Array ( [id] => 139842 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州新洪塘大桥部分通车 老桥封闭等待拆除 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-01-02 10:24:45 [createdby] => 10056 [createdip] => 120.35.7.76 [published] => 2020-01-02 10:24:45 [publishedby] => 10056 [modified] => 2020-01-02 10:26:28 [modifiedby] => 10056 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 559 [virtual_pv] => 459 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

1日,新建洪塘大桥下游三分之一桥幅正式通车,新老洪塘大桥正式完成“接棒”,这也标志着“两洪桥”拓宽改造项目新的“两桥一隧”全线贯通,服役近30年的洪塘大桥同步封闭并启动拆除。

新洪塘大桥三分之一幅桥面1日通车。(无人机拍摄)

1日上午,记者在洪塘大桥东侧上桥处看到,下游处三分之一幅桥已经开放,车辆有序驶上新桥。新桥设双向2车道,采取机非混行,通行能力维持不变。桥位较低的老洪塘大桥“陷”在两座新桥之间,正等待拆除。

值得注意的是,新桥仍维持限高限载通行模式。项目负责人介绍,此次启用的新桥仅为三分之一幅桥面,未闭合成完整桥梁,经设计单位验算,只能满足车流通行,故仍维持旧桥限高限载模式。重载车辆和大型货车要注意绕行,以免误闯限高架导致交通堵塞。

此外,老洪塘大桥将整体拆除,部分拆除的桥段要通过上游三分之一幅新桥运输,因此乌龙江上游的新桥作为施工场地及便道,暂不开放。

“两洪桥”项目起于鼓楼区洪山桥与杨桥西路、洪甘路的交叉口处,经洪山桥、妙峰山隧道、洪塘大桥,终点位于洪塘大桥西桥头附近,与国宾大道衔接,双向八车道,路线总长4.19公里。为了保证西向进出城交通不中断,项目采取了边施工、边通车的“保通”建设方案:分上、中、下游三个部分建设,先建上下游各三分之一幅桥面,再拆除老桥,新建中间三分之一幅桥,最后用预应力钢绞线将三幅桥串联在一起形成整体。“分三幅施工一次串联”的边施工、边通车“保通”建设方案,在国内尚属首例。

“两洪桥”项目计划明年全面建成通车,届时从杨桥路福大老校区北门至闽侯上街将全线无红绿灯,从福州西大门进出城将更加顺畅。


来源:福州新闻网
编辑:强婕宁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202001\/4914d8d01cdafca0af5675980cc5b56f.jpeg","id":"1555068"}] [url] => /p/139842.html [all_pv] => 559 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 新桥 [1] => 大桥 [2] => 三分之一 [3] => 洪塘 [4] => 拆除 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 139404 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/139404.html [wapUrl] => http://m.fztvapp.zohi.tv/p/139404.html [published_timestamp] => 1577784726 [published] => 1577784726 [pv] => 213 [virtual_pv] => 443 [all_pv] => 213 [title] => 新洪塘大桥下游三分之一幅,元旦零时通车! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201912/8d2d1a1eec3f3c0ea5418a66384a1fd8.jpeg ) [1] => Array ( [relateid] => 26269 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26269.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26269.html [published_timestamp] => 1531829146 [published] => 1531829146 [pv] => 104 [virtual_pv] => 432 [all_pv] => 104 [title] => 新洪塘大桥"双脚"已站立江中 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201807/8fb118b1dd7a2e836ddda757c1ec4e50.JPG ) [2] => Array ( [relateid] => 93972 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/93972.html [wapUrl] => http://m.fztvapp.zohi.tv/p/93972.html [published_timestamp] => 1560391481 [published] => 1560391481 [pv] => 333 [virtual_pv] => 375 [all_pv] => 333 [title] => 新洪塘大桥主塔本周“上梁” [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/4e7e02a5331658d3de1a803a18bf3fc4.jpeg ) [3] => Array ( [relateid] => 26539 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/26539.html [wapUrl] => http://m.fztvapp.zohi.tv/p/26539.html [published_timestamp] => 1532179285 [published] => 1532179285 [pv] => 1258 [virtual_pv] => 397 [all_pv] => 1258 [title] => 新洪塘大桥建设稳步推进 预计2020年建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201807/a6a8907089bf1fb6a6533484f9745259.JPG@w720_h540.JPG ) [4] => Array ( [relateid] => 99918 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/99918.html [wapUrl] => http://m.fztvapp.zohi.tv/p/99918.html [published_timestamp] => 1562723118 [published] => 1562723118 [pv] => 128 [virtual_pv] => 405 [all_pv] => 128 [title] => 洪塘大桥主塔上横梁安装完成 预计明年通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/c093bb8bff907506b239d673361babc2.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202001/4914d8d01cdafca0af5675980cc5b56f.jpeg ) 1

福州新洪塘大桥部分通车 老桥封闭等待拆除

2020-01-02 10:24   福视悦动  

1日,新建洪塘大桥下游三分之一桥幅正式通车,新老洪塘大桥正式完成“接棒”,这也标志着“两洪桥”拓宽改造项目新的“两桥一隧”全线贯通,服役近30年的洪塘大桥同步封闭并启动拆除。

新洪塘大桥三分之一幅桥面1日通车。(无人机拍摄)

1日上午,记者在洪塘大桥东侧上桥处看到,下游处三分之一幅桥已经开放,车辆有序驶上新桥。新桥设双向2车道,采取机非混行,通行能力维持不变。桥位较低的老洪塘大桥“陷”在两座新桥之间,正等待拆除。

值得注意的是,新桥仍维持限高限载通行模式。项目负责人介绍,此次启用的新桥仅为三分之一幅桥面,未闭合成完整桥梁,经设计单位验算,只能满足车流通行,故仍维持旧桥限高限载模式。重载车辆和大型货车要注意绕行,以免误闯限高架导致交通堵塞。

此外,老洪塘大桥将整体拆除,部分拆除的桥段要通过上游三分之一幅新桥运输,因此乌龙江上游的新桥作为施工场地及便道,暂不开放。

“两洪桥”项目起于鼓楼区洪山桥与杨桥西路、洪甘路的交叉口处,经洪山桥、妙峰山隧道、洪塘大桥,终点位于洪塘大桥西桥头附近,与国宾大道衔接,双向八车道,路线总长4.19公里。为了保证西向进出城交通不中断,项目采取了边施工、边通车的“保通”建设方案:分上、中、下游三个部分建设,先建上下游各三分之一幅桥面,再拆除老桥,新建中间三分之一幅桥,最后用预应力钢绞线将三幅桥串联在一起形成整体。“分三幅施工一次串联”的边施工、边通车“保通”建设方案,在国内尚属首例。

“两洪桥”项目计划明年全面建成通车,届时从杨桥路福大老校区北门至闽侯上街将全线无红绿灯,从福州西大门进出城将更加顺畅。