Array ( [id] => 159922 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => “服役”16年 闽侯甘竹大桥首次大修 [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-06-21 17:47:13 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-06-21 17:47:13 [publishedby] => 10056 [modified] => 0000-00-00 00:00:00 [modifiedby] => 0 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 503 [virtual_pv] => 455 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

近来,连接闽侯甘蔗、竹岐的重要跨江通道——甘竹大桥的15个桥墩进行维修加固,预计10月完工。这是甘竹大桥“服役”16年来的首次大修。

甘竹大桥正在开展桥墩维修加固工作

甘竹大桥于2004年建成通车,全长约1.376公里,是闽侯县自建的第一座跨闽江大桥。去年,闽侯县交通运输局委托省交通科研所对甘竹大桥14#~28#桥墩水下桩基进行详细探摸检测,发现水下桩基损坏严重。特别是桩基常年受到闽江水流冲刷,混凝土加剧疏松、剥落,钢筋网外露,原桩的有效桩径普遍缩小,部分桩基钢筋受到腐蚀,影响桥梁运行安全。

今年5月,闽侯县交通运输局启动桥墩维修加固工作。该项目总投资2820万元,计划采用增大桩基截面的方法,对14#~28#15个桥墩的42根水下桩基进行加固。

据施工单位相关负责人介绍,此次施工作业位于深水环境,且受上游水口电站泄洪影响,水流变化复杂,施工风险高。同时,桥梁净空不足、内支撑设置难度较大等也是大桥维修加固的难点。为确保如期完工,施工方每天安排近30名工人抢抓进度。为了避开高温天气,施工方还及时调整作业时间,实行错峰施工。

闽侯县交通运输局相关工作人员介绍,目前,该工程已完成19#、20#桥墩桩基的维修工作,整体预计10月完工。在大桥维修加固期间,桥面可以正常通行。


来源:福州新闻网
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => 15个桥墩将维修加固 桥面交通不受影响 [thumb] => [{"url":"\/a\/10001\/202006\/ace48978060b6bd48292cf91d2c03286.jpeg","id":"1821436"}] [url] => /p/159922.html [all_pv] => 503 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 桩基 [1] => 大桥 [2] => 桥墩 [3] => 加固 [4] => 维修 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 60327 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/60327.html [wapUrl] => http://m.fztvapp.zohi.tv/p/60327.html [published_timestamp] => 1547089500 [published] => 1547089500 [pv] => 683 [virtual_pv] => 457 [all_pv] => 683 [title] => 连江山仔水库除险加固工程正式开工 工期18个月 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/50c2a958aacc2396aff413e3217116c8.jpeg ) [1] => Array ( [relateid] => 89922 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/89922.html [wapUrl] => http://m.fztvapp.zohi.tv/p/89922.html [published_timestamp] => 1558696317 [published] => 1558696317 [pv] => 308 [virtual_pv] => 457 [all_pv] => 308 [title] => 乌龙江旧大桥突发"险情" 实战演练提升应急处置能力 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/5e429a09356bba87aa43be29641f3284.jpeg ) [2] => Array ( [relateid] => 58473 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/58473.html [wapUrl] => http://m.fztvapp.zohi.tv/p/58473.html [published_timestamp] => 1546421969 [published] => 1546421969 [pv] => 1227 [virtual_pv] => 391 [all_pv] => 1227 [title] => 2019元旦起,维修资金使用全新升级! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/2addd26253c00f0182965ffee60d707b.jpeg ) [3] => Array ( [relateid] => 146678 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/146678.html [wapUrl] => http://m.fztvapp.zohi.tv/p/146678.html [published_timestamp] => 1581995545 [published] => 1581995545 [pv] => 156 [virtual_pv] => 469 [all_pv] => 156 [title] => 福州前横路改造工程桩基施工快速推进 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/202002/1f8e224161255f746061ba9302b0ac89.jpeg ) [4] => Array ( [relateid] => 113268 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/113268.html [wapUrl] => http://m.fztvapp.zohi.tv/p/113268.html [published_timestamp] => 1567753527 [published] => 1567753527 [pv] => 52 [virtual_pv] => 389 [all_pv] => 52 [title] => 闽侯二桥成功完成首根桩基浇筑! [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201909/883254a2cbdb0a2a83d23d69d69fc419.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202006/ace48978060b6bd48292cf91d2c03286.jpeg ) 1

“服役”16年 闽侯甘竹大桥首次大修

2020-06-21 17:47   福视悦动  

近来,连接闽侯甘蔗、竹岐的重要跨江通道——甘竹大桥的15个桥墩进行维修加固,预计10月完工。这是甘竹大桥“服役”16年来的首次大修。

甘竹大桥正在开展桥墩维修加固工作

甘竹大桥于2004年建成通车,全长约1.376公里,是闽侯县自建的第一座跨闽江大桥。去年,闽侯县交通运输局委托省交通科研所对甘竹大桥14#~28#桥墩水下桩基进行详细探摸检测,发现水下桩基损坏严重。特别是桩基常年受到闽江水流冲刷,混凝土加剧疏松、剥落,钢筋网外露,原桩的有效桩径普遍缩小,部分桩基钢筋受到腐蚀,影响桥梁运行安全。

今年5月,闽侯县交通运输局启动桥墩维修加固工作。该项目总投资2820万元,计划采用增大桩基截面的方法,对14#~28#15个桥墩的42根水下桩基进行加固。

据施工单位相关负责人介绍,此次施工作业位于深水环境,且受上游水口电站泄洪影响,水流变化复杂,施工风险高。同时,桥梁净空不足、内支撑设置难度较大等也是大桥维修加固的难点。为确保如期完工,施工方每天安排近30名工人抢抓进度。为了避开高温天气,施工方还及时调整作业时间,实行错峰施工。

闽侯县交通运输局相关工作人员介绍,目前,该工程已完成19#、20#桥墩桩基的维修工作,整体预计10月完工。在大桥维修加固期间,桥面可以正常通行。