Array ( [id] => 158510 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州北向第二通道有了新进展!北岭隧道开始掘进 [editor] => (责编)林真贞 [has_thumb] => 1 [created] => 2020-06-05 11:06:43 [createdby] => 10092 [createdip] => 112.54.37.33 [published] => 2020-06-05 11:06:43 [publishedby] => 10092 [modified] => 2020-06-05 11:08:20 [modifiedby] => 10125 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 500 [virtual_pv] => 370 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

福州北向第二通道是除绕城高速外又一条连接福州主城区、晋安区桂湖片区以及连江县贵安片区的重要通道,记者从交建集团了解到,该项目重要控制性节点——北岭隧道已经开始进洞掘进,全线工程力争2023年完工通车。


北岭隧道全长近8公里,设计双向六车道,时速60公里,隧道穿越多个山体断层带,山体内来水较多,给施工造成不少困难。



中铁隧道局福州北向第二通道A2标段总工程师梁泽:“每一次掘进控制在0.5米,来保证施工安全。水主要以引排为主,我们设计了一系列堵水措施,力争明年年底实现隧道贯通。”

北岭隧道采用双向掘进方式,其中A1标段由新店镇杨廷村向桂湖方向掘进,A2标段由桂湖向新店方向掘进。此外,福州北向第二通道A3标段负责建设连接桂湖和贵安长约4.6公里的快速通道,全程利用高架桥连接并建有两座枢纽。



中铁隧道局福州北向第二通道A3标段副经理朱先会:“因为路基挖方量很大,离绕城高速很近,施工爆破采用高墙防护,并做好警示。在技术方面我们安排了专职测量组,一道道工序控制好,现在已完成10%左右工程量。”

福州北向第二通道全长13.26公里,预计2023年完工,通车后,可极大缓解绕城高速及贵新隧道的交通压力,拉近福州城区、晋安桂湖片区以及连江贵安片区的通行距离,加快区域建设发展。







福州广播电视台出品
编辑:强婕宁 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202006\/f09949c57ed78de318931f8a73c5b145.gif","id":"1813756"}] [url] => /p/158510.html [all_pv] => 500 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 福州 [1] => 隧道 [2] => 标段 [3] => 北向 [4] => 掘进 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 158476 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/158476.html [wapUrl] => http://m.fztvapp.zohi.tv/p/158476.html [published_timestamp] => 1591270276 [published] => 1591270276 [pv] => 376 [virtual_pv] => 482 [all_pv] => 376 [title] => 福州北向第二通道有了新进展!北岭隧道开始掘进 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202006/5806df4f3913f916cb2d73f220e54636.png ) [1] => Array ( [relateid] => 158464 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/158464.html [wapUrl] => http://m.fztvapp.zohi.tv/p/158464.html [published_timestamp] => 1591269669 [published] => 1591269669 [pv] => 145 [virtual_pv] => 477 [all_pv] => 145 [title] => 福州北向第二通道北岭隧道开始掘进 全线力争2023年通车 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/thumb/10001/202006/575e512656b904fd4862445f7c60d845.jpg@w858_h483.jpg ) [2] => Array ( [relateid] => 73602 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/73602.html [wapUrl] => http://m.fztvapp.zohi.tv/p/73602.html [published_timestamp] => 1552440259 [published] => 1552440259 [pv] => 961 [virtual_pv] => 391 [all_pv] => 961 [title] => 福州城区北向第二通道(晋安段)工程建设用地获批 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/82a1eccc1357e6f9ea904ca7274adfb0.jpeg ) [3] => Array ( [relateid] => 97089 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/97089.html [wapUrl] => http://m.fztvapp.zohi.tv/p/97089.html [published_timestamp] => 1561599176 [published] => 1561599176 [pv] => 113 [virtual_pv] => 486 [all_pv] => 113 [title] => 工业北路延伸线慢行隧道“穿山” 主体明年底建成 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201906/e62ce28678cd71ab6d0b520dbc160282.jpeg ) [4] => Array ( [relateid] => 42675 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/42675.html [wapUrl] => http://m.fztvapp.zohi.tv/p/42675.html [published_timestamp] => 1540263985 [published] => 1540263985 [pv] => 888 [virtual_pv] => 430 [all_pv] => 888 [title] => 福厦客运专线闽侯段建设提速 杨梅山隧道进洞施工 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201810/765757655f9e47adf93cbe81c95512ab.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202006/f09949c57ed78de318931f8a73c5b145.gif ) 1

福州北向第二通道有了新进展!北岭隧道开始掘进

2020-06-05 11:06   福视悦动  

福州北向第二通道是除绕城高速外又一条连接福州主城区、晋安区桂湖片区以及连江县贵安片区的重要通道,记者从交建集团了解到,该项目重要控制性节点——北岭隧道已经开始进洞掘进,全线工程力争2023年完工通车。


北岭隧道全长近8公里,设计双向六车道,时速60公里,隧道穿越多个山体断层带,山体内来水较多,给施工造成不少困难。



中铁隧道局福州北向第二通道A2标段总工程师梁泽:“每一次掘进控制在0.5米,来保证施工安全。水主要以引排为主,我们设计了一系列堵水措施,力争明年年底实现隧道贯通。”

北岭隧道采用双向掘进方式,其中A1标段由新店镇杨廷村向桂湖方向掘进,A2标段由桂湖向新店方向掘进。此外,福州北向第二通道A3标段负责建设连接桂湖和贵安长约4.6公里的快速通道,全程利用高架桥连接并建有两座枢纽。



中铁隧道局福州北向第二通道A3标段副经理朱先会:“因为路基挖方量很大,离绕城高速很近,施工爆破采用高墙防护,并做好警示。在技术方面我们安排了专职测量组,一道道工序控制好,现在已完成10%左右工程量。”

福州北向第二通道全长13.26公里,预计2023年完工,通车后,可极大缓解绕城高速及贵新隧道的交通压力,拉近福州城区、晋安桂湖片区以及连江贵安片区的通行距离,加快区域建设发展。