Array ( [id] => 111000 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 好消息!福州地铁4号线池边站主体结构顺利封顶! [editor] => (二审)强婕宁 [has_thumb] => 1 [created] => 2019-08-27 17:28:34 [createdby] => 10056 [createdip] => 192.168.12.10 [published] => 2019-08-27 17:28:34 [publishedby] => 10056 [modified] => 2019-08-27 17:28:45 [modifiedby] => 10056 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 484 [virtual_pv] => 405 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 1 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

8月26日上午,随着最后一车混凝土浇筑完成,标志着由中国建筑承建的福州地铁4号线池边站主体结构实现全部封顶,提前5天完成了业主下达的节点目标。

福州地铁4号线2标池边站车站主体结构长190米,标准段宽19.7米,为地下二层岛式结构。由中国建筑下属公司中建海峡承担具体施工任务。

该车站地处市区繁华地带,施工期间,遭遇重重困难,一是施工场地狭小,多工种交叉施工,协调配合难度大;二是环保管控严,文明施工及标准化要求高,土方外运、混凝土供应阻碍多;三是地质条件复杂,车站底部基岩突起,地连墙成槽困难,开挖难度大。

施工期间,地连墙创新采用大功率成槽机+冲孔修槽工艺,大大提高了成槽效率;底板基岩凸起采用静态爆破,顺利解决开挖难题。通过科学筹划、方案优化、精心施工、严控风险等,项目部提前完成池边站主体结构封顶。

延伸阅读 

2018年1月21日,池边站一期围挡顺利封闭,成为全线第一个完成围挡封闭的车站。

2018年2月8日,池边站一期首幅地连墙正式开槽,成为全线第一个进入围护结构施工的车站。

2018年10月10日,池边站首仓底板混凝土浇筑完成,成为第一个进行主体结构施工的车站。

2018年12月30日,池边站首段顶板混凝土浇筑完成,成为全线第一个整段浇筑完成的车站。

2019年1月31日,池边区间左线首台盾构机吊装下井,成为全线第一个盾构机下井的区间。

2019年4月21日,池边站区间左线首台盾构机始发,成为全线第一个盾构始发的区间。

2019年7月5日,池边站获得福州地铁五星级(最高等级)党建标准化阵地荣誉称号,是福州地铁44个参评车站唯五,福州地铁四号线唯一获此殊荣的车站。

2019年5月10日,4号线2标7工区化工路站率先顺利完成主体结构封顶,成为福州地铁4号线全线首个封顶的车站。

2019年8月26日,6工区池边站顺利完成主体结构封顶,是4号线2标第二座完成主体结构封顶的车站。

未来,期待其他车站的好消息!

来源:中建福州地铁4号线2标段项目部微信
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 热烈庆祝! [thumb] => [{"url":"\/a\/10001\/201908\/bfc82a374592c626739ca365c8666516.jpeg","id":"1190559"}] [url] => /p/111000.html [all_pv] => 484 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 车站 [1] => 封顶 [2] => 2019 [3] => 4号线 [4] => 池边站 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 27443 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/27443.html [wapUrl] => http://m.fztvapp.zohi.tv/p/27443.html [published_timestamp] => 1533185485 [published] => 1533185485 [pv] => 475 [virtual_pv] => 410 [all_pv] => 475 [title] => 地铁2号线全线22个车站主体结构封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201808/1e98e3517a756ea70869b0830452427e.jpeg ) [1] => Array ( [relateid] => 87381 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/87381.html [wapUrl] => http://m.fztvapp.zohi.tv/p/87381.html [published_timestamp] => 1557797721 [published] => 1557797721 [pv] => 27 [virtual_pv] => 383 [all_pv] => 27 [title] => 福州地铁5号线螺洲镇站完成主体结构封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/179df0fdc6852204c28f47bd7caec625.jpeg ) [2] => Array ( [relateid] => 87795 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/87795.html [wapUrl] => http://m.fztvapp.zohi.tv/p/87795.html [published_timestamp] => 1557914610 [published] => 1557914610 [pv] => 90 [virtual_pv] => 473 [all_pv] => 90 [title] => 地铁5号线螺洲镇站主体结构提前封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/5014503f17d16c7b86ab44f7a384d31f.jpeg ) [3] => Array ( [relateid] => 82434 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/82434.html [wapUrl] => http://m.fztvapp.zohi.tv/p/82434.html [published_timestamp] => 1555899264 [published] => 1555899264 [pv] => 31 [virtual_pv] => 412 [all_pv] => 31 [title] => 福州地铁4号线进入盾构施工 一期工程设23个站点 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/d9734f5d84f674279f84105a11197e9f.jpeg ) [4] => Array ( [relateid] => 47862 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/47862.html [wapUrl] => http://m.fztvapp.zohi.tv/p/47862.html [published_timestamp] => 1542249873 [published] => 1542249873 [pv] => 314 [virtual_pv] => 402 [all_pv] => 314 [title] => 福州地铁5号线高仕路站主体封顶 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/7bce019bcb7221dce148881f62516b71.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201908/bfc82a374592c626739ca365c8666516.jpeg ) 1

好消息!福州地铁4号线池边站主体结构顺利封顶!

2019-08-27 17:28   福视悦动  

8月26日上午,随着最后一车混凝土浇筑完成,标志着由中国建筑承建的福州地铁4号线池边站主体结构实现全部封顶,提前5天完成了业主下达的节点目标。

福州地铁4号线2标池边站车站主体结构长190米,标准段宽19.7米,为地下二层岛式结构。由中国建筑下属公司中建海峡承担具体施工任务。

该车站地处市区繁华地带,施工期间,遭遇重重困难,一是施工场地狭小,多工种交叉施工,协调配合难度大;二是环保管控严,文明施工及标准化要求高,土方外运、混凝土供应阻碍多;三是地质条件复杂,车站底部基岩突起,地连墙成槽困难,开挖难度大。

施工期间,地连墙创新采用大功率成槽机+冲孔修槽工艺,大大提高了成槽效率;底板基岩凸起采用静态爆破,顺利解决开挖难题。通过科学筹划、方案优化、精心施工、严控风险等,项目部提前完成池边站主体结构封顶。

延伸阅读 

2018年1月21日,池边站一期围挡顺利封闭,成为全线第一个完成围挡封闭的车站。

2018年2月8日,池边站一期首幅地连墙正式开槽,成为全线第一个进入围护结构施工的车站。

2018年10月10日,池边站首仓底板混凝土浇筑完成,成为第一个进行主体结构施工的车站。

2018年12月30日,池边站首段顶板混凝土浇筑完成,成为全线第一个整段浇筑完成的车站。

2019年1月31日,池边区间左线首台盾构机吊装下井,成为全线第一个盾构机下井的区间。

2019年4月21日,池边站区间左线首台盾构机始发,成为全线第一个盾构始发的区间。

2019年7月5日,池边站获得福州地铁五星级(最高等级)党建标准化阵地荣誉称号,是福州地铁44个参评车站唯五,福州地铁四号线唯一获此殊荣的车站。

2019年5月10日,4号线2标7工区化工路站率先顺利完成主体结构封顶,成为福州地铁4号线全线首个封顶的车站。

2019年8月26日,6工区池边站顺利完成主体结构封顶,是4号线2标第二座完成主体结构封顶的车站。

未来,期待其他车站的好消息!

来源:中建福州地铁4号线2标段项目部微信