Array ( [id] => 260841 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 白马河杨桥路桥梁工程有新进展 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2022-05-06 15:10:55 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2022-05-06 15:10:58 [publishedby] => 10270 [modified] => 2022-05-06 15:13:31 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 708 [virtual_pv] => 455 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 1 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 0180983355e7c0010000b3021673fadc [cdv_type] => 1 [content] =>

白马河杨桥路桥北半幅桥梁已完成下部结构施工。记者 陈暖 摄

记者5日从市城乡建设局获悉,作为全面优化白马河通航条件的核心工程,白马河杨桥路桥梁改造工程又有新进展,目前北半幅桥梁已完成下部结构施工,本周可完成旧桥拆除,下月将转入南半幅桥梁施工。按计划,新桥力争在国庆前整体亮相。

“目前,北半幅桥梁的旧桥已破除近80%,从5日开始,我们对白马河展开了降水施工,通过河道上游水闸来控制水位,计划持续至7日。”福州城投集团所属城乡建总集团该项目负责人郭聪介绍,本周内,北半幅的旧桥就将“卸任”。“五一”期间,新桥的钢结构就已完成上漆作业。本月中旬,2台180吨的吊机将就位,吊装工作将安排在夜间11点至第二天凌晨展开,避开高峰期的交通流。南半幅桥梁方面,本月底计划进行交通导改,将车流引至北半幅的新桥通行,再封闭进行旧桥拆除作业,尽可能把对市民出行的影响降到最低。

据了解,建于上世纪80年代的白马河杨桥路桥梁,已无法满足现有排洪及交通疏导需求,因未设置非机动车道,还形成机非混流的交通隘口。为建起加宽加高的新桥,项目按“边施工,边通车”的方案,分为两期展开改造。

今后,机动车、非机动车将在桥上通行,桥下新打通的5.5米宽的半开放式步道,则为市民游客“牵”起一条沿河慢行步道,让通行安全有序。按计划,新桥将在国庆前全面建成,让西湖左海—白马河游线加快串联。


来源:福州日报
编辑:黄国伟 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202205\/953dc1017817ce9359e3774294401b05.jpeg","id":"2316459"}] [url] => /p/260841.html [all_pv] => 708 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 半幅 [1] => 白马河 [2] => 桥梁 [3] => 新桥 [4] => 旧桥 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202205/953dc1017817ce9359e3774294401b05.jpeg ) 1

白马河杨桥路桥梁工程有新进展

2022-05-06 15:10   福视悦动  

白马河杨桥路桥北半幅桥梁已完成下部结构施工。记者 陈暖 摄

记者5日从市城乡建设局获悉,作为全面优化白马河通航条件的核心工程,白马河杨桥路桥梁改造工程又有新进展,目前北半幅桥梁已完成下部结构施工,本周可完成旧桥拆除,下月将转入南半幅桥梁施工。按计划,新桥力争在国庆前整体亮相。

“目前,北半幅桥梁的旧桥已破除近80%,从5日开始,我们对白马河展开了降水施工,通过河道上游水闸来控制水位,计划持续至7日。”福州城投集团所属城乡建总集团该项目负责人郭聪介绍,本周内,北半幅的旧桥就将“卸任”。“五一”期间,新桥的钢结构就已完成上漆作业。本月中旬,2台180吨的吊机将就位,吊装工作将安排在夜间11点至第二天凌晨展开,避开高峰期的交通流。南半幅桥梁方面,本月底计划进行交通导改,将车流引至北半幅的新桥通行,再封闭进行旧桥拆除作业,尽可能把对市民出行的影响降到最低。

据了解,建于上世纪80年代的白马河杨桥路桥梁,已无法满足现有排洪及交通疏导需求,因未设置非机动车道,还形成机非混流的交通隘口。为建起加宽加高的新桥,项目按“边施工,边通车”的方案,分为两期展开改造。

今后,机动车、非机动车将在桥上通行,桥下新打通的5.5米宽的半开放式步道,则为市民游客“牵”起一条沿河慢行步道,让通行安全有序。按计划,新桥将在国庆前全面建成,让西湖左海—白马河游线加快串联。


来源:福州日报
编辑:黄国伟 责编:庄颖