Array ( [id] => 91383 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 出行请注意!地铁施工,福州这些地方近期将围挡! [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-05-31 12:16:36 [createdby] => 10052 [createdip] => 192.168.12.200 [published] => 2019-05-31 12:16:36 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 727 [virtual_pv] => 369 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

福州人出行注意了!因为地铁施工需要,这些地方近期将建围挡,一起来看看!

福州地铁4号线金牛山站二期围挡施工通告

福州地铁4号线金牛山站位于杨桥西路与西洪路交叉口处,车站拟分二期进行车站主体围护结构施工。因施工需要,该站将于2019年6月1日凌晨(遇雨顺延)进行二期围挡施工,围挡长70米,宽14米,计划工期约33个月。根据交通导改方案,将一期围挡施工期间占用的西洪路恢复至原状,杨桥路西洪路口交通组织方式保持不变。

因地铁施工给沿线市民出行造成的不便,深表歉意,敬请谅解!

福州地铁4号线岳峰镇北站一期围挡施工通告

福州地铁4号线岳峰镇北站位于塔头路与三八路、长乐北路交叉口,车站沿塔头路东西向敷设。因施工需要,该站将于2019年6月1日凌晨(遇雨顺延)进行一期围挡施工,围挡长385米,宽44米,计划工期约21个月。根据交通导改方案,施工占道采取占一还一,将占用的塔头路道路导改至围挡北、南两侧通行,保持现有交通组织双向6车道,两侧均设置3米宽非机动车道及2米宽人行道。

因地铁施工给沿线市民出行造成的不便,深表歉意,敬请谅解。

福州地铁4号线化工路站-福新东路站区间围挡施工通告

福州地铁4号线化工路站位于晋安区前横北路与化工路交叉口,因盾构施工需要,需拆除化工路下穿通道格构柱,将于2019年6月1日凌晨(遇雨顺延)进行围挡施工,该期围挡长约380米,宽约20米,计划工期1.5个月。根据交通疏解方案,施工围挡将封闭化工路下穿通道,拓宽现状东往西方向辅道,新增两个直行车道,设置东往西单向6个车道,其余路段交通组织方式保持不变。

因地铁施工给沿线市民出行造成不便,深表歉意,敬请谅解!

来源:福州晚报
编辑:王蕾 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 深表歉意,敬请谅解! [thumb] => [{"url":"\/a\/10001\/201905\/6e5af0d6939b5c70ce88fd3b040137ae.jpeg","id":"1041045"}] [url] => /p/91383.html [all_pv] => 727 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 围挡 [1] => 施工 [2] => 地铁 [3] => 号线 [4] => 福州 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 86634 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/86634.html [wapUrl] => http://m.fztvapp.zohi.tv/p/86634.html [published_timestamp] => 1557467229 [published] => 1557467229 [pv] => 384 [virtual_pv] => 455 [all_pv] => 384 [title] => 福州地铁4号线重大进展! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/f530b95c52f91ed4d96cd8e7ba4afc1e.jpeg ) [1] => Array ( [relateid] => 77835 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77835.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77835.html [published_timestamp] => 1554031495 [published] => 1554031495 [pv] => 786 [virtual_pv] => 417 [all_pv] => 786 [title] => 市领导督导检查地铁2号线围挡拆除及道路恢复景观提升工作 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/d00d05ef124cd9f7370bb756ac57c315.JPG ) [2] => Array ( [relateid] => 86682 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/86682.html [wapUrl] => http://m.fztvapp.zohi.tv/p/86682.html [published_timestamp] => 1557476833 [published] => 1557476833 [pv] => 229 [virtual_pv] => 402 [all_pv] => 229 [title] => 好消息!福州地铁4号线重大进展! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/7de9ac5d7f667c764e68f5ed3ae75a61.jpeg ) [3] => Array ( [relateid] => 47862 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/47862.html [wapUrl] => http://m.fztvapp.zohi.tv/p/47862.html [published_timestamp] => 1542249873 [published] => 1542249873 [pv] => 717 [virtual_pv] => 402 [all_pv] => 717 [title] => 福州地铁5号线高仕路站主体封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/7bce019bcb7221dce148881f62516b71.jpeg ) [4] => Array ( [relateid] => 21211 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/21211.html [wapUrl] => http://m.fztvapp.zohi.tv/p/21211.html [published_timestamp] => 1525920652 [published] => 1525920652 [pv] => 643 [virtual_pv] => 369 [all_pv] => 643 [title] => 福州地铁4号线前屿站与福新东路站将围挡施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201805/fa82c525de379af273ba1186e8414742.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/201905/6e5af0d6939b5c70ce88fd3b040137ae.jpeg ) 1

出行请注意!地铁施工,福州这些地方近期将围挡!

2019-05-31 12:16   福视悦动  

福州人出行注意了!因为地铁施工需要,这些地方近期将建围挡,一起来看看!

福州地铁4号线金牛山站二期围挡施工通告

福州地铁4号线金牛山站位于杨桥西路与西洪路交叉口处,车站拟分二期进行车站主体围护结构施工。因施工需要,该站将于2019年6月1日凌晨(遇雨顺延)进行二期围挡施工,围挡长70米,宽14米,计划工期约33个月。根据交通导改方案,将一期围挡施工期间占用的西洪路恢复至原状,杨桥路西洪路口交通组织方式保持不变。

因地铁施工给沿线市民出行造成的不便,深表歉意,敬请谅解!

福州地铁4号线岳峰镇北站一期围挡施工通告

福州地铁4号线岳峰镇北站位于塔头路与三八路、长乐北路交叉口,车站沿塔头路东西向敷设。因施工需要,该站将于2019年6月1日凌晨(遇雨顺延)进行一期围挡施工,围挡长385米,宽44米,计划工期约21个月。根据交通导改方案,施工占道采取占一还一,将占用的塔头路道路导改至围挡北、南两侧通行,保持现有交通组织双向6车道,两侧均设置3米宽非机动车道及2米宽人行道。

因地铁施工给沿线市民出行造成的不便,深表歉意,敬请谅解。

福州地铁4号线化工路站-福新东路站区间围挡施工通告

福州地铁4号线化工路站位于晋安区前横北路与化工路交叉口,因盾构施工需要,需拆除化工路下穿通道格构柱,将于2019年6月1日凌晨(遇雨顺延)进行围挡施工,该期围挡长约380米,宽约20米,计划工期1.5个月。根据交通疏解方案,施工围挡将封闭化工路下穿通道,拓宽现状东往西方向辅道,新增两个直行车道,设置东往西单向6个车道,其余路段交通组织方式保持不变。

因地铁施工给沿线市民出行造成不便,深表歉意,敬请谅解!

来源:福州晚报
编辑:王蕾 责编:庄颖