于鳌峰路。此外,同步建设2座非机动车天桥,连接鼓山大桥与鳌港路,完善鼓山大桥的通行功能。


来源:福州日报