Array ( [id] => 165968 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => ​平潭海峡公铁两用大桥顺利通过静载试验 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-08-29 10:53:44 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-08-29 10:53:44 [publishedby] => 10056 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 446 [virtual_pv] => 422 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

备受关注的福平铁路传来最新进展,记者28日获悉,该铁路关键控制性工程——平潭海峡公铁两用大桥已于日前顺利通过静态荷载试验,完成通车前的一次重要“体检”,同时大桥精调施工也已启动,将于9月15日完成。

据介绍,平潭海峡公铁两用大桥荷载试验主要包括静载试验和动载试验。此次完成的静载试验从22日持续至27日,为期6天,主要对主航道桥和其他2座航道桥在列车荷载不同轮位作用下的应力、索力和位移等参数总计449个测试点进行静载测试工作,以检验大桥的整体工作性能,为验收交付提供依据。

值得一提的是,静载试验采用公路、铁路同时加载的方式,其中公路桥面采用36辆三轴货车进行加载,铁路采用两列道砟车进行加载。为了避免温度影响,静载试验均安排在夜间进行。

从8月25日开始,大桥也启动了首轮线路精调作业。为确保线路质量和安全,鹰潭工务机械段抽调了4台世界上最先进的连续式捣稳车,使用精确法作业的模式,对大桥铁路线路进行道床全方位的线路精调作业。

平潭海峡公铁两用大桥是福州至平潭铁路的关键控制性工程,大桥桥址位于海坛海峡北口,是世界在建难度最大的海峡大桥。该桥所在的平潭海峡为世界三大风口海域之一,全年6级以上的大风天数超过309天。项目自2013年11月底开工建设以来,克服了大风、水深、浪高、流急等恶劣气象,水文,地质难题。大桥建成通车后,将实现福州、长乐、平潭三地的互联互通。


来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202008\/366c57fd73b7dcc563b3f746f4b802e1.jpeg","id":"1850480"}] [url] => /p/165968.html [all_pv] => 446 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 大桥 [1] => 平潭 [2] => 静载 [3] => 试验 [4] => 海峡 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 165470 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/165470.html [wapUrl] => http://m.fztvapp.zohi.tv/p/165470.html [published_timestamp] => 1598166493 [published] => 1598166493 [pv] => 65 [virtual_pv] => 409 [all_pv] => 65 [title] => 平潭海峡公铁两用大桥启动荷载试验 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/202008/4270faa8cd8438e3db0c1d1592578474.jpeg@w801_h601.jpeg ) [1] => Array ( [relateid] => 117606 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/117606.html [wapUrl] => http://m.fztvapp.zohi.tv/p/117606.html [published_timestamp] => 1569376005 [published] => 1569376005 [pv] => 1273 [virtual_pv] => 402 [all_pv] => 1273 [title] => 9月25日!平潭海峡公铁两用大桥全桥贯通! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/cb37aaad3490ee67eabb85fb8cc0c01e.jpeg ) [2] => Array ( [relateid] => 138489 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/138489.html [wapUrl] => http://m.fztvapp.zohi.tv/p/138489.html [published_timestamp] => 1577417464 [published] => 1577417464 [pv] => 427 [virtual_pv] => 389 [all_pv] => 427 [title] => 平潭海峡公铁大桥春节前公路通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201912/3764859b746edef86fddb027bbe5bf35.jpeg ) [3] => Array ( [relateid] => 165706 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/165706.html [wapUrl] => http://m.fztvapp.zohi.tv/p/165706.html [published_timestamp] => 1598423201 [published] => 1598423201 [pv] => 66 [virtual_pv] => 397 [all_pv] => 66 [title] => 这座跨海公铁两用大桥世界最长,就在福州⇆平潭的路上 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202008/e5e3e855ee7cbc82501c1c604efd7001.png ) [4] => Array ( [relateid] => 124146 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/124146.html [wapUrl] => http://m.fztvapp.zohi.tv/p/124146.html [published_timestamp] => 1571820370 [published] => 1571820370 [pv] => 187 [virtual_pv] => 442 [all_pv] => 187 [title] => 平潭海峡公铁两用大桥施工进入扫尾 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/01f070a5bd5805c9a94ae39b45d6f73f.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202008/366c57fd73b7dcc563b3f746f4b802e1.jpeg ) 1

​平潭海峡公铁两用大桥顺利通过静载试验

2020-08-29 10:53   福视悦动  

备受关注的福平铁路传来最新进展,记者28日获悉,该铁路关键控制性工程——平潭海峡公铁两用大桥已于日前顺利通过静态荷载试验,完成通车前的一次重要“体检”,同时大桥精调施工也已启动,将于9月15日完成。

据介绍,平潭海峡公铁两用大桥荷载试验主要包括静载试验和动载试验。此次完成的静载试验从22日持续至27日,为期6天,主要对主航道桥和其他2座航道桥在列车荷载不同轮位作用下的应力、索力和位移等参数总计449个测试点进行静载测试工作,以检验大桥的整体工作性能,为验收交付提供依据。

值得一提的是,静载试验采用公路、铁路同时加载的方式,其中公路桥面采用36辆三轴货车进行加载,铁路采用两列道砟车进行加载。为了避免温度影响,静载试验均安排在夜间进行。

从8月25日开始,大桥也启动了首轮线路精调作业。为确保线路质量和安全,鹰潭工务机械段抽调了4台世界上最先进的连续式捣稳车,使用精确法作业的模式,对大桥铁路线路进行道床全方位的线路精调作业。

平潭海峡公铁两用大桥是福州至平潭铁路的关键控制性工程,大桥桥址位于海坛海峡北口,是世界在建难度最大的海峡大桥。该桥所在的平潭海峡为世界三大风口海域之一,全年6级以上的大风天数超过309天。项目自2013年11月底开工建设以来,克服了大风、水深、浪高、流急等恶劣气象,水文,地质难题。大桥建成通车后,将实现福州、长乐、平潭三地的互联互通。