Array ( [id] => 132762 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福厦高铁西溪特大桥进入规模化架梁阶段 [editor] => (编辑)王蕾 [has_thumb] => 1 [created] => 2019-12-01 11:18:57 [createdby] => 10052 [createdip] => 120.35.7.76 [published] => 2019-12-01 11:18:57 [publishedby] => 10052 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 412 [virtual_pv] => 404 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

福厦高铁西溪特大桥架梁施工现场,一孔长32米、重近900吨的庞然大物———预制箱梁,缓缓从地面向空中转移,精准落在桥面的运梁车上。目前,西溪特大桥进入规模化架梁阶段,运梁车将与架桥机配合,完成665孔箱梁的架设任务。据悉,目前已完成架梁约1公里,特大桥雏形初显。

福厦高铁西溪特大桥进行箱梁架设作业。(王协云航拍器摄)

昨日,记者在中铁四局福厦高铁8标西溪特大桥施工现场看到,一台硕大的提梁机正在与运梁车配合“演出”:铁路预制箱梁被提梁机缓缓提起,在10多米高的上方,运梁车已经停在桥面上接应。历时一个多小时的提拉、平移、定位,箱梁才从地面被搬到运梁车上。这台长约40米的运梁车共有16组、64个直径与成年人身高相当的大轮胎,从外观上看非常壮观,载着箱梁前进时就像是一座巨大的移动城堡。

西溪特大桥前期吊装架设三孔箱梁,形成一个作业面供运梁车在上方行驶;运梁车接过从地面吊上来的箱梁,载着它到达指定位置,与架桥机配合完成架梁。截至昨日,西溪特大桥已完成29孔箱梁的架设。

福厦高铁建设正在全力拼抢工期,厦门段控制性工程西溪特大桥更是处于全面攻坚阶段,工人们同步进行箱梁预制和墩身施工,多点开花,展现“高铁速度”。 


来源:厦门网
编辑:王蕾 责编:庄颖


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/201912\/969c428a45be744d3c75713a27d4042b.jpeg","id":"1456395"}] [url] => /p/132762.html [all_pv] => 412 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 箱梁 [1] => 西溪 [2] => 大桥 [3] => 福厦 [4] => 架梁 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 84309 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84309.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84309.html [published_timestamp] => 1556587188 [published] => 1556587188 [pv] => 339 [virtual_pv] => 416 [all_pv] => 339 [title] => 新进展!福厦高铁首孔箱梁成功架设,2022年9月通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/7d81d405710cb89d09c0e5b79d9bf6cb.jpeg ) [1] => Array ( [relateid] => 88227 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/88227.html [wapUrl] => http://m.fztvapp.zohi.tv/p/88227.html [published_timestamp] => 1558072230 [published] => 1558072230 [pv] => 282 [virtual_pv] => 482 [all_pv] => 282 [title] => 福厦客专正式进入线上架梁施工 建设速度将全面加快 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/4d49e8a15a53084bb768404b7ffd16bd.jpeg ) [2] => Array ( [relateid] => 39201 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39201.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39201.html [published_timestamp] => 1538964341 [published] => 1538964341 [pv] => 1047 [virtual_pv] => 465 [all_pv] => 1047 [title] => 新洪塘大桥骨架逐渐成形 计划12月开展钢箱梁施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/b52a6bec724a757e8784cdd15ed98db5.jpeg ) [3] => Array ( [relateid] => 112554 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/112554.html [wapUrl] => http://m.fztvapp.zohi.tv/p/112554.html [published_timestamp] => 1567507724 [published] => 1567507724 [pv] => 593 [virtual_pv] => 454 [all_pv] => 593 [title] => 新建福厦高铁乌龙江特大桥进入承台及墩柱施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/9c299157796c53ca4fa8bcf8784e75d8.jpeg ) [4] => Array ( [relateid] => 39741 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/39741.html [wapUrl] => http://m.fztvapp.zohi.tv/p/39741.html [published_timestamp] => 1539152863 [published] => 1539152863 [pv] => 1066 [virtual_pv] => 380 [all_pv] => 1066 [title] => 福厦高铁泉州湾跨海大桥主栈桥顺利贯通 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/e4a891a6cabea92fa7063341ff6c7e37.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/201912/969c428a45be744d3c75713a27d4042b.jpeg ) 1

福厦高铁西溪特大桥进入规模化架梁阶段

2019-12-01 11:18   福视悦动  

福厦高铁西溪特大桥架梁施工现场,一孔长32米、重近900吨的庞然大物———预制箱梁,缓缓从地面向空中转移,精准落在桥面的运梁车上。目前,西溪特大桥进入规模化架梁阶段,运梁车将与架桥机配合,完成665孔箱梁的架设任务。据悉,目前已完成架梁约1公里,特大桥雏形初显。

福厦高铁西溪特大桥进行箱梁架设作业。(王协云航拍器摄)

昨日,记者在中铁四局福厦高铁8标西溪特大桥施工现场看到,一台硕大的提梁机正在与运梁车配合“演出”:铁路预制箱梁被提梁机缓缓提起,在10多米高的上方,运梁车已经停在桥面上接应。历时一个多小时的提拉、平移、定位,箱梁才从地面被搬到运梁车上。这台长约40米的运梁车共有16组、64个直径与成年人身高相当的大轮胎,从外观上看非常壮观,载着箱梁前进时就像是一座巨大的移动城堡。

西溪特大桥前期吊装架设三孔箱梁,形成一个作业面供运梁车在上方行驶;运梁车接过从地面吊上来的箱梁,载着它到达指定位置,与架桥机配合完成架梁。截至昨日,西溪特大桥已完成29孔箱梁的架设。

福厦高铁建设正在全力拼抢工期,厦门段控制性工程西溪特大桥更是处于全面攻坚阶段,工人们同步进行箱梁预制和墩身施工,多点开花,展现“高铁速度”。 


来源:厦门网
编辑:王蕾 责编:庄颖