Array ( [id] => 131754 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州工业路这个路段将提升改造!全长3.66千米 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2019-11-26 15:18:28 [createdby] => 10056 [createdip] => 120.35.7.76 [published] => 2019-11-26 15:18:28 [publishedby] => 10056 [modified] => 2019-11-26 15:19:16 [modifiedby] => 10056 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 519 [virtual_pv] => 461 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

为缓解西二环交通压力,完善片区路网,福州市工业路(上浦路-杨桥路)将进行提升改造。道路改造全长约3.66千米(其中:工业路改造长2.50千米,上浦路改造长0.73千米,乌山西路改造长0.43千米),道路红线宽度40米。项目主要建设内容包括道路、桥梁、人行天桥、人行地道、给排水、配套管线、电气照明、绿化、交通及安全设施等。建设工期为20个月。

近日,福州市城乡建设发展有限公司《关于申请审批福州市工业路(上浦路-杨桥路)提升改造工程项目可行性研究报告的请示》获福州市发展和改革委员会批复,原文如下:

网站截图

福州市城乡建设发展有限公司:

你司《关于申请审批福州市工业路(上浦路-杨桥路)提升改造工程项目可行性研究报告的请示》(榕发市政〔2019〕1128号)及有关附件收悉。为缓解西二环交通压力,完善片区路网,经研究,原则同意福州市工业路(上浦路-杨桥路)提升改造工程可行性研究报告(项目代码:2019-350100-48-01-032281),具体批复如下:

一、项目单位:福州市城乡建设发展有限公司

二、建设地点:项目起于上浦路金山大桥桥头,终于杨桥路。

三、建设规模和内容

道路改造全长约3.66千米(其中:工业路改造长2.50千米,上浦路改造长0.73千米,乌山西路改造长0.43千米),道路红线宽度40米。项目主要建设内容包括道路、桥梁、人行天桥、人行地道、给排水、配套管线、电气照明、绿化、交通及安全设施等。

四、主要技术指标

(一)道路等级:城市主干路;

(二)设计速度:工业路(主路)、上浦路(相交道路)、乌山西路(相交道路)—50公里/小时,工业路(辅路)、工业-上浦节点互通匝道—40公里/小时,工业-乌山节点互通匝道—30公里/小时;

(三)设计荷载:路面—标准轴载BZZ-100,桥梁—城-A级。

五、项目总投资及资金来源

项目总投资估算124278.21万元,其中工程费用91268.36万元、工程建设其他费用23804.06万元(含建设用地费13180.62万元)、预备费9205.79万元。项目建设资金由福州市财政统筹安排。

六、建设工期:20个月

七、社会稳定风险评估

项目单位委托开展社会稳定风险分析,并委托对项目社会稳定风险分析进行评估,评估结论为低风险等级。福州市城乡建设局同意项目社会稳定风险等级为低风险。请项目单位认真落实各项风险防范和化解措施,切实维护群众利益,确保项目顺利实施。

八、其他要求:请项目单位据此批复并结合评估报告和专家组意见,进一步深化前期工作,委托有相应资质的设计单位编制初步设计文件,报我委审批。

福州市发展和改革委员会

2019年11月18日


来源:福州市人民政府网站
编辑:强婕宁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201911\/35cb17fd4cffb9f7c92405f7bfa2027d.png","id":"1440873"}] [url] => /p/131754.html [all_pv] => 519 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 福州市 [1] => 浦路 [2] => 改造 [3] => 项目 [4] => 道路 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 19280 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/19280.html [wapUrl] => http://m.fztvapp.zohi.tv/p/19280.html [published_timestamp] => 1523664791 [published] => 1523664791 [pv] => 235 [virtual_pv] => 429 [all_pv] => 235 [title] => 福州拟对9个建筑项目进行节能改造 面积超44万㎡ 改造后节能率都在20%以上 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201804/ca2a616d0837370c303348a8445354e2.jpg ) [1] => Array ( [relateid] => 113958 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/113958.html [wapUrl] => http://m.fztvapp.zohi.tv/p/113958.html [published_timestamp] => 1567998878 [published] => 1567998878 [pv] => 65 [virtual_pv] => 413 [all_pv] => 65 [title] => 鹤林片区海绵改造工程又有9个项目完工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/c83a5585641b16d2f432def86a904451.jpeg ) [2] => Array ( [relateid] => 109593 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/109593.html [wapUrl] => http://m.fztvapp.zohi.tv/p/109593.html [published_timestamp] => 1566353647 [published] => 1566353647 [pv] => 177 [virtual_pv] => 456 [all_pv] => 177 [title] => 福州精准景观改造任务出炉 年底前157个项目基本完成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201908/0e741a7b71d36ca6ee9779a2199b29e8.jpeg ) [3] => Array ( [relateid] => 17087 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/17087.html [wapUrl] => http://m.fztvapp.zohi.tv/p/17087.html [published_timestamp] => 1520773488 [published] => 1520773488 [pv] => 1033 [virtual_pv] => 20 [all_pv] => 1033 [title] => 改造道路缓堵情 治理乱象保畅通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201803/7c106110f28feb90dec827a3400cdd62.JPG@w720_h540.JPG ) [4] => Array ( [relateid] => 26486 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26486.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26486.html [published_timestamp] => 1532093768 [published] => 1532093768 [pv] => 861 [virtual_pv] => 409 [all_pv] => 861 [title] => 地铁2号线沿线道路启动修复提升工程 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/abaee66e8f4f35969031b362d1430785.JPG@w720_h540.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/201911/35cb17fd4cffb9f7c92405f7bfa2027d.png ) 1

福州工业路这个路段将提升改造!全长3.66千米

2019-11-26 15:18   福视悦动  

为缓解西二环交通压力,完善片区路网,福州市工业路(上浦路-杨桥路)将进行提升改造。道路改造全长约3.66千米(其中:工业路改造长2.50千米,上浦路改造长0.73千米,乌山西路改造长0.43千米),道路红线宽度40米。项目主要建设内容包括道路、桥梁、人行天桥、人行地道、给排水、配套管线、电气照明、绿化、交通及安全设施等。建设工期为20个月。

近日,福州市城乡建设发展有限公司《关于申请审批福州市工业路(上浦路-杨桥路)提升改造工程项目可行性研究报告的请示》获福州市发展和改革委员会批复,原文如下:

网站截图

福州市城乡建设发展有限公司:

你司《关于申请审批福州市工业路(上浦路-杨桥路)提升改造工程项目可行性研究报告的请示》(榕发市政〔2019〕1128号)及有关附件收悉。为缓解西二环交通压力,完善片区路网,经研究,原则同意福州市工业路(上浦路-杨桥路)提升改造工程可行性研究报告(项目代码:2019-350100-48-01-032281),具体批复如下:

一、项目单位:福州市城乡建设发展有限公司

二、建设地点:项目起于上浦路金山大桥桥头,终于杨桥路。

三、建设规模和内容

道路改造全长约3.66千米(其中:工业路改造长2.50千米,上浦路改造长0.73千米,乌山西路改造长0.43千米),道路红线宽度40米。项目主要建设内容包括道路、桥梁、人行天桥、人行地道、给排水、配套管线、电气照明、绿化、交通及安全设施等。

四、主要技术指标

(一)道路等级:城市主干路;

(二)设计速度:工业路(主路)、上浦路(相交道路)、乌山西路(相交道路)—50公里/小时,工业路(辅路)、工业-上浦节点互通匝道—40公里/小时,工业-乌山节点互通匝道—30公里/小时;

(三)设计荷载:路面—标准轴载BZZ-100,桥梁—城-A级。

五、项目总投资及资金来源

项目总投资估算124278.21万元,其中工程费用91268.36万元、工程建设其他费用23804.06万元(含建设用地费13180.62万元)、预备费9205.79万元。项目建设资金由福州市财政统筹安排。

六、建设工期:20个月

七、社会稳定风险评估

项目单位委托开展社会稳定风险分析,并委托对项目社会稳定风险分析进行评估,评估结论为低风险等级。福州市城乡建设局同意项目社会稳定风险等级为低风险。请项目单位认真落实各项风险防范和化解措施,切实维护群众利益,确保项目顺利实施。

八、其他要求:请项目单位据此批复并结合评估报告和专家组意见,进一步深化前期工作,委托有相应资质的设计单位编制初步设计文件,报我委审批。

福州市发展和改革委员会

2019年11月18日