Array ( [id] => 90804 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 鳌峰学校计划年底交付使用 为九年一贯制公立学校 [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-05-29 09:10:22 [createdby] => 10052 [createdip] => 192.168.12.8 [published] => 2019-05-29 09:10:22 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 516 [virtual_pv] => 418 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 0 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

记者28日获悉,在建的鳌峰学校计划年底交付使用,到时,台江区将新增一所区属九年一贯制公立学校。

28日,位于台江区福光南路与鳌兴路交汇处的鳌峰学校项目建设现场,高架塔吊在空中挥舞长臂,运输车在工地来回穿梭,工人争分夺秒抓紧施工……一派热火朝天的建设场景。

据悉,鳌峰学校项目总投资约4.6亿元,规划用地面积约46.7亩,总建筑面积5.8平方米,绿地率30.002%。主要建设4栋5层和4栋6层的教学综合楼及附属办公室,按标准化学校添置教学设备、水电增容等,按66班(在校生3090人)配置,其中小学42班,初中24班。这所位于台江“东翼”上的学校建成后,将有效缓解海峡金融商务区一带的入学压力。

代建单位福州江滨建设开发公司工程部副经理江翼介绍,鳌峰学校项目自去年10月开工以来,平均每天有200多名工人在现场施工,施工期间节假日及农历春节均正常施工,至今已连续施工超过200天。目前,项目主体结构1号楼已经封顶,其他建筑也正在加快建设。“在台江区委、区政府关心支持及各参建单位共同努力下,我们计划于6月底主体结构全面封顶,年底全面竣工交付使用。”江翼说。

建设速度快马加鞭,工程质量精益求精。柱筋绑扎样板、电渣压力焊接头样板、横向斜撑样板……在工地一侧,一个样板展示区格外引人注目。“我们在每一道工序施工前都会先做一个样板。现场质量、安全文明等严格按照省标化工地执行。”江翼介绍,由于现场施工人员很多,工艺参差不齐,而样本化施工为每一位工人提供一个标准的工艺,做到标准化施工,确保工程的质量。

值得一提的是,为了进一步落实有关校园安全的要求,确保学生安全进出校园,鳌峰学校项目充分利用地下空间,地下建筑面积达到1.9万平方米,地下室面积作为停车及设备用房等使用,可停非机动车1000辆,机动车110辆,实现人车分流。此外,地下室在设计上充分考虑到采光、通风等问题,步入地下室并没有印象中一般地下室阴暗潮湿的感觉。

“鳌峰学校总体布局采用‘一环E型’三区的结构形式。”江翼介绍,“一环”为校园的主要交通环;“E型”为综合教学楼平面布置的中小学教学、实验室、报告厅、图书馆、阅览室、活动室、学生食堂、教职办公室和行政办公室等综合设施连通校园主要建筑;三区为依附道路主环的三大主要功能区,分别是教学楼、生活区、体育活动区。此外,三区以教学区为中心,动静有隔,有分有连,疏密相间。

来源:福州日报
编辑:王蕾 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 到时,台江区将新增一所区属九年一贯制公立学校。 [thumb] => [{"url":"\/a\/10001\/201905\/31389c8fd4433aef69c597f403b479a8.jpeg","id":"1037562"}] [url] => /p/90804.html [all_pv] => 516 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 鳌峰 [1] => 施工 [2] => 样板 [3] => 学校 [4] => 地下室 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 32967 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32967.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32967.html [published_timestamp] => 1536491530 [published] => 1536491530 [pv] => 1401 [virtual_pv] => 388 [all_pv] => 1401 [title] => 鳌峰洲大桥新增匝道 力争明年春节前通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201809/c3aa1bf0317a2bbb2cfdab4cfdd86beb.jpeg@w553_h415.jpeg ) [1] => Array ( [relateid] => 32052 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/32052.html [wapUrl] => http://m.fztvapp.zohi.tv/p/32052.html [published_timestamp] => 1536196944 [published] => 1536196944 [pv] => 865 [virtual_pv] => 449 [all_pv] => 865 [title] => 推广标准化作业 地铁施工有“样板间” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201809/2d7fa230706bd6328b770cee265844f5.png ) [2] => Array ( [relateid] => 62052 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/62052.html [wapUrl] => http://m.fztvapp.zohi.tv/p/62052.html [published_timestamp] => 1547724091 [published] => 1547724091 [pv] => 419 [virtual_pv] => 457 [all_pv] => 419 [title] => 滨海新城综合医院:保质保量加快施工 4月完成医技楼结构封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/0ac5c17b69caa3c6e8e9a46705ebb168.JPG ) [3] => Array ( [relateid] => 39198 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39198.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39198.html [published_timestamp] => 1538964169 [published] => 1538964169 [pv] => 612 [virtual_pv] => 453 [all_pv] => 612 [title] => 持续攻坚不停步 福州缓堵项目国庆施工全面提速 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/8b840de03eca13478837c58ae633fb01.jpeg ) [4] => Array ( [relateid] => 80730 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/80730.html [wapUrl] => http://m.fztvapp.zohi.tv/p/80730.html [published_timestamp] => 1555205704 [published] => 1555205704 [pv] => 350 [virtual_pv] => 463 [all_pv] => 350 [title] => 青口拆迁安置房二期有序推进 年底建成地下室主体 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/9dc6951e6314fe1228a2dc319563e0c9.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201905/31389c8fd4433aef69c597f403b479a8.jpeg ) 1

鳌峰学校计划年底交付使用 为九年一贯制公立学校

2019-05-29 09:10   福视悦动  

记者28日获悉,在建的鳌峰学校计划年底交付使用,到时,台江区将新增一所区属九年一贯制公立学校。

28日,位于台江区福光南路与鳌兴路交汇处的鳌峰学校项目建设现场,高架塔吊在空中挥舞长臂,运输车在工地来回穿梭,工人争分夺秒抓紧施工……一派热火朝天的建设场景。

据悉,鳌峰学校项目总投资约4.6亿元,规划用地面积约46.7亩,总建筑面积5.8平方米,绿地率30.002%。主要建设4栋5层和4栋6层的教学综合楼及附属办公室,按标准化学校添置教学设备、水电增容等,按66班(在校生3090人)配置,其中小学42班,初中24班。这所位于台江“东翼”上的学校建成后,将有效缓解海峡金融商务区一带的入学压力。

代建单位福州江滨建设开发公司工程部副经理江翼介绍,鳌峰学校项目自去年10月开工以来,平均每天有200多名工人在现场施工,施工期间节假日及农历春节均正常施工,至今已连续施工超过200天。目前,项目主体结构1号楼已经封顶,其他建筑也正在加快建设。“在台江区委、区政府关心支持及各参建单位共同努力下,我们计划于6月底主体结构全面封顶,年底全面竣工交付使用。”江翼说。

建设速度快马加鞭,工程质量精益求精。柱筋绑扎样板、电渣压力焊接头样板、横向斜撑样板……在工地一侧,一个样板展示区格外引人注目。“我们在每一道工序施工前都会先做一个样板。现场质量、安全文明等严格按照省标化工地执行。”江翼介绍,由于现场施工人员很多,工艺参差不齐,而样本化施工为每一位工人提供一个标准的工艺,做到标准化施工,确保工程的质量。

值得一提的是,为了进一步落实有关校园安全的要求,确保学生安全进出校园,鳌峰学校项目充分利用地下空间,地下建筑面积达到1.9万平方米,地下室面积作为停车及设备用房等使用,可停非机动车1000辆,机动车110辆,实现人车分流。此外,地下室在设计上充分考虑到采光、通风等问题,步入地下室并没有印象中一般地下室阴暗潮湿的感觉。

“鳌峰学校总体布局采用‘一环E型’三区的结构形式。”江翼介绍,“一环”为校园的主要交通环;“E型”为综合教学楼平面布置的中小学教学、实验室、报告厅、图书馆、阅览室、活动室、学生食堂、教职办公室和行政办公室等综合设施连通校园主要建筑;三区为依附道路主环的三大主要功能区,分别是教学楼、生活区、体育活动区。此外,三区以教学区为中心,动静有隔,有分有连,疏密相间。

来源:福州日报