Array ( [id] => 216814 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 假期“不打烊”!福州大学城项目稳步推进 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2021-10-03 09:48:09 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2021-10-03 09:48:11 [publishedby] => 10056 [modified] => 2021-10-03 09:57:38 [modifiedby] => 10056 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 498 [virtual_pv] => 432 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 017c43d473d0c00100009767457a4607 [cdv_type] => 1 [content] =>

钢筋林立、焊花飞舞,挖掘机、推土机的轰鸣声此起彼伏,各项工程正在开足马力建设……国庆假期,走进福州大学城在建项目现场,处处是火热的施工场面。高新区和闽侯县积极贯彻落实市第十二次党代会精神,以实际行动加速建设一流大学城。

创新园三期封顶 将提供又一“创新源”

在高新区海西园创新园三期,A地块的主体结构已经封顶,工人们正在进行室内墙体砌筑施工,B地块的主体已建至地上11层。

“三期A地块和B地块均将建成多层研发楼,预计分别于明年上半年和下半年竣工。”负责该项目全程筹建的福州高新区投资控股有限公司相关负责人说,作为2021年省重点项目,创新园三期项目聚焦高端产业和人才,以“创新”为核心设计服务链,将为福州大学城发展提供又一“创新源”。

1日上午,福州高新区第一中心小学二期施工现场,数十名建筑工人正在为综合教学楼基坑支护冠梁钢筋进行绑扎。项目部为一线劳动者送上凉茶、矿泉水、花生牛奶等物资,并嘱咐他们做好防暑和防疫工作。

据了解,该项目位于南屿镇南前村,将建设教学综合楼、体艺楼、服务用房等。建成后可设置42个班,容纳学生1890人。

高新区相关负责人表示,为贯彻落实市第十二次党代会精神,高新区立足新起点,全面推进福州大学城相关项目建设,加快建设创新活力迸发的现代化国际城市。

旗山湖项目主体 力争月底完工

作为福州第一大绿色生态景观湖,旗山湖项目十一期间也在如火如荼的建设中。

旗山湖项目建成后,湖体水域面积达1063亩,景观绿化面积813亩。据指挥部现场负责人介绍,6月30日先行对外开园的是中心湖体园区(分区一、二),余下未开园部分(分区三、四、五)主体工程力争于10月底基本完成。

“开工以来工程进展顺利,目前节制闸、启闭房、管理房已建设完成,机电设备安装调试可正常使用。”上述现场负责人介绍,接下来,旗山湖项目将加快桥梁工程施工进度,同时加快旗山桂冠、片山居、观山筑、湖山在望等4座景观建筑物施工进度,完工后的旗山湖项目将具备防洪、生态、景观、聚集产业等功能,成为福州的一张新名片。


来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202110\/ecd8fa48c158b3c20d43583ef298083a.jpeg","id":"2089442"}] [url] => /p/216814.html [all_pv] => 498 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 旗山 [1] => 高新区 [2] => 项目 [3] => 创新 [4] => 三期 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => http://www.zohi.tv/a/10001/202110/ecd8fa48c158b3c20d43583ef298083a.jpeg ) 1

假期“不打烊”!福州大学城项目稳步推进

2021-10-03 09:48   福视悦动  

钢筋林立、焊花飞舞,挖掘机、推土机的轰鸣声此起彼伏,各项工程正在开足马力建设……国庆假期,走进福州大学城在建项目现场,处处是火热的施工场面。高新区和闽侯县积极贯彻落实市第十二次党代会精神,以实际行动加速建设一流大学城。

创新园三期封顶 将提供又一“创新源”

在高新区海西园创新园三期,A地块的主体结构已经封顶,工人们正在进行室内墙体砌筑施工,B地块的主体已建至地上11层。

“三期A地块和B地块均将建成多层研发楼,预计分别于明年上半年和下半年竣工。”负责该项目全程筹建的福州高新区投资控股有限公司相关负责人说,作为2021年省重点项目,创新园三期项目聚焦高端产业和人才,以“创新”为核心设计服务链,将为福州大学城发展提供又一“创新源”。

1日上午,福州高新区第一中心小学二期施工现场,数十名建筑工人正在为综合教学楼基坑支护冠梁钢筋进行绑扎。项目部为一线劳动者送上凉茶、矿泉水、花生牛奶等物资,并嘱咐他们做好防暑和防疫工作。

据了解,该项目位于南屿镇南前村,将建设教学综合楼、体艺楼、服务用房等。建成后可设置42个班,容纳学生1890人。

高新区相关负责人表示,为贯彻落实市第十二次党代会精神,高新区立足新起点,全面推进福州大学城相关项目建设,加快建设创新活力迸发的现代化国际城市。

旗山湖项目主体 力争月底完工

作为福州第一大绿色生态景观湖,旗山湖项目十一期间也在如火如荼的建设中。

旗山湖项目建成后,湖体水域面积达1063亩,景观绿化面积813亩。据指挥部现场负责人介绍,6月30日先行对外开园的是中心湖体园区(分区一、二),余下未开园部分(分区三、四、五)主体工程力争于10月底基本完成。

“开工以来工程进展顺利,目前节制闸、启闭房、管理房已建设完成,机电设备安装调试可正常使用。”上述现场负责人介绍,接下来,旗山湖项目将加快桥梁工程施工进度,同时加快旗山桂冠、片山居、观山筑、湖山在望等4座景观建筑物施工进度,完工后的旗山湖项目将具备防洪、生态、景观、聚集产业等功能,成为福州的一张新名片。