Array ( [id] => 126327 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 好消息!新洪塘大桥左幅将于春节前通车 [editor] => (编辑)王蕾 [has_thumb] => 1 [created] => 2019-11-02 14:30:13 [createdby] => 10052 [createdip] => 192.168.12.200 [published] => 2019-11-02 14:30:13 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 472 [virtual_pv] => 432 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

日前,记者从中交二航局洪塘大桥拓宽改建工程项目部获悉,洪塘大桥拓宽改建工程主桥钢桥面混凝土开始铺设,大桥左幅计划于春节前通车,届时,将开始拆除老桥,过往车辆将转到新桥上行驶。

▲建设中的新洪塘大桥 陈炜/摄

采用超高强韧性砼铺装工艺 

据介绍,新洪塘大桥主桥一阶段摊铺长度800米,面积11760平方米,共划分为4个浇筑段,每个浇筑段长200米。

▲新洪塘大桥左右幅同时施工 吴国棋/摄

近日,记者在洪塘大桥拓宽改建工程建设工地看到,电焊机火花四溅,施工机械繁忙运转,工人们正忙着焊接桥面钢筋和护栏模板安装,虽然天气转凉,桥面上微风阵阵,但仍然吹不干工人们脸颊的汗珠。

▲施工机械吊装建设材料 吴国棋/摄

“新洪塘大桥主桥钢桥面铺装采用55毫米厚超高强韧性混凝土。”项目部现场生产经理周宴平告诉记者,“这是一种具有超高性能、超高韧性及超长耐久性的水泥基复合材料,通过其与钢桥面组合,可有效减轻钢梁结构自重,大大降低钢桥面疲劳开裂的风险,且运营期间维修成本低。”

▲主桥钢桥面混凝土铺设 吴国棋/摄

▲护栏模板安装 吴国棋/摄

根据主桥超高强韧性砼铺装施工工艺,摊铺完成后,施工方还将对其进行高温蒸汽养护,以降低收缩率,增强体积稳定性,提高抗压强度。

▲主桥钢桥面混凝土开始铺设后,正进行高温蒸汽养护 吴国棋/摄

左幅桥面混凝土铺设12月完成

新洪塘大桥主桥为独塔双索面自锚式悬索桥,总体布置依次为50米锚跨、150米主跨、150米边跨、50米锚跨,采用半漂浮结构体系,主梁采用钢箱梁。

▲右幅下部施工基本完成 吴国棋/摄

2019年是新洪塘大桥项目攻坚之年,因“保畅通”的设计理念,主桥按两阶段进行施工。其中,一阶段摊铺两侧各1/3幅,二阶段待中间1/3幅钢梁架设完成后进行摊铺。目前,项目部每天安排了200多号工人奋战在项目施工一线,一阶段下部结构已全部施工完成,桥面铺装已完成近7成。按照目前进度,新洪塘大桥左幅桥面铺设将于12月中旬前完成,届时将转入桥面的沥青铺设与护栏、灯光等附属工程施工,力争明年春节前左幅建成通车。

▲左幅桥面混凝土铺装已完成近7成 吴国棋/摄

据悉,洪塘大桥是连接福州与上街大学新区的一条重要跨江通道,每天交通压力大。新洪塘大桥于2017年开工,路线总长约2.2公里,主线采用设计速度60公里/小时的双向八车道标准建设,新洪塘大桥通车后,将实现全线无红绿灯通行,大大缓解大学城区域往福州的交通拥堵情况。


来源:遇见闽侯
编辑:王蕾 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201911\/5374a3cea3c2e3ed3f98f48e1661a5a5.jpeg","id":"1366044"}] [url] => /p/126327.html [all_pv] => 472 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 桥面 [1] => 大桥 [2] => 主桥 [3] => 新洪塘 [4] => 吴国 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 116214 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/116214.html [wapUrl] => http://m.fztvapp.zohi.tv/p/116214.html [published_timestamp] => 1568857398 [published] => 1568857398 [pv] => 81 [virtual_pv] => 423 [all_pv] => 81 [title] => 新洪塘大桥正式启动主桥桥面施工 预计2020年通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/0e1d6916dcda986c8b1f5f1dc1a5aae3.jpeg ) [1] => Array ( [relateid] => 102735 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/102735.html [wapUrl] => http://m.fztvapp.zohi.tv/p/102735.html [published_timestamp] => 1563870533 [published] => 1563870533 [pv] => 87 [virtual_pv] => 392 [all_pv] => 87 [title] => 道庆洲大桥跨江主桥钢桁梁首件吊装成功 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/8f656d25f052574fac3250301b7b1a8d.jpeg ) [2] => Array ( [relateid] => 93972 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/93972.html [wapUrl] => http://m.fztvapp.zohi.tv/p/93972.html [published_timestamp] => 1560391481 [published] => 1560391481 [pv] => 251 [virtual_pv] => 375 [all_pv] => 251 [title] => 新洪塘大桥主塔本周“上梁” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/4e7e02a5331658d3de1a803a18bf3fc4.jpeg ) [3] => Array ( [relateid] => 26269 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26269.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26269.html [published_timestamp] => 1531829146 [published] => 1531829146 [pv] => 79 [virtual_pv] => 432 [all_pv] => 79 [title] => 新洪塘大桥"双脚"已站立江中 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/8fb118b1dd7a2e836ddda757c1ec4e50.JPG ) [4] => Array ( [relateid] => 26539 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26539.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26539.html [published_timestamp] => 1532179285 [published] => 1532179285 [pv] => 1215 [virtual_pv] => 397 [all_pv] => 1215 [title] => 新洪塘大桥建设稳步推进 预计2020年建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/a6a8907089bf1fb6a6533484f9745259.JPG@w720_h540.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/201911/5374a3cea3c2e3ed3f98f48e1661a5a5.jpeg ) 1

好消息!新洪塘大桥左幅将于春节前通车

2019-11-02 14:30   福视悦动  

日前,记者从中交二航局洪塘大桥拓宽改建工程项目部获悉,洪塘大桥拓宽改建工程主桥钢桥面混凝土开始铺设,大桥左幅计划于春节前通车,届时,将开始拆除老桥,过往车辆将转到新桥上行驶。

▲建设中的新洪塘大桥 陈炜/摄

采用超高强韧性砼铺装工艺 

据介绍,新洪塘大桥主桥一阶段摊铺长度800米,面积11760平方米,共划分为4个浇筑段,每个浇筑段长200米。

▲新洪塘大桥左右幅同时施工 吴国棋/摄

近日,记者在洪塘大桥拓宽改建工程建设工地看到,电焊机火花四溅,施工机械繁忙运转,工人们正忙着焊接桥面钢筋和护栏模板安装,虽然天气转凉,桥面上微风阵阵,但仍然吹不干工人们脸颊的汗珠。

▲施工机械吊装建设材料 吴国棋/摄

“新洪塘大桥主桥钢桥面铺装采用55毫米厚超高强韧性混凝土。”项目部现场生产经理周宴平告诉记者,“这是一种具有超高性能、超高韧性及超长耐久性的水泥基复合材料,通过其与钢桥面组合,可有效减轻钢梁结构自重,大大降低钢桥面疲劳开裂的风险,且运营期间维修成本低。”

▲主桥钢桥面混凝土铺设 吴国棋/摄

▲护栏模板安装 吴国棋/摄

根据主桥超高强韧性砼铺装施工工艺,摊铺完成后,施工方还将对其进行高温蒸汽养护,以降低收缩率,增强体积稳定性,提高抗压强度。

▲主桥钢桥面混凝土开始铺设后,正进行高温蒸汽养护 吴国棋/摄

左幅桥面混凝土铺设12月完成

新洪塘大桥主桥为独塔双索面自锚式悬索桥,总体布置依次为50米锚跨、150米主跨、150米边跨、50米锚跨,采用半漂浮结构体系,主梁采用钢箱梁。

▲右幅下部施工基本完成 吴国棋/摄

2019年是新洪塘大桥项目攻坚之年,因“保畅通”的设计理念,主桥按两阶段进行施工。其中,一阶段摊铺两侧各1/3幅,二阶段待中间1/3幅钢梁架设完成后进行摊铺。目前,项目部每天安排了200多号工人奋战在项目施工一线,一阶段下部结构已全部施工完成,桥面铺装已完成近7成。按照目前进度,新洪塘大桥左幅桥面铺设将于12月中旬前完成,届时将转入桥面的沥青铺设与护栏、灯光等附属工程施工,力争明年春节前左幅建成通车。

▲左幅桥面混凝土铺装已完成近7成 吴国棋/摄

据悉,洪塘大桥是连接福州与上街大学新区的一条重要跨江通道,每天交通压力大。新洪塘大桥于2017年开工,路线总长约2.2公里,主线采用设计速度60公里/小时的双向八车道标准建设,新洪塘大桥通车后,将实现全线无红绿灯通行,大大缓解大学城区域往福州的交通拥堵情况。


来源:遇见闽侯
编辑:王蕾 责编:林真贞