Array ( [id] => 118299 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 泉州首条海底隧道可研获批!晋江直通东海只需4分多钟 [editor] => (编辑)王蕾 [has_thumb] => 1 [created] => 2019-09-27 16:41:45 [createdby] => 10052 [createdip] => 192.168.12.200 [published] => 2019-09-27 16:41:45 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 458 [virtual_pv] => 434 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

日前,省发改委批复泉州东海通道工程可行性研究报告。也就是说,泉州首条海底隧道真的要来了!

选址在哪儿?何时开建?来看详情!

海底隧道拟建在哪里?

起于晋江双龙路,采用隧道下穿晋江入海口后对接丰泽区滨海街(综合大道),路线全长约4.8公里,其中隧道长约4.235公里(含敞开段),建设工期45个月,总投资估算约52.45亿元。

隧道有多宽有多高?

项目全线主、辅路均采用双向六车道的城市主干路标准建设,主路设计速度采用60公里/小时,辅路设计速度采用40公里/小时。隧道净宽2×13.25米,净高5米。桥涵荷载设计等级为城-A级,抗震设防烈度8度,设计洪水频率1/100。

按设计行车时速60公里/小时来估算,穿越隧道大概只要4分钟!也就是说,从晋江直通东海只需4分多钟!太赞了!相当于一首歌的时间!

(示意图,以正式公开为准)

批复全文如下——

报来《关于呈报泉州东海通道工程可行性研究报告的请示》(泉发改审〔2019〕97号)及相关材料收悉。经研究,现批复如下:

一、本项目符合《泉州市城市总体规划(2008-2030)》。项目建设有利于完善泉州城市骨架路网,缓解跨海通道交通压力,完善泉州环湾面海城市发展布局,推动环泉州湾地区发展,做大做强湾区经济等。同意建设泉州东海通道工程(项目代码:2018-350500-48-01-002825)。

二、项目建设地点:泉州市丰泽区、晋江市。

三、项目建设单位:泉州市交通投资有限责任公司。

四、项目建设规模和主要内容:本项目起于晋江双龙路,采用隧道下穿晋江入海口后对接丰泽区滨海街(综合大道),路线全长约4.8公里,其中隧道长约4.235公里(含敞开段)。

项目全线主、辅路均采用双向六车道的城市主干路标准建设,主路设计速度采用60公里/小时,辅路设计速度采用40公里/小时。隧道净宽2×13.25米,净高5米。桥涵荷载设计等级为城-A级,抗震设防烈度8度,设计洪水频率1/100。其它技术标准按《城市道路工程设计规范》(CJJ37-2012)执行。

五、投资估算及资金来源:总投资估算约52.45亿元。项目资金由泉州市依法合规自筹,并纳入政府年度预算,不违规举债,不新增地方政府隐性债务风险。

六、项目建设工期:45个月。

七、根据招标投标法以及《必须招标的工程项目规定》(2018年国家发展改革委令第16号)《福建省工程建设项目招标事项核准实施办法》(闽发改法规〔2015〕404号)等相关规定,本项目单位决定勘察、设计、施工、监理以及与工程建设有关的重要设备、材料、服务等采购均采取公开招标方式发包,其招标事项不再核准。请项目单位严格执行招标投标法及其配套政策法规,依法依规认真组织开展招投标活动。

八、项目已按有关规定开展社会稳定风险评估,并经丰泽区和晋江市人民政府审查(泉丰政函〔2018〕34号、晋政函〔2018〕55号),项目总体风险等级为低风险。请严格落实项目风险防范和化解措施,切实维护广大群众的切身利益和社会稳定。

九、请你委督促项目建设单位严格执行生态环保、水利、港航、安全等部门意见,在开展初步设计中及后续建设中,落实各项生态保护、污染防治、水土保持和通航、防洪、安全生产措施。

十、请据此批复抓紧开展初步设计,深化其他相关前期工作,争取项目尽早开工建设。项目建设期间要加强管理,落实征地拆迁相应政策,合理掌握建设工期,确保工程质量。在初步设计中要做好以下工作:

(一)加强基础资料收集,深入实地开展海域水文地质、工程地质勘察。通过加大新技术、新工艺、新材料、新理念的推广应用,深化大断面海底隧道建设关键技术、施工方案、抗震、通风、防灾救援等专题研究,降低工程建设和运营风险。

(二)深化与泉州湾两岸主要交通干道的联系研究,优化通道两端地下互通式立交的布设方案,保障运营期行车安全,研究市政管线过江的搭载方案的可行性。

(三)做好施工期间道路的交通组织设计,确保施工期间道路安全畅通。

(四)在初步设计中,进一步做好投资测算,加强概算管控。

十一、如需对本项目审批文件所确定的内容进行调整,请及时以书面形式向我委报告,并按照有关规定办理。

福建省发展和改革委员会

2019年9月25日

新闻多看点

泉州将规划东海、金屿、百崎三条跨江通道

近年来,泉州规划拟新建东海、金屿和百崎三条跨江通道,它们将分别为连接东海组团和晋江东部片区、城东组团和台商投资区、东海组团和台商投资区的重要通道。其中——东海通道确定采用六车道的海底隧道工程,规划路线长4.8公里。

截至2019年1月,项目进展如下——金屿通道采用双向八车道,目前正开展工程可行性研究等前期工作。百崎通道按海底隧道双向六车道方案设计,目前项目建议书已通过批复。


来源:福建日报
编辑:王蕾 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201909\/22f4b48c8fda48a750a94d7be5bd3ad2.jpeg","id":"1249338"}] [url] => /p/118299.html [all_pv] => 458 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 项目 [1] => 泉州 [2] => 建设 [3] => 通道 [4] => 东海 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 92199 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/92199.html [wapUrl] => http://m.fztvapp.zohi.tv/p/92199.html [published_timestamp] => 1559615336 [published] => 1559615336 [pv] => 111 [virtual_pv] => 409 [all_pv] => 111 [title] => 开辟审批绿色通道 支持养老项目建设 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/a74cce13aab12ac101b10be88691ea49.jpeg ) [1] => Array ( [relateid] => 60885 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/60885.html [wapUrl] => http://m.fztvapp.zohi.tv/p/60885.html [published_timestamp] => 1547281236 [published] => 1547281236 [pv] => 360 [virtual_pv] => 439 [all_pv] => 360 [title] => 福清今年将启动324国道改造 加快建设滨海大通道 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/7ec84efc18142f0cab9ee404a6c74650.jpeg ) [2] => Array ( [relateid] => 60783 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/60783.html [wapUrl] => http://m.fztvapp.zohi.tv/p/60783.html [published_timestamp] => 1547258237 [published] => 1547258237 [pv] => 607 [virtual_pv] => 459 [all_pv] => 607 [title] => 福清今年将启动324国道改造 加快建设滨海大通道 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/47ff371adc4bf14b8efe9b79a945dcb6.png ) [3] => Array ( [relateid] => 84984 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84984.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84984.html [published_timestamp] => 1556881773 [published] => 1556881773 [pv] => 143 [virtual_pv] => 482 [all_pv] => 143 [title] => 中央省市媒体走进泉州 聚焦数字经济建设发展成果 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/6e456e39b054c43f7e2db59caaac8114.JPG ) [4] => Array ( [relateid] => 29418 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/29418.html [wapUrl] => http://m.fztvapp.zohi.tv/p/29418.html [published_timestamp] => 1535176892 [published] => 1535176892 [pv] => 908 [virtual_pv] => 445 [all_pv] => 908 [title] => 两个经济协作区发展访谈录丨泉州:主动融入闽西南经济协作 共同推动高质量赶超跨越 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201808/ee9e78078ee90c7a7976aa5cb91f1200.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201909/22f4b48c8fda48a750a94d7be5bd3ad2.jpeg ) 1

泉州首条海底隧道可研获批!晋江直通东海只需4分多钟

2019-09-27 16:41   福视悦动  

日前,省发改委批复泉州东海通道工程可行性研究报告。也就是说,泉州首条海底隧道真的要来了!

选址在哪儿?何时开建?来看详情!

海底隧道拟建在哪里?

起于晋江双龙路,采用隧道下穿晋江入海口后对接丰泽区滨海街(综合大道),路线全长约4.8公里,其中隧道长约4.235公里(含敞开段),建设工期45个月,总投资估算约52.45亿元。

隧道有多宽有多高?

项目全线主、辅路均采用双向六车道的城市主干路标准建设,主路设计速度采用60公里/小时,辅路设计速度采用40公里/小时。隧道净宽2×13.25米,净高5米。桥涵荷载设计等级为城-A级,抗震设防烈度8度,设计洪水频率1/100。

按设计行车时速60公里/小时来估算,穿越隧道大概只要4分钟!也就是说,从晋江直通东海只需4分多钟!太赞了!相当于一首歌的时间!

(示意图,以正式公开为准)

批复全文如下——

报来《关于呈报泉州东海通道工程可行性研究报告的请示》(泉发改审〔2019〕97号)及相关材料收悉。经研究,现批复如下:

一、本项目符合《泉州市城市总体规划(2008-2030)》。项目建设有利于完善泉州城市骨架路网,缓解跨海通道交通压力,完善泉州环湾面海城市发展布局,推动环泉州湾地区发展,做大做强湾区经济等。同意建设泉州东海通道工程(项目代码:2018-350500-48-01-002825)。

二、项目建设地点:泉州市丰泽区、晋江市。

三、项目建设单位:泉州市交通投资有限责任公司。

四、项目建设规模和主要内容:本项目起于晋江双龙路,采用隧道下穿晋江入海口后对接丰泽区滨海街(综合大道),路线全长约4.8公里,其中隧道长约4.235公里(含敞开段)。

项目全线主、辅路均采用双向六车道的城市主干路标准建设,主路设计速度采用60公里/小时,辅路设计速度采用40公里/小时。隧道净宽2×13.25米,净高5米。桥涵荷载设计等级为城-A级,抗震设防烈度8度,设计洪水频率1/100。其它技术标准按《城市道路工程设计规范》(CJJ37-2012)执行。

五、投资估算及资金来源:总投资估算约52.45亿元。项目资金由泉州市依法合规自筹,并纳入政府年度预算,不违规举债,不新增地方政府隐性债务风险。

六、项目建设工期:45个月。

七、根据招标投标法以及《必须招标的工程项目规定》(2018年国家发展改革委令第16号)《福建省工程建设项目招标事项核准实施办法》(闽发改法规〔2015〕404号)等相关规定,本项目单位决定勘察、设计、施工、监理以及与工程建设有关的重要设备、材料、服务等采购均采取公开招标方式发包,其招标事项不再核准。请项目单位严格执行招标投标法及其配套政策法规,依法依规认真组织开展招投标活动。

八、项目已按有关规定开展社会稳定风险评估,并经丰泽区和晋江市人民政府审查(泉丰政函〔2018〕34号、晋政函〔2018〕55号),项目总体风险等级为低风险。请严格落实项目风险防范和化解措施,切实维护广大群众的切身利益和社会稳定。

九、请你委督促项目建设单位严格执行生态环保、水利、港航、安全等部门意见,在开展初步设计中及后续建设中,落实各项生态保护、污染防治、水土保持和通航、防洪、安全生产措施。

十、请据此批复抓紧开展初步设计,深化其他相关前期工作,争取项目尽早开工建设。项目建设期间要加强管理,落实征地拆迁相应政策,合理掌握建设工期,确保工程质量。在初步设计中要做好以下工作:

(一)加强基础资料收集,深入实地开展海域水文地质、工程地质勘察。通过加大新技术、新工艺、新材料、新理念的推广应用,深化大断面海底隧道建设关键技术、施工方案、抗震、通风、防灾救援等专题研究,降低工程建设和运营风险。

(二)深化与泉州湾两岸主要交通干道的联系研究,优化通道两端地下互通式立交的布设方案,保障运营期行车安全,研究市政管线过江的搭载方案的可行性。

(三)做好施工期间道路的交通组织设计,确保施工期间道路安全畅通。

(四)在初步设计中,进一步做好投资测算,加强概算管控。

十一、如需对本项目审批文件所确定的内容进行调整,请及时以书面形式向我委报告,并按照有关规定办理。

福建省发展和改革委员会

2019年9月25日

新闻多看点

泉州将规划东海、金屿、百崎三条跨江通道

近年来,泉州规划拟新建东海、金屿和百崎三条跨江通道,它们将分别为连接东海组团和晋江东部片区、城东组团和台商投资区、东海组团和台商投资区的重要通道。其中——东海通道确定采用六车道的海底隧道工程,规划路线长4.8公里。

截至2019年1月,项目进展如下——金屿通道采用双向八车道,目前正开展工程可行性研究等前期工作。百崎通道按海底隧道双向六车道方案设计,目前项目建议书已通过批复。


来源:福建日报
编辑:王蕾 责编:林真贞