Array ( [id] => 93972 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 新洪塘大桥主塔本周“上梁” [editor] => (二审)王蕾 [has_thumb] => 1 [created] => 2019-06-13 10:04:41 [createdby] => 10052 [createdip] => 192.168.12.13 [published] => 2019-06-13 10:04:41 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 712 [virtual_pv] => 375 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

记者12日从洪塘大桥拓宽改造项目部获悉,新建洪塘大桥将于本周进行两座主塔之间的上横梁提升安装,届时洪塘大桥将进行交通管制,禁止一切机动车、非机动车及行人通行。

老洪塘大桥为双向两车道,新建洪塘大桥将在旧桥上下游各建三分之一桥面,再拆除中间旧桥建新桥,从而达到双向八车道的标准。

新洪塘大桥设计为自锚式单塔双索面悬索桥,高71米的主塔是其控制性工程,通过悬索承担主桥桥面荷载,即将提升安装的上横梁将架设在两座主塔之间,形成H形。据介绍,上横梁长44米、宽4米,重达240吨,目前已横跨于既有洪塘大桥之上,即将提升42米进行空中安装。目前新建洪塘大桥项目两侧新桥的钻孔桩基础已全部完成,下部结构已完成98%,主桥钢箱梁已完成77%,引桥钢梁架设已完成68%。

为确保横梁提升安装期间的安全,14日(周五)22时至17日(周一)6时,洪塘大桥将进行交通管制,禁止一切机动车、非机动车及行人通行。往仓山、闽侯方向的市民可绕行橘园洲大桥。

新洪塘大桥于2017年开工,工期36个月,路线总长约2.2公里,主线采用设计速度60公里/小时的双向八车道标准建设,预计2020年通车。届时,从鼓楼到闽侯上街将实现双向八车道无红绿灯通行,畅通西向进出城通道。


来源:福州日报
编辑:王蕾 责编:卢明铭

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 14日22时至17日6时老桥禁止通行 [thumb] => [{"url":"\/a\/10001\/201906\/4e7e02a5331658d3de1a803a18bf3fc4.jpeg","id":"1062003"}] [url] => /p/93972.html [all_pv] => 712 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 大桥 [1] => 洪塘 [2] => 横梁 [3] => 主塔 [4] => 车道 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 26148 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26148.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26148.html [published_timestamp] => 1531708957 [published] => 1531708957 [pv] => 798 [virtual_pv] => 410 [all_pv] => 798 [title] => 新洪塘大桥“站”稳脚跟 主塔桩基提前28天完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/077a8f44ae94f863db85e95077d48bb4.jpeg ) [1] => Array ( [relateid] => 26539 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26539.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26539.html [published_timestamp] => 1532179285 [published] => 1532179285 [pv] => 1258 [virtual_pv] => 397 [all_pv] => 1258 [title] => 新洪塘大桥建设稳步推进 预计2020年建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/a6a8907089bf1fb6a6533484f9745259.JPG@w720_h540.JPG ) [2] => Array ( [relateid] => 26269 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26269.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26269.html [published_timestamp] => 1531829146 [published] => 1531829146 [pv] => 104 [virtual_pv] => 432 [all_pv] => 104 [title] => 新洪塘大桥"双脚"已站立江中 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/8fb118b1dd7a2e836ddda757c1ec4e50.JPG ) [3] => Array ( [relateid] => 20387 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/20387.html [wapUrl] => http://m.fztvapp.zohi.tv/p/20387.html [published_timestamp] => 1524915666 [published] => 1524915666 [pv] => 1112 [virtual_pv] => 474 [all_pv] => 1112 [title] => 洪塘大桥拓宽改建 五一假期不停工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201804/1c908ecf4bb71d02d78d26bf01a8de06.JPG@w720_h540.JPG ) [4] => Array ( [relateid] => 27882 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/27882.html [wapUrl] => http://m.fztvapp.zohi.tv/p/27882.html [published_timestamp] => 1533717318 [published] => 1533717318 [pv] => 896 [virtual_pv] => 369 [all_pv] => 896 [title] => 洪塘大桥上一辆小轿车突然起火 原因还在调查当中 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201808/52bc667528b06601a52964ac78064f1c.png@w726_h545.png ) ) [article_thumb] => http://www.zohi.tv/a/10001/201906/4e7e02a5331658d3de1a803a18bf3fc4.jpeg ) 1

新洪塘大桥主塔本周“上梁”

2019-06-13 10:04   福视悦动  

记者12日从洪塘大桥拓宽改造项目部获悉,新建洪塘大桥将于本周进行两座主塔之间的上横梁提升安装,届时洪塘大桥将进行交通管制,禁止一切机动车、非机动车及行人通行。

老洪塘大桥为双向两车道,新建洪塘大桥将在旧桥上下游各建三分之一桥面,再拆除中间旧桥建新桥,从而达到双向八车道的标准。

新洪塘大桥设计为自锚式单塔双索面悬索桥,高71米的主塔是其控制性工程,通过悬索承担主桥桥面荷载,即将提升安装的上横梁将架设在两座主塔之间,形成H形。据介绍,上横梁长44米、宽4米,重达240吨,目前已横跨于既有洪塘大桥之上,即将提升42米进行空中安装。目前新建洪塘大桥项目两侧新桥的钻孔桩基础已全部完成,下部结构已完成98%,主桥钢箱梁已完成77%,引桥钢梁架设已完成68%。

为确保横梁提升安装期间的安全,14日(周五)22时至17日(周一)6时,洪塘大桥将进行交通管制,禁止一切机动车、非机动车及行人通行。往仓山、闽侯方向的市民可绕行橘园洲大桥。

新洪塘大桥于2017年开工,工期36个月,路线总长约2.2公里,主线采用设计速度60公里/小时的双向八车道标准建设,预计2020年通车。届时,从鼓楼到闽侯上街将实现双向八车道无红绿灯通行,畅通西向进出城通道。


来源:福州日报