Array ( [id] => 113271 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 海峡奥体中心周边2条新路加速收尾 20日前建成通车 [editor] => (二审)强婕宁 [has_thumb] => 1 [created] => 2019-09-06 15:06:37 [createdby] => 10056 [createdip] => 192.168.12.10 [published] => 2019-09-06 15:06:37 [publishedby] => 10056 [modified] => 2019-09-06 16:08:28 [modifiedby] => 10056 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 496 [virtual_pv] => 479 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

昨日,记者从市城乡建设局获悉,海峡奥体中心周边4#地块安置房土地收储项目周边道路工程已转入全面收尾阶段,连接建新南路与杨周路的A路、串起鹭岭路延伸段及A路的B路都将在20日前建成通车。通过这2条新路,市民更方便地在二环、建新南路、浦上大道等主干道间通行,让路网更畅达、出行更便捷。

海峡奥体中心周边两条新路进入收尾阶段。

“新路不长,但串联作用明显。”市建发集团下属福州市政建设开发公司该项目负责人黄曦告诉记者,A路起于建新南路,沿线与已建成的鹭岭路延伸段、金榕支路相交,终点至现状杨周路,总长936米,宽34米,设计车速40公里/小时,为双向4车道通行;B路则起于鹭岭路延伸段,终于A路,总长234米,宽18米,设计车速30公里/小时,为双向2车道。

黄曦介绍,目前,从市区前往海峡奥体中心,主要通道有2条,可以从浦上大道至金榕南路,或通过二环到双湖互通。

“A路的加入,能让市民的出行变为‘多选题’。”黄曦说,A路升级后,从村道加“断头”,变为与建新南路、杨周路、金榕支路、鹭岭路延伸段相接,通车后,在海峡奥体中心附近的车辆,可经由A路、杨周路及周边道路,便捷抵达浦上大道,还可通过鹭岭路延伸段顺利驶入二环路,让交通流快速疏散。

B路则像A路的枝节,主要为沿线小区、学校服务,提前考虑到今后居民入住的出行需要。

“保护沿线历史建筑,是B路的一大亮点。”黄曦介绍,按B路原有道路线形,将和建平村杨桃岭22号、杨桃岭21号及杨桃岭11号这3处历史建筑相遇。为守好占地面积1500多平方米的古建,B路决定绕行。

来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201909\/d74a67093aa5c82f935ca09f529b369b.jpeg","id":"1208550"}] [url] => /p/113271.html [all_pv] => 496 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 延伸段 [1] => 奥体中心 [2] => 鹭岭 [3] => 南路 [4] => 建新 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 12866 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/12866.html [wapUrl] => http://m.fztvapp.zohi.tv/p/12866.html [published_timestamp] => 1514865707 [published] => 1514865707 [pv] => 644 [virtual_pv] => 0 [all_pv] => 644 [title] => 仓山区鹭岭路将“拉长”至建新南路 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/be7781ce859bb35abc5ca42fb63001eb.jpg ) [1] => Array ( [relateid] => 26619 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26619.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26619.html [published_timestamp] => 1532309272 [published] => 1532309272 [pv] => 300 [virtual_pv] => 409 [all_pv] => 300 [title] => 百花洲路“拉伸”段8月通车 年内与鹭岭路延伸段相连 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/75529deae9f5694f24d37aa9bfdff032.jpeg ) [2] => Array ( [relateid] => 40122 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/40122.html [wapUrl] => http://m.fztvapp.zohi.tv/p/40122.html [published_timestamp] => 1539307532 [published] => 1539307532 [pv] => 543 [virtual_pv] => 391 [all_pv] => 543 [title] => 鹭岭路延伸段15日通车 连通奥体片区和南二环路 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/5f156b2936e832ea72565c5539cb79f0.jpeg ) [3] => Array ( [relateid] => 26357 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26357.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26357.html [published_timestamp] => 1531919628 [published] => 1531919628 [pv] => 33 [virtual_pv] => 395 [all_pv] => 33 [title] => 鹭岭路"拉长"将连接奥体 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/8b75342ebd5c00c3d22260fa9aa36d7b.JPG ) [4] => Array ( [relateid] => 26909 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26909.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26909.html [published_timestamp] => 1532518381 [published] => 1532518381 [pv] => 764 [virtual_pv] => 461 [all_pv] => 764 [title] => 鹭岭路延伸段工程力争10月主线通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/4dc3d3cd8f68b2de09dfdb377f4584c7.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/201909/d74a67093aa5c82f935ca09f529b369b.jpeg ) 1

海峡奥体中心周边2条新路加速收尾 20日前建成通车

2019-09-06 15:06  

昨日,记者从市城乡建设局获悉,海峡奥体中心周边4#地块安置房土地收储项目周边道路工程已转入全面收尾阶段,连接建新南路与杨周路的A路、串起鹭岭路延伸段及A路的B路都将在20日前建成通车。通过这2条新路,市民更方便地在二环、建新南路、浦上大道等主干道间通行,让路网更畅达、出行更便捷。

海峡奥体中心周边两条新路进入收尾阶段。

“新路不长,但串联作用明显。”市建发集团下属福州市政建设开发公司该项目负责人黄曦告诉记者,A路起于建新南路,沿线与已建成的鹭岭路延伸段、金榕支路相交,终点至现状杨周路,总长936米,宽34米,设计车速40公里/小时,为双向4车道通行;B路则起于鹭岭路延伸段,终于A路,总长234米,宽18米,设计车速30公里/小时,为双向2车道。

黄曦介绍,目前,从市区前往海峡奥体中心,主要通道有2条,可以从浦上大道至金榕南路,或通过二环到双湖互通。

“A路的加入,能让市民的出行变为‘多选题’。”黄曦说,A路升级后,从村道加“断头”,变为与建新南路、杨周路、金榕支路、鹭岭路延伸段相接,通车后,在海峡奥体中心附近的车辆,可经由A路、杨周路及周边道路,便捷抵达浦上大道,还可通过鹭岭路延伸段顺利驶入二环路,让交通流快速疏散。

B路则像A路的枝节,主要为沿线小区、学校服务,提前考虑到今后居民入住的出行需要。

“保护沿线历史建筑,是B路的一大亮点。”黄曦介绍,按B路原有道路线形,将和建平村杨桃岭22号、杨桃岭21号及杨桃岭11号这3处历史建筑相遇。为守好占地面积1500多平方米的古建,B路决定绕行。

来源:福州新闻网
编辑:强婕宁 责编:林真贞