Array ( [id] => 157944 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 好消息!晋安这里新建跨河大桥,预计年底投用! [editor] => (编辑)王蕾 [has_thumb] => 1 [created] => 2020-05-29 15:57:53 [createdby] => 10052 [createdip] => 112.54.37.33 [published] => 2020-05-29 15:57:53 [publishedby] => 10052 [modified] => 2020-05-29 16:36:34 [modifiedby] => 10052 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 499 [virtual_pv] => 441 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 1 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

一桥跨南北  “天堑”变通途

陈暖/摄

在晋安区远洋路与前横路交叉口的光明港上,一座跨河桥梁粗具规模。这里,正在加速推进建设的是前横路快速化改造项目第四标段。

预计今年底,光明港上2座跨河桥梁将建成投用,往来晋安与台江将更方便。

效果图

前横路快速化改造工程分为4个标段,目前均已动工建设。

1标段(化工路至湖塘路)

2标段(塔头路至福新路)

3标段(福新路至远洋路)

4标段(远洋路至鳌峰路)

其中,第四标段长约1公里,需要打桩209根,已完成9根桩基施工,力争8月底前完成桩基和承台建设,9月底前完成辅桥下部结构施工,明年元旦前开放通行。

叶义斌/摄

辅桥每座宽17.5米,分别设有2条机动车道、1条非机动车道和1条人行道。作为城区第三批治堵重大项目之一,前横路快速化改造自动工之初就备受关注。这个被称为城区东部“2.5环”的工程,几乎全线与地铁4号线并线。

项目北起园中互通,南至鳌峰路,全长超5公里宽40米至70米。

项目采用“高架+辅路”建设方式,辅以互通、匝道等,在鹤林路、远洋路各新建1个互通化工路、前屿路、长春路各建设1处匝道。


项目效果图

通过该项目往北经园,中互通可去往连江、新店、琅岐方向往,南经跨越闽江的前横大桥接往林浦路、林浦互通等,可快速前往三江口以及滨海新城。

项目效果图

沿线串联起横屿组团鹤林片区、晋安湖片区、台江金融街片区、仓山江南CBD片区成为福州东部片区的快速通道。



来源:福州晚报
编辑:王蕾 责编:庄颖


[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202005\/b6daea437d1fd0d235ffa7afe32e0d84.jpeg","id":"1811130"}] [url] => /p/157944.html [all_pv] => 499 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 标段 [1] => 片区 [2] => 互通 [3] => 快速化 [4] => 远洋 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 150268 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/150268.html [wapUrl] => http://m.fztvapp.zohi.tv/p/150268.html [published_timestamp] => 1584583923 [published] => 1584583923 [pv] => 82 [virtual_pv] => 368 [all_pv] => 82 [title] => 前横路快速化改造工程启动 缓解东二环东三环交通压力 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202003/3ea9c23e31561601c37d61caa23d8e96.jpeg ) [1] => Array ( [relateid] => 157698 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/157698.html [wapUrl] => http://m.fztvapp.zohi.tv/p/157698.html [published_timestamp] => 1590544390 [published] => 1590544390 [pv] => 91 [virtual_pv] => 431 [all_pv] => 91 [title] => 福州前横路将要向前横跨光明港 两座辅桥年底可投用 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202005/ce59e0e1cc74ad7d58f5d190142b6a37.jpeg ) [2] => Array ( [relateid] => 84279 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/84279.html [wapUrl] => http://m.fztvapp.zohi.tv/p/84279.html [published_timestamp] => 1556585791 [published] => 1556585791 [pv] => 412 [virtual_pv] => 452 [all_pv] => 412 [title] => 榕东北片区重要通道5月展新颜 点亮互通扮靓隧道 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/bf1aa6e87ea1f7319927cbba1851da65.jpeg ) [3] => Array ( [relateid] => 157728 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/157728.html [wapUrl] => http://m.fztvapp.zohi.tv/p/157728.html [published_timestamp] => 1590566158 [published] => 1590566158 [pv] => 100 [virtual_pv] => 369 [all_pv] => 100 [title] => 福州东“2.5环”!重大进展! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202005/3c1ec3b9378404c3406b04b3adef7d0c.jpeg ) [4] => Array ( [relateid] => 99630 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/99630.html [wapUrl] => http://m.fztvapp.zohi.tv/p/99630.html [published_timestamp] => 1562584802 [published] => 1562584802 [pv] => 309 [virtual_pv] => 422 [all_pv] => 309 [title] => 农业农村部批准设立福州(连江)国家远洋渔业基地 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201907/442a6cf33d735cac0075f674b4769bdc.JPG ) ) [article_thumb] => http://www.zohi.tv/a/10001/202005/b6daea437d1fd0d235ffa7afe32e0d84.jpeg ) 1

好消息!晋安这里新建跨河大桥,预计年底投用!

2020-05-29 15:57   福视悦动  

一桥跨南北  “天堑”变通途

陈暖/摄

在晋安区远洋路与前横路交叉口的光明港上,一座跨河桥梁粗具规模。这里,正在加速推进建设的是前横路快速化改造项目第四标段。

预计今年底,光明港上2座跨河桥梁将建成投用,往来晋安与台江将更方便。

效果图

前横路快速化改造工程分为4个标段,目前均已动工建设。

1标段(化工路至湖塘路)

2标段(塔头路至福新路)

3标段(福新路至远洋路)

4标段(远洋路至鳌峰路)

其中,第四标段长约1公里,需要打桩209根,已完成9根桩基施工,力争8月底前完成桩基和承台建设,9月底前完成辅桥下部结构施工,明年元旦前开放通行。

叶义斌/摄

辅桥每座宽17.5米,分别设有2条机动车道、1条非机动车道和1条人行道。作为城区第三批治堵重大项目之一,前横路快速化改造自动工之初就备受关注。这个被称为城区东部“2.5环”的工程,几乎全线与地铁4号线并线。

项目北起园中互通,南至鳌峰路,全长超5公里宽40米至70米。

项目采用“高架+辅路”建设方式,辅以互通、匝道等,在鹤林路、远洋路各新建1个互通化工路、前屿路、长春路各建设1处匝道。


项目效果图

通过该项目往北经园,中互通可去往连江、新店、琅岐方向往,南经跨越闽江的前横大桥接往林浦路、林浦互通等,可快速前往三江口以及滨海新城。

项目效果图

沿线串联起横屿组团鹤林片区、晋安湖片区、台江金融街片区、仓山江南CBD片区成为福州东部片区的快速通道。



来源:福州晚报
编辑:王蕾 责编:庄颖