Array ( [id] => 84990 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 桂后溪分流工程6月投用 将提升火车站及洋下片区排涝能力 [editor] => 林秀梅 [has_thumb] => 1 [created] => 2019-05-03 19:10:41 [createdby] => 10065 [createdip] => 192.168.12.13 [published] => 2019-05-03 19:10:41 [publishedby] => 10065 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 791 [virtual_pv] => 416 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

作为城区水系综合治理的重要组成部分,桂后溪分流工程正加速推进,预计6月完工并投入使用,届时将进一步提升火车站与洋下片区的排涝能力。

桂后溪分流工程位于三环路北侧,目前,一条长为1.08公里的隧洞已全部贯通,将登云水库和涧田湖连通起来。施工方正在加紧对两个设备房的主体施工,以及隧洞的二衬工作。

桂后溪分流工程施工方负责人杨恩强:主要建设功能是为了缓解火车站南北广场,还有洋下片区的内涝问题,兼有补水功能。补水主要是从登云水库放水到涧田湖,增加涧田湖水量,促进下游晋安河的水循环。

桂后溪分流工程承担着调节涧田湖和登云水库之间水位的功能。当汛期来临时,涧田湖的水位要是超过库容,桂后溪泵站将开始工作。湖水经过拦污栅净化后,通过泵站将湖水提升到39米高的位置。接着,湖水通过隧洞排到库容333万立方米的登云水库,从而实现低水高排。而在枯水季节时,则可通过隧洞将登云水库的水引入涧田湖。整体项目将于今年6月完成并投入使用。

来源:福州新闻
编辑:林秀梅 责编:卢明铭

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201905\/0612441b30f81a6033d2af2ab7ee78da.JPG","id":"989697"}] [url] => /p/84990.html [all_pv] => 791 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福州新闻 ) [2] => Array ( [0] => 田湖 [1] => 桂后 [2] => 登云 [3] => 隧洞 [4] => 水库 ) ) [menu] => 269 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 84978 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84978.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84978.html [published_timestamp] => 1556880954 [published] => 1556880954 [pv] => 114 [virtual_pv] => 405 [all_pv] => 114 [title] => 坚守岗位度"五一":我劳动 我快乐 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/46d5054f012dba49a0059a9bdb41d643.jpeg ) [1] => Array ( [relateid] => 84975 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84975.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84975.html [published_timestamp] => 1556880896 [published] => 1556880896 [pv] => 469 [virtual_pv] => 428 [all_pv] => 469 [title] => 第二届数字中国建设成果展览会亮点抢先看! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/bf6af86d87a93288e7de953a41de1005.jpeg ) [2] => Array ( [relateid] => 84960 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84960.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84960.html [published_timestamp] => 1556873046 [published] => 1556873046 [pv] => 363 [virtual_pv] => 430 [all_pv] => 363 [title] => 注意!三坊七巷部分景点暂时关闭! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/2311910f2d4ce2ea3f9dfc93aca9c08b.jpeg ) [3] => Array ( [relateid] => 84954 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84954.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84954.html [published_timestamp] => 1556872407 [published] => 1556872407 [pv] => 426 [virtual_pv] => 448 [all_pv] => 426 [title] => 返程别急,福州地铁延时收车,等你! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/8260ffbdebe8a127fc5e2cefa56f483b.jpeg ) [4] => Array ( [relateid] => 84942 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84942.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84942.html [published_timestamp] => 1556870357 [published] => 1556870357 [pv] => 329 [virtual_pv] => 417 [all_pv] => 329 [title] => 台江:分类垃圾桶假期“上岗” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/5f623a0b119f39d671fbac4a6117a920.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201905/0612441b30f81a6033d2af2ab7ee78da.JPG ) 1

桂后溪分流工程6月投用 将提升火车站及洋下片区排涝能力

2019-05-03 19:10   福州新闻  

作为城区水系综合治理的重要组成部分,桂后溪分流工程正加速推进,预计6月完工并投入使用,届时将进一步提升火车站与洋下片区的排涝能力。

桂后溪分流工程位于三环路北侧,目前,一条长为1.08公里的隧洞已全部贯通,将登云水库和涧田湖连通起来。施工方正在加紧对两个设备房的主体施工,以及隧洞的二衬工作。

桂后溪分流工程施工方负责人杨恩强:主要建设功能是为了缓解火车站南北广场,还有洋下片区的内涝问题,兼有补水功能。补水主要是从登云水库放水到涧田湖,增加涧田湖水量,促进下游晋安河的水循环。

桂后溪分流工程承担着调节涧田湖和登云水库之间水位的功能。当汛期来临时,涧田湖的水位要是超过库容,桂后溪泵站将开始工作。湖水经过拦污栅净化后,通过泵站将湖水提升到39米高的位置。接着,湖水通过隧洞排到库容333万立方米的登云水库,从而实现低水高排。而在枯水季节时,则可通过隧洞将登云水库的水引入涧田湖。整体项目将于今年6月完成并投入使用。

来源:福州新闻
编辑:林秀梅 责编:卢明铭

相关阅读

0 条评论
最新