Array ( [id] => 90813 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 道庆洲大桥转入水上部分施工 计划明年5月桥面合拢 [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-05-29 09:23:30 [createdby] => 10052 [createdip] => 192.168.12.8 [published] => 2019-05-29 09:23:30 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 774 [virtual_pv] => 467 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 0 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [content] =>

道庆洲过江通道主墩下部结构已完成,即将转入水上部分施工,工期进度比计划提前一个月。

为满足地铁6号线的铺轨节点,按原定要求,项目须在7月之前完成水下部分施工,然后进入水上部分如桥墩、钢桁梁施工。

道庆洲大桥所在的乌龙江水深超过10米,为了能在江中作业,项目采取“钢套箱围堰”施工工艺。深入江面的临时钢栈桥每隔一段距离就会出现一个巨大的钢套箱,工人们正在钢套箱内进行最后的水泥灌注,“这些钢箱最深可到10米,工人们在钢套箱内进行桥墩的施工。最大的钢套箱重量超过1000吨。”有关负责人介绍。

道庆洲大桥位于青洲大桥和乌龙江特大桥之间,为福州首座公轨合建大桥,上层搭载市政公路,下层搭载福州地铁6号线。项目全长6.82公里,其中跨江段2.26公里,建设标准为城市主干道兼一级公路。其中主桥的主跨长达276米,采用变高度钢桁结合梁,跨度为同类型桥梁国内最大。钢桁梁采用“搭积木式”散件拼装工艺,单件最大重量达150吨,水上拼装对接误差必须控制在几毫米。

“计划于明年春节前,实现钢桁梁合拢,明年5月份实现桥面合拢。”上述负责人表示,项目建成后,福州海峡国际会展中心、三江口片区开车到福州滨海新城,只需约25分钟,比现在节省大约一个小时。

来源:福州日报
编辑:王蕾 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 工期进度比计划提前一个月。 [thumb] => [{"url":"\/a\/10001\/201905\/2b3bdec6700311546a416bceeb63c72d.jpeg","id":"1037580"}] [url] => /p/90813.html [all_pv] => 774 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 钢套 [1] => 大桥 [2] => 福州 [3] => 道庆洲 [4] => 桁梁 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 41934 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/41934.html [wapUrl] => http://m.fztvapp.zohi.tv/p/41934.html [published_timestamp] => 1539948417 [published] => 1539948417 [pv] => 1454 [virtual_pv] => 482 [all_pv] => 1454 [title] => 道庆洲大桥首个钢套箱围堰下放 大桥建设从水下桩基转入承台施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/38f988c7a02187c8cc5595a4ce2404dc.jpeg ) [1] => Array ( [relateid] => 41856 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/41856.html [wapUrl] => http://m.fztvapp.zohi.tv/p/41856.html [published_timestamp] => 1539930574 [published] => 1539930574 [pv] => 740 [virtual_pv] => 422 [all_pv] => 740 [title] => 道庆洲大桥首个承台钢围堰下放 整体施工预计下月初完成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/90d19e0b08999cdc7f87a50533ba1f32.jpeg ) [2] => Array ( [relateid] => 38517 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/38517.html [wapUrl] => http://m.fztvapp.zohi.tv/p/38517.html [published_timestamp] => 1538629027 [published] => 1538629027 [pv] => 428 [virtual_pv] => 434 [all_pv] => 428 [title] => 道庆洲大桥首个承台预计本月中旬起“脱水”浇筑 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/83350a8d897ef0d77c4143188532a0c0.jpeg ) [3] => Array ( [relateid] => 38295 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/38295.html [wapUrl] => http://m.fztvapp.zohi.tv/p/38295.html [published_timestamp] => 1538531048 [published] => 1538531048 [pv] => 484 [virtual_pv] => 373 [all_pv] => 484 [title] => 道庆洲大桥首个承台预计本月中旬起“脱水”浇筑 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/01e86f4c9196a2d991360fd63baa4906.jpeg ) [4] => Array ( [relateid] => 14452 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14452.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14452.html [published_timestamp] => 1516848057 [published] => 1516848057 [pv] => 1197 [virtual_pv] => 0 [all_pv] => 1197 [title] => 道庆洲大桥长乐段主栈桥春节前建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201801/8d9673b48bb6daebbbe59bd55e3142fc.jpeg@w773_h580.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201905/2b3bdec6700311546a416bceeb63c72d.jpeg ) 1

道庆洲大桥转入水上部分施工 计划明年5月桥面合拢

2019-05-29 09:23   福视悦动  

道庆洲过江通道主墩下部结构已完成,即将转入水上部分施工,工期进度比计划提前一个月。

为满足地铁6号线的铺轨节点,按原定要求,项目须在7月之前完成水下部分施工,然后进入水上部分如桥墩、钢桁梁施工。

道庆洲大桥所在的乌龙江水深超过10米,为了能在江中作业,项目采取“钢套箱围堰”施工工艺。深入江面的临时钢栈桥每隔一段距离就会出现一个巨大的钢套箱,工人们正在钢套箱内进行最后的水泥灌注,“这些钢箱最深可到10米,工人们在钢套箱内进行桥墩的施工。最大的钢套箱重量超过1000吨。”有关负责人介绍。

道庆洲大桥位于青洲大桥和乌龙江特大桥之间,为福州首座公轨合建大桥,上层搭载市政公路,下层搭载福州地铁6号线。项目全长6.82公里,其中跨江段2.26公里,建设标准为城市主干道兼一级公路。其中主桥的主跨长达276米,采用变高度钢桁结合梁,跨度为同类型桥梁国内最大。钢桁梁采用“搭积木式”散件拼装工艺,单件最大重量达150吨,水上拼装对接误差必须控制在几毫米。

“计划于明年春节前,实现钢桁梁合拢,明年5月份实现桥面合拢。”上述负责人表示,项目建成后,福州海峡国际会展中心、三江口片区开车到福州滨海新城,只需约25分钟,比现在节省大约一个小时。

来源:福州日报