Array ( [id] => 157698 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州前横路将要向前横跨光明港 两座辅桥年底可投用 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-05-27 09:53:10 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-05-27 09:53:10 [publishedby] => 10056 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 526 [virtual_pv] => 431 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

前横路快速化改造工程全长5.285公里,约4.7公里与地铁4号线共线,为了与地铁建设“抢速度”,该项目桩基施工正加速推进。记者昨日从市城乡建设局获悉,该项目第四标段跨光明港两座辅桥将在年底率先投用,连接起远洋路和鳌港路。

光明港上方已横跨一座钢铁栈桥,它为前横路快速化改造工程第四标段主桥和辅桥建设提供工作面。

昨日,记者来到亚峰公园看到,光明港上方已横跨一座钢铁栈桥,大型机械正在上面挥舞“手臂”吊装各式材料。

“这座栈桥长114米,它为前横路快速化改造工程第四标段主桥和辅桥建设提供工作面,桥体两侧共设置了4个施工平台,下周起将进行光明港水下桩基施工。”市城乡建总该项目负责人告诉记者,由于跨光明港区域地质结构复杂,卵石层较深,第四标段是前横路快速化改造工程4个标段中,桩基长度最长的标段,平均桩长约80米,水下桩基总量为24根。

记者注意到,为了不影响岸上行人和河内游船通行,栈桥的设置也颇费心思。“如果仅从施工角度考虑,光明港两侧桥下净空仅有1米,这意味着光明港两侧的步道要被切断。为了方便市民通行,我们对栈桥方案进行优化,抬高栈桥高度,保障有不低于2米的桥下净空。同样,为了便于游船通过,光明港南侧近岸区域也优化了工程设置。”上述负责人说。

上述负责人表示,前横路快速化改造工程第四标段长约1公里,需要打桩209根,目前已完成9根桩基施工,力争在8月底前完成桩基和承台建设,9月底前完成两座辅桥下部结构施工,明年元旦前开放通行。届时,可将远洋路和鳌港路联系起来。据了解,这2座辅桥每座宽17.5米,分别设有2条机动车道、1条非机动车道和1条人行道。

上述负责人介绍,作为城区第三批缓堵重大项目,前横路快速化改造工程位于晋安区和台江区,南起鳌峰路,北接城区北向第二通道,几乎全线与地铁4号线并线。项目结合地铁进度分期实施,并确保于地铁盾构通过前完成桥梁下部结构施工。

目前,该项目4个标段下部结构施工已全面展开,其中第一标段已基本完工,第二标段桩基施工基本完成,正在进行承台施工,第三标段和第四标段均在进行桩基施工。

市城乡建设局相关负责人表示,前横路快速化改造工程北接园中互通,可连接连江、新店、琅岐方向,南接林浦路及林浦互通,可与三江口、滨海新城快速相接,被称为城区东部的“2.5环”,它对于缓解东二环和东三环交通压力意义重大。同时,该项目上部高架桥建设完成后将沿线串联鹤林组团、晋安湖片区、台江金融街片区、江南CBD片区,是福州东部片区快速进出的一个主通道。


来源:福州新闻网
编辑:强婕宁 责编:林真贞


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202005\/ce59e0e1cc74ad7d58f5d190142b6a37.jpeg","id":"1810016"}] [url] => /p/157698.html [all_pv] => 526 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 标段 [1] => 快速化 [2] => 桩基 [3] => 光明港 [4] => 施工 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 146678 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/146678.html [wapUrl] => http://m.fztvapp.zohi.tv/p/146678.html [published_timestamp] => 1581995545 [published] => 1581995545 [pv] => 160 [virtual_pv] => 469 [all_pv] => 160 [title] => 福州前横路改造工程桩基施工快速推进 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202002/1f8e224161255f746061ba9302b0ac89.jpeg ) [1] => Array ( [relateid] => 17430 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/17430.html [wapUrl] => http://m.fztvapp.zohi.tv/p/17430.html [published_timestamp] => 1521343609 [published] => 1521343609 [pv] => 182 [virtual_pv] => 474 [all_pv] => 182 [title] => 福州数字中国会展中心完成桩基施工 预计明年4月建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201803/460d95350b80c552360ae2a5200f84e1.png@w662_h497.png ) [2] => Array ( [relateid] => 17376 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/17376.html [wapUrl] => http://m.fztvapp.zohi.tv/p/17376.html [published_timestamp] => 1521246924 [published] => 1521246924 [pv] => 589 [virtual_pv] => 446 [all_pv] => 589 [title] => 福州数字中国会展中心完成桩基施工 预计明年4月建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201803/401ebdfba542eeaad2300b8d49fe19b4.png ) [3] => Array ( [relateid] => 14844 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/14844.html [wapUrl] => http://m.fztvapp.zohi.tv/p/14844.html [published_timestamp] => 1517453165 [published] => 1517453165 [pv] => 1068 [virtual_pv] => 0 [all_pv] => 1068 [title] => 滨海新城安置房一期桩基施工完成 共计3100余根 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/201802/dffc09296463b83e7e2bec23c335b75a.jpg@w414_h311.jpg ) [4] => Array ( [relateid] => 44394 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/44394.html [wapUrl] => http://m.fztvapp.zohi.tv/p/44394.html [published_timestamp] => 1540951053 [published] => 1540951053 [pv] => 1001 [virtual_pv] => 437 [all_pv] => 1001 [title] => 长福高速龙山互通桥面施工 预计2020年建成通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/a992a895a637fbf90a47204f3452a3dd.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202005/ce59e0e1cc74ad7d58f5d190142b6a37.jpeg ) 1

福州前横路将要向前横跨光明港 两座辅桥年底可投用

2020-05-27 09:53   福视悦动  

前横路快速化改造工程全长5.285公里,约4.7公里与地铁4号线共线,为了与地铁建设“抢速度”,该项目桩基施工正加速推进。记者昨日从市城乡建设局获悉,该项目第四标段跨光明港两座辅桥将在年底率先投用,连接起远洋路和鳌港路。

光明港上方已横跨一座钢铁栈桥,它为前横路快速化改造工程第四标段主桥和辅桥建设提供工作面。

昨日,记者来到亚峰公园看到,光明港上方已横跨一座钢铁栈桥,大型机械正在上面挥舞“手臂”吊装各式材料。

“这座栈桥长114米,它为前横路快速化改造工程第四标段主桥和辅桥建设提供工作面,桥体两侧共设置了4个施工平台,下周起将进行光明港水下桩基施工。”市城乡建总该项目负责人告诉记者,由于跨光明港区域地质结构复杂,卵石层较深,第四标段是前横路快速化改造工程4个标段中,桩基长度最长的标段,平均桩长约80米,水下桩基总量为24根。

记者注意到,为了不影响岸上行人和河内游船通行,栈桥的设置也颇费心思。“如果仅从施工角度考虑,光明港两侧桥下净空仅有1米,这意味着光明港两侧的步道要被切断。为了方便市民通行,我们对栈桥方案进行优化,抬高栈桥高度,保障有不低于2米的桥下净空。同样,为了便于游船通过,光明港南侧近岸区域也优化了工程设置。”上述负责人说。

上述负责人表示,前横路快速化改造工程第四标段长约1公里,需要打桩209根,目前已完成9根桩基施工,力争在8月底前完成桩基和承台建设,9月底前完成两座辅桥下部结构施工,明年元旦前开放通行。届时,可将远洋路和鳌港路联系起来。据了解,这2座辅桥每座宽17.5米,分别设有2条机动车道、1条非机动车道和1条人行道。

上述负责人介绍,作为城区第三批缓堵重大项目,前横路快速化改造工程位于晋安区和台江区,南起鳌峰路,北接城区北向第二通道,几乎全线与地铁4号线并线。项目结合地铁进度分期实施,并确保于地铁盾构通过前完成桥梁下部结构施工。

目前,该项目4个标段下部结构施工已全面展开,其中第一标段已基本完工,第二标段桩基施工基本完成,正在进行承台施工,第三标段和第四标段均在进行桩基施工。

市城乡建设局相关负责人表示,前横路快速化改造工程北接园中互通,可连接连江、新店、琅岐方向,南接林浦路及林浦互通,可与三江口、滨海新城快速相接,被称为城区东部的“2.5环”,它对于缓解东二环和东三环交通压力意义重大。同时,该项目上部高架桥建设完成后将沿线串联鹤林组团、晋安湖片区、台江金融街片区、江南CBD片区,是福州东部片区快速进出的一个主通道。