Array ( [id] => 112287 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 国内最大断面的公路特长隧道正式动工!位于福州长乐 [editor] => 熊英宏 [has_thumb] => 1 [created] => 2019-09-02 16:46:34 [createdby] => 10179 [createdip] => 192.168.12.11 [published] => 2019-09-02 16:46:34 [publishedby] => 10179 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 446 [virtual_pv] => 382 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 2 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

9月1日上午9点58分,由中交二航局承建的国道316长乐漳港至营前段工程A3标(以下简称“G316项目A3标”)董奉山隧道正式进行明洞段土石方开挖施工。

本次明洞顺利开挖施工,标志着G316项目A3标正式动工,也是国道G316项目全线正式进入实质性动工阶段,为确保全线2022年通车的目标奠定了坚实的基础。

此次正式动工的G316项目A3标控制性工程董奉山特长隧道全长4.07公里,是国内最大断面的公路特长隧道,最大断面达234平方米。主路隧道采用双向八车道,辅路隧道为双向四车道,计划工期36个月,施工难度大,工期紧。

项目自7月5日中标后,福州分公司高度重视,立即组织人员进场,迅速完成驻地选址并于8月中旬完成驻地建设并入驻办公,同时项目部积极主动与业主、东南办、镇(村)等单位进行对接,相关单位大力发扬福州滨海新城大干快上马上就办的精神积极推动现场红线用地征收交付工作,目前已交付红线用地达35%,正在进行清表及明洞土石方开挖工作。

据悉, G316项目起于文武砂镇东岱村至营前街道洞头村,与在建的道庆洲大桥长乐侧终点顺接。全长15.578公里,主路采用双向八车道按一级公路兼城市快速路标准建设,设计速度80km/h,辅路采用双向四车道按二级公路兼城市次干道标准建设,设计速度40km/h。投资概算101.57亿,其中:主路部分55.42亿,辅路部分46.15亿元。项目分为5个路基土建标段、1个机电标段、1个房建标段,计划工期36个月。

来源:中交二航局福州分公司
编辑:熊英宏 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 昨日,福州长乐国内最大断面的公路特长隧道正式动工! [thumb] => [{"url":"\/a\/10001\/201909\/3f742c12e4678a9070aa85c15e2abeb8.jpeg","id":"1199946"}] [url] => /p/112287.html [all_pv] => 446 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => G316 [1] => A3 [2] => 隧道 [3] => 明洞 [4] => 辅路 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 99492 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/99492.html [wapUrl] => http://m.fztvapp.zohi.tv/p/99492.html [published_timestamp] => 1562550809 [published] => 1562550809 [pv] => 0 [virtual_pv] => 391 [all_pv] => 0 [title] => 长福高速A3合同段建设进入冲刺阶段 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/1f7218f0342915716833b7f77a7e4886.jpeg ) [1] => Array ( [relateid] => 44394 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/44394.html [wapUrl] => http://m.fztvapp.zohi.tv/p/44394.html [published_timestamp] => 1540951053 [published] => 1540951053 [pv] => 573 [virtual_pv] => 437 [all_pv] => 573 [title] => 长福高速龙山互通桥面施工 预计2020年建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/a992a895a637fbf90a47204f3452a3dd.jpeg ) [2] => Array ( [relateid] => 96591 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/96591.html [wapUrl] => http://m.fztvapp.zohi.tv/p/96591.html [published_timestamp] => 1561447943 [published] => 1561447943 [pv] => 0 [virtual_pv] => 369 [all_pv] => 0 [title] => 长福高速公路龙江特大桥右幅贯通 预计2020年建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/944b292cddd519c5be1bb5e67c6b9c6e.jpeg ) [3] => Array ( [relateid] => 46269 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/46269.html [wapUrl] => http://m.fztvapp.zohi.tv/p/46269.html [published_timestamp] => 1541638926 [published] => 1541638926 [pv] => 672 [virtual_pv] => 440 [all_pv] => 672 [title] => 技术创新助攻坚 莆炎高速嵩口互通有望提前完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201811/bbbd6122e8fa17634faf8f83b8a931db.jpeg ) [4] => Array ( [relateid] => 23195 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/23195.html [wapUrl] => http://m.fztvapp.zohi.tv/p/23195.html [published_timestamp] => 1528342740 [published] => 1528342740 [pv] => 578 [virtual_pv] => 446 [all_pv] => 578 [title] => 三环辅路跨福飞路高架动建 力争春节前建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201806/cdf82c1c6c196725bebac08c9681fd5b.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201909/3f742c12e4678a9070aa85c15e2abeb8.jpeg ) 1

国内最大断面的公路特长隧道正式动工!位于福州长乐

2019-09-02 16:46   福视悦动  

9月1日上午9点58分,由中交二航局承建的国道316长乐漳港至营前段工程A3标(以下简称“G316项目A3标”)董奉山隧道正式进行明洞段土石方开挖施工。

本次明洞顺利开挖施工,标志着G316项目A3标正式动工,也是国道G316项目全线正式进入实质性动工阶段,为确保全线2022年通车的目标奠定了坚实的基础。

此次正式动工的G316项目A3标控制性工程董奉山特长隧道全长4.07公里,是国内最大断面的公路特长隧道,最大断面达234平方米。主路隧道采用双向八车道,辅路隧道为双向四车道,计划工期36个月,施工难度大,工期紧。

项目自7月5日中标后,福州分公司高度重视,立即组织人员进场,迅速完成驻地选址并于8月中旬完成驻地建设并入驻办公,同时项目部积极主动与业主、东南办、镇(村)等单位进行对接,相关单位大力发扬福州滨海新城大干快上马上就办的精神积极推动现场红线用地征收交付工作,目前已交付红线用地达35%,正在进行清表及明洞土石方开挖工作。

据悉, G316项目起于文武砂镇东岱村至营前街道洞头村,与在建的道庆洲大桥长乐侧终点顺接。全长15.578公里,主路采用双向八车道按一级公路兼城市快速路标准建设,设计速度80km/h,辅路采用双向四车道按二级公路兼城市次干道标准建设,设计速度40km/h。投资概算101.57亿,其中:主路部分55.42亿,辅路部分46.15亿元。项目分为5个路基土建标段、1个机电标段、1个房建标段,计划工期36个月。

来源:中交二航局福州分公司
编辑:熊英宏 责编:庄颖