Array ( [id] => 124251 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 通车倒计时!平潭海峡公铁两用大桥施工进入扫尾阶段 [editor] => (实习)陈洁 [has_thumb] => 1 [created] => 2019-10-24 09:15:39 [createdby] => 10176 [createdip] => 192.168.12.13 [published] => 2019-10-24 09:15:39 [publishedby] => 10176 [modified] => 2019-10-24 09:24:56 [modifiedby] => 10176 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 911 [virtual_pv] => 418 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

好消息!平潭海峡公铁两用大桥又有新进展了!

记者从大桥建设项目部了解到,目前大桥主体已经全部完工,正在进行工程的扫尾工作,预计明年元旦公路可实现通车。

22日上午,在平潭海峡公铁两用大桥苏澳段的施工现场,工人们正在抓紧铁路梁两侧的风屏障施工。风屏障上,均匀分布着许多大小一致的圆形镂空。福平铁路四标二分部安全总监李炳峰介绍,这一设计在降低风力的同时,也能减少风屏障的整体受力,延长风屏障的使用寿命,同时又保证海上风光可以不被完全隔绝。

“因为平潭风比较大,风屏障可以有效减低风力,确保火车、汽车可以在桥上正常通行。”李炳峰说,按一季风期来测算,安装风屏障后大约可以减少30%到40%的风力。

风屏障设计是平潭海峡公铁两用大桥的建设特色之一。目前,铁路梁已经全部启动风屏障工程施工,公路梁的风屏障施工也即将开始。“公路比较简单,先把风屏障装上去,然后防护栏装上去就行了,计划11月份开始风屏障施工,争取年底前做完,预计明年元旦公路就可以通车了。”李炳峰说。

除了风屏障的施工,大桥的各项附属工程也都进入收尾阶段,包括大桥主体的缺陷修补与施工现场整治,以及临时支架和临时房屋的拆除等等。

平潭海峡公铁两用大桥全长16.34公里,大桥下层设计为时速200公里的双线I级铁路,上层设计为时速100公里的六车道高速公路。大桥建成后,平潭将和福州形成半小时“经济生活圈”,进一步提升平潭作为海峡两岸经贸合作、文化交流和人员往来的重要通道的地位。

今年9月25日,平潭海峡公铁两用大桥实现全桥贯通!

平潭海峡公铁两用大桥也是目前世界最长、我国第一座跨海峡公铁大桥。

来!屏幕横过来,滑动指尖到桥上看看~

期待大桥早日通车!


来源:福州日报微信
编辑:陈洁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 风屏障设计是平潭海峡公铁两用大桥的建设特色之一。 [thumb] => [{"url":"\/a\/10001\/201910\/83a5b9db97c9a9c1a70b129f299ed115.jpeg","id":"1339227"}] [url] => /p/124251.html [all_pv] => 911 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 大桥 [1] => 屏障 [2] => 平潭 [3] => 公铁 [4] => 两用 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 124146 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/124146.html [wapUrl] => http://m.fztvapp.zohi.tv/p/124146.html [published_timestamp] => 1571820370 [published] => 1571820370 [pv] => 113 [virtual_pv] => 442 [all_pv] => 113 [title] => 平潭海峡公铁两用大桥施工进入扫尾 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/01f070a5bd5805c9a94ae39b45d6f73f.jpeg ) [1] => Array ( [relateid] => 117606 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/117606.html [wapUrl] => http://m.fztvapp.zohi.tv/p/117606.html [published_timestamp] => 1569376005 [published] => 1569376005 [pv] => 81 [virtual_pv] => 402 [all_pv] => 81 [title] => 9月25日!平潭海峡公铁两用大桥全桥贯通! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/cb37aaad3490ee67eabb85fb8cc0c01e.jpeg ) [2] => Array ( [relateid] => 101700 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/101700.html [wapUrl] => http://m.fztvapp.zohi.tv/p/101700.html [published_timestamp] => 1563430222 [published] => 1563430222 [pv] => 45 [virtual_pv] => 401 [all_pv] => 45 [title] => 福平铁路平潭海峡公铁两用大桥平潭段实现全部贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/dbf76987eed8c4ba8a65a62cc9dfef72.jpeg ) [3] => Array ( [relateid] => 92709 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/92709.html [wapUrl] => http://m.fztvapp.zohi.tv/p/92709.html [published_timestamp] => 1559809772 [published] => 1559809772 [pv] => 371 [virtual_pv] => 452 [all_pv] => 371 [title] => 平潭海峡公铁两用大桥元洪航道桥合龙 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/c659dc249a58f92e23261436457acd48.jpeg ) [4] => Array ( [relateid] => 27021 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/27021.html [wapUrl] => http://m.fztvapp.zohi.tv/p/27021.html [published_timestamp] => 1532662021 [published] => 1532662021 [pv] => 577 [virtual_pv] => 476 [all_pv] => 577 [title] => 平潭海峡公铁两用大桥明年完成土建施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/8243c8ce4881abc8753daaf5bf378883.jpeg@w882_h496.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201910/83a5b9db97c9a9c1a70b129f299ed115.jpeg ) 1

通车倒计时!平潭海峡公铁两用大桥施工进入扫尾阶段

2019-10-24 09:15   福视悦动  

好消息!平潭海峡公铁两用大桥又有新进展了!

记者从大桥建设项目部了解到,目前大桥主体已经全部完工,正在进行工程的扫尾工作,预计明年元旦公路可实现通车。

22日上午,在平潭海峡公铁两用大桥苏澳段的施工现场,工人们正在抓紧铁路梁两侧的风屏障施工。风屏障上,均匀分布着许多大小一致的圆形镂空。福平铁路四标二分部安全总监李炳峰介绍,这一设计在降低风力的同时,也能减少风屏障的整体受力,延长风屏障的使用寿命,同时又保证海上风光可以不被完全隔绝。

“因为平潭风比较大,风屏障可以有效减低风力,确保火车、汽车可以在桥上正常通行。”李炳峰说,按一季风期来测算,安装风屏障后大约可以减少30%到40%的风力。

风屏障设计是平潭海峡公铁两用大桥的建设特色之一。目前,铁路梁已经全部启动风屏障工程施工,公路梁的风屏障施工也即将开始。“公路比较简单,先把风屏障装上去,然后防护栏装上去就行了,计划11月份开始风屏障施工,争取年底前做完,预计明年元旦公路就可以通车了。”李炳峰说。

除了风屏障的施工,大桥的各项附属工程也都进入收尾阶段,包括大桥主体的缺陷修补与施工现场整治,以及临时支架和临时房屋的拆除等等。

平潭海峡公铁两用大桥全长16.34公里,大桥下层设计为时速200公里的双线I级铁路,上层设计为时速100公里的六车道高速公路。大桥建成后,平潭将和福州形成半小时“经济生活圈”,进一步提升平潭作为海峡两岸经贸合作、文化交流和人员往来的重要通道的地位。

今年9月25日,平潭海峡公铁两用大桥实现全桥贯通!

平潭海峡公铁两用大桥也是目前世界最长、我国第一座跨海峡公铁大桥。

来!屏幕横过来,滑动指尖到桥上看看~

期待大桥早日通车!


来源:福州日报微信
编辑:陈洁 责编:林真贞