Array ( [id] => 131346 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 大学新区首个安置型商品房项目主体结构本月底封顶 [editor] => (实习)林婉宁 [has_thumb] => 1 [created] => 2019-11-24 15:27:14 [createdby] => 10182 [createdip] => 120.35.7.76 [published] => 2019-11-24 15:27:14 [publishedby] => 10182 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 1 [pv] => 403 [virtual_pv] => 380 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 5 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

24日,记者从大学新区二期安置房建设指挥部获悉,作为大学新区首个安置型商品房项目,福州上街美岐红星商住花园主体结构即将全部封顶。

上街美岐红星商住花园正加速建设。

上街美岐红星商住花园是闽侯县重要的民生补短板项目。该项目紧邻美岐村源江路,占地面积64.33亩,总建筑面积约12.87万平方米,总投资6亿元,项目采取市场化运作模式,共建设9幢共1163套安置房。除了住宅用房外,该项目还建设有商业用房及配套地下停车场,配建公用设施居民活动用房、社区工作用房、社区卫生服务站、居家养老服务点及社区室外活动场地等。

现场,项目经理陈水金告诉记者,项目部对施工方案和进度计划进行了再优化再梳理,保质保量推进项目建设。“目前正进行主体结构梁板钢筋绑扎、砌体等施工,按照施工进度,预计11月内项目主体结构将全部封顶,明年初砌体工程即可全面完成。同时,外墙粉刷、铝合金门窗安装、内墙涂料、进户门安装等装修工序也将同步进行。”陈水金说。


来源:福州日报
编辑:林婉宁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 作为大学新区首个安置型商品房项目,福州上街美岐红星商住花园主体结构即将全部封顶。 [thumb] => [{"url":"\/a\/10001\/201911\/fc54bc240d770e07c8c9b99f8d28c2c1.jpeg","id":"1434564"}] [url] => /p/131346.html [all_pv] => 403 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 用房 [1] => 美岐 [2] => 项目 [3] => 商住 [4] => 红星 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 26480 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26480.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26480.html [published_timestamp] => 1532092770 [published] => 1532092770 [pv] => 1079 [virtual_pv] => 412 [all_pv] => 1079 [title] => 红星及周边旧改项目民房拆除完毕 拆除总建筑面积超96万平方米 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/8669561309584fbaa8490f60c7d7a123.JPG@w720_h540.JPG ) [1] => Array ( [relateid] => 26436 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26436.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26436.html [published_timestamp] => 1532055988 [published] => 1532055988 [pv] => 1248 [virtual_pv] => 386 [all_pv] => 1248 [title] => 红星及周边旧屋区改造项目民房拆除完毕 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/857bf9a239b4361b3ecb22cf35cc02d6.jpeg ) [2] => Array ( [relateid] => 19738 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/19738.html [wapUrl] => http://m.fztvapp.zohi.tv/p/19738.html [published_timestamp] => 1524191114 [published] => 1524191114 [pv] => 430 [virtual_pv] => 375 [all_pv] => 430 [title] => 台江区红星及周边地块旧改项目征收扫尾进展顺利 总签约率和总搬迁率双达98% [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201804/651dc8392434ea53eb94c01980f56fe3.jpeg ) [3] => Array ( [relateid] => 28519 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/28519.html [wapUrl] => http://m.fztvapp.zohi.tv/p/28519.html [published_timestamp] => 1534418681 [published] => 1534418681 [pv] => 2033 [virtual_pv] => 423 [all_pv] => 2033 [title] => 商住两用房装修 业主更改消防设施谁来管? [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201808/02b29a74e202b748718108edff958d36.jpeg ) [4] => Array ( [relateid] => 55482 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/55482.html [wapUrl] => http://m.fztvapp.zohi.tv/p/55482.html [published_timestamp] => 1545217833 [published] => 1545217833 [pv] => 1032 [virtual_pv] => 461 [all_pv] => 1032 [title] => 全力推动高质量发展 我市第四季度集中开工183个重大项目 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201812/aa69ae5233406ae85a943fd57084cc12.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/201911/fc54bc240d770e07c8c9b99f8d28c2c1.jpeg ) 1

大学新区首个安置型商品房项目主体结构本月底封顶

2019-11-24 15:27   福视悦动  

24日,记者从大学新区二期安置房建设指挥部获悉,作为大学新区首个安置型商品房项目,福州上街美岐红星商住花园主体结构即将全部封顶。

上街美岐红星商住花园正加速建设。

上街美岐红星商住花园是闽侯县重要的民生补短板项目。该项目紧邻美岐村源江路,占地面积64.33亩,总建筑面积约12.87万平方米,总投资6亿元,项目采取市场化运作模式,共建设9幢共1163套安置房。除了住宅用房外,该项目还建设有商业用房及配套地下停车场,配建公用设施居民活动用房、社区工作用房、社区卫生服务站、居家养老服务点及社区室外活动场地等。

现场,项目经理陈水金告诉记者,项目部对施工方案和进度计划进行了再优化再梳理,保质保量推进项目建设。“目前正进行主体结构梁板钢筋绑扎、砌体等施工,按照施工进度,预计11月内项目主体结构将全部封顶,明年初砌体工程即可全面完成。同时,外墙粉刷、铝合金门窗安装、内墙涂料、进户门安装等装修工序也将同步进行。”陈水金说。


来源:福州日报
编辑:林婉宁 责编:林真贞


相关阅读

0 条评论
最新