Array ( [id] => 124752 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州滨海新城临空经济区安置房预计明年上半年全面封顶 [editor] => (编辑)翁彬冰 [has_thumb] => 1 [created] => 2019-10-26 15:14:18 [createdby] => 10022 [createdip] => 192.168.12.3 [published] => 2019-10-26 15:14:18 [publishedby] => 10022 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 476 [virtual_pv] => 464 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

10月份以来,天气晴好,工程建设也正式进入“施工黄金期”,福州滨海新城持续掀起了“大干100天,当好排头兵”主题竞赛活动新高潮。临空经济区安置房一、二期自2019年3月29日开工以来,两个项目加快建设步伐,目前均已完成桩基工程施工,正在进行地下室结构建设,预计明年上半年实现全面封顶。

10月18日,记者来到临空经济区安置房项目建设工地,安置房一期(龙翔小区)和二期(棋山花园)项目现场热火朝天的繁忙景象映入眼帘:塔吊林立,机器轰鸣,运输车辆来回穿梭,工人们正进行紧张作业。

临空经济区安置房一期(龙翔小区)项目位于文松路东侧、仙宅路北侧、仙昙路南侧,占地面积12.1万平方米,总投资约16.5亿元,规划建设29栋11至12层共1711套安置房,并配套幼儿园、商业楼等公共设施,总建筑面积为26.1万平方米。

据安置房一期(龙翔小区)项目现场相关负责人介绍,23号、28号住宅楼以及32号商业楼现已进入二层梁板施工阶段,目前正在加快地下室结构建设进度,11月将有部分楼栋进行上部结构施工,整个项目预计明年9月完工。

临空经济区安置房二期(棋山花园)项目位于文鹤路西侧、仙宅路北侧、仙昙路南侧,占地面积9.8万平方米,总投资约15.4亿元,规划建设31栋10至11层共1705套安置房,总建筑面积24.6万平方米,与安置房一期(龙翔小区)共享幼儿园、商业楼等公共设施。

据安置房二期(棋山花园)项目现场相关负责人介绍,该项目分南、北两个区按流水施工顺序进行,目前南区正在进行地下室顶板施工,北区桩基工程已完成验收,计划11月上旬进入上部结构施工阶段,整个项目预计明年年底完工。

据了解,两个安置房项目均为装配式建筑,共计3416套安置房,预计明年上半年均可实现全面封顶。临空经济区安置房项目投用后,将主要用于解决湖南镇、文岭镇及规划综合保税区征迁户的安置,并搭配完善的配套设施,为周边居民和企业员工提供优质的生活服务。


来源:吴航乡情报
编辑:翁彬冰 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201910\/b0f4fadfb54deda7dab01027d7904b2f.jpeg","id":"1344183"}] [url] => /p/124752.html [all_pv] => 476 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 安置 [1] => 临空 [2] => 项目 [3] => 11 [4] => 经济区 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 122940 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/122940.html [wapUrl] => http://m.fztvapp.zohi.tv/p/122940.html [published_timestamp] => 1571370776 [published] => 1571370776 [pv] => 25 [virtual_pv] => 482 [all_pv] => 25 [title] => 福州滨海新城临空经济区安置房加快建设 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201910/a27ed160b3973ae831dd1f82b94266f5.jpeg ) [1] => Array ( [relateid] => 104736 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/104736.html [wapUrl] => http://m.fztvapp.zohi.tv/p/104736.html [published_timestamp] => 1564624884 [published] => 1564624884 [pv] => 36 [virtual_pv] => 449 [all_pv] => 36 [title] => 福州滨海新城临空经济区安置房项目进展顺利 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201908/524315a59c6693ae7c6e6435d8c5d797.jpeg ) [2] => Array ( [relateid] => 77634 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/77634.html [wapUrl] => http://m.fztvapp.zohi.tv/p/77634.html [published_timestamp] => 1553944815 [published] => 1553944815 [pv] => 83 [virtual_pv] => 426 [all_pv] => 83 [title] => 滨海新城发展按下"加速键" 开工项目亮点纷呈 总投资超百亿元 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/586e06e560820b1b2b49bb76b1bd25ee.JPG ) [3] => Array ( [relateid] => 14306 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14306.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14306.html [published_timestamp] => 1516677299 [published] => 1516677299 [pv] => 631 [virtual_pv] => 0 [all_pv] => 631 [title] => 滨海新城临空经济区今年拟开工30个项目 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/03c8c10d38d5f7c4d91ca2afa757f67f.jpeg ) [4] => Array ( [relateid] => 14296 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14296.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14296.html [published_timestamp] => 1516675171 [published] => 1516675171 [pv] => 770 [virtual_pv] => 0 [all_pv] => 770 [title] => 滨海新城临空经济区今年拟开工30个项目 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201801/6e615c66b1e69ff291dc318a06137a9f.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201910/b0f4fadfb54deda7dab01027d7904b2f.jpeg ) 1

福州滨海新城临空经济区安置房预计明年上半年全面封顶

2019-10-26 15:14   福视悦动  

10月份以来,天气晴好,工程建设也正式进入“施工黄金期”,福州滨海新城持续掀起了“大干100天,当好排头兵”主题竞赛活动新高潮。临空经济区安置房一、二期自2019年3月29日开工以来,两个项目加快建设步伐,目前均已完成桩基工程施工,正在进行地下室结构建设,预计明年上半年实现全面封顶。

10月18日,记者来到临空经济区安置房项目建设工地,安置房一期(龙翔小区)和二期(棋山花园)项目现场热火朝天的繁忙景象映入眼帘:塔吊林立,机器轰鸣,运输车辆来回穿梭,工人们正进行紧张作业。

临空经济区安置房一期(龙翔小区)项目位于文松路东侧、仙宅路北侧、仙昙路南侧,占地面积12.1万平方米,总投资约16.5亿元,规划建设29栋11至12层共1711套安置房,并配套幼儿园、商业楼等公共设施,总建筑面积为26.1万平方米。

据安置房一期(龙翔小区)项目现场相关负责人介绍,23号、28号住宅楼以及32号商业楼现已进入二层梁板施工阶段,目前正在加快地下室结构建设进度,11月将有部分楼栋进行上部结构施工,整个项目预计明年9月完工。

临空经济区安置房二期(棋山花园)项目位于文鹤路西侧、仙宅路北侧、仙昙路南侧,占地面积9.8万平方米,总投资约15.4亿元,规划建设31栋10至11层共1705套安置房,总建筑面积24.6万平方米,与安置房一期(龙翔小区)共享幼儿园、商业楼等公共设施。

据安置房二期(棋山花园)项目现场相关负责人介绍,该项目分南、北两个区按流水施工顺序进行,目前南区正在进行地下室顶板施工,北区桩基工程已完成验收,计划11月上旬进入上部结构施工阶段,整个项目预计明年年底完工。

据了解,两个安置房项目均为装配式建筑,共计3416套安置房,预计明年上半年均可实现全面封顶。临空经济区安置房项目投用后,将主要用于解决湖南镇、文岭镇及规划综合保税区征迁户的安置,并搭配完善的配套设施,为周边居民和企业员工提供优质的生活服务。