Array ( [id] => 163188 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁1号线二期试运营倒计时!途经…… [editor] => (编辑)强婕宁 [has_thumb] => 1 [created] => 2020-07-29 19:08:58 [createdby] => 10056 [createdip] => 112.54.37.33 [published] => 2020-07-29 18:45:03 [publishedby] => 10056 [modified] => 2020-07-29 19:37:30 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 432 [virtual_pv] => 377 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [content] =>

距离福州地铁免费乘坐还有两天时间。

↓↓↓↓

重磅!福州地铁、公交车限时免费乘坐!

今天,福州地铁又有好消息啦!市城乡建设局发布了福州地铁最新建设进展,涉及1号线二期、4号线、5号线、6号线。

1号线二期已全部洞通 预计今年底试运营

距离地铁1号线一期开通不知不觉已经3年多了,不少小伙伴都留言问二期什么时候建好?

最新消息来了!目前,1号线二期已全部洞通,预计2020年底开通试运营。

根据规划,福州地铁1号线二期工程北起福州火车南站站,南至三江口站,线路全长4.924千米。共设四站四区间,途经安平、梁厝、下洋、三江口4座车站,其中,梁厝站、下洋站可与在建6号线换乘。

4号线一期2022年底试运营

福州地铁4号线车站已全面开工建设,其中4座已完成结构封顶,2个区间双向贯通,预计一期工程2022年底建成试运营。

4号线一期工程线路起于半洲站,止于浦口站,全长约28.4千米,全部为地下线。

途经金山片区、鼓台、晋安、仓山、义序片区等组团,连接中央CBD、福州海峡国际会展中心、鼓台中心商业区等重要节点,共设置23座车站,全部为地下车站。

5号线计划2021年底试运营

5号线14座车站主体结构完成封顶,5个区间双向贯通,4个区间单向贯通,计划于2021年底开通试运营。

5号线一期工程线路起于荆溪新城站,止于福州火车南站站,大致呈东西走向,全长约27.7千米,全部为地下线。

共设置20座车站,途经荆溪新城、金山片区、义序片区、南台岛东部片区等组团,连接福州海峡奥林匹克体育中心、福州南站等重要节点。

6号线计划分两期开通试运营

近日,作为6号线唯一的高架站,营前站附属人行天桥钢结构工程也顺利完成吊装。

目前,6号线车站已全部封顶盾构区间完成98%,计划分两期开通试运营。

长乐段(营前站至万寿站)计划于2021年1月30日完成消防验收,仓山段(潘墩站至营前站)计划于2021年7月30日完成消防验收。

6号线东延段

6号线起于潘墩站,止于国际学校站(工程名),大致呈东西走向,全长约36.5千米。

途经仓山区、长乐区,连接三江口、长乐、滨海新城等组团,共设置22座车站,包括地下站21座、高架站1座。其中,梁厝站和下洋站为1号线二期和6号线换乘站。

营前站效果图

2号线东延线规划方案公布

日前,国家发改委官网发布《关于调整福州市城市轨道交通第二期建设规划方案的批复》,同意对《福州市城市轨道交通第二期建设规划(2015-2021年)》方案进行适当调整。

方案中优化调整了2号线,原先的“福州地铁2号线马尾延伸段”改名为“福州地铁2号线东延线”。

2号线东延线由鼓山站延伸至马尾港站。在站点规划上也发生了变化,最为明显的是原先的“东方名城站”并未体现,只保留“魁岐站”。


目前,2号线船政文化城站正在施工中,预计今年年底,船政文化城站可完成地下连续墙施工。马尾地铁建设又向前迈进了一步!

看了这个时间表,2020年至2023年福州是每年新开通一条地铁线路的节奏,你最期待哪条线路通车?


来源:福州市城乡建设局、福州地铁、最美长乐、马尾的事儿、海西房产网等
编辑:强婕宁 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202007\/a9bb1bc3f8fa2a3c60932dcffe250e60.jpeg","id":"1837522"},{"url":"\/a\/10001\/202007\/775d6344d9fd6f8a37ec071ee7425e79.jpeg","id":"1837524"},{"url":"\/a\/10001\/202007\/58905d7d629dffd3e3eefd346b9b03a9.png","id":"1837526"}] [url] => /p/163188.html [all_pv] => 432 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 福州 [2] => 地铁 [3] => 试运营 [4] => 车站 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( [0] => Array ( [relateid] => 59370 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/59370.html [wapUrl] => http://m.fztvapp.zohi.tv/p/59370.html [published_timestamp] => 1546741705 [published] => 1546741705 [pv] => 818 [virtual_pv] => 368 [all_pv] => 818 [title] => 定了!福州地铁2号线5月1日试运营 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201901/a2854e6fff68333155ddca326a82d5c6.jpeg ) [1] => Array ( [relateid] => 83559 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/83559.html [wapUrl] => http://m.fztvapp.zohi.tv/p/83559.html [published_timestamp] => 1556277902 [published] => 1556277902 [pv] => 180 [virtual_pv] => 404 [all_pv] => 180 [title] => 地铁2号线正式开通试运营 福州地铁步入"换乘时代" [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/94770643da48f39b6160558f91421fcb.JPG ) [2] => Array ( [relateid] => 83082 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/83082.html [wapUrl] => http://m.fztvapp.zohi.tv/p/83082.html [published_timestamp] => 1556104238 [published] => 1556104238 [pv] => 460 [virtual_pv] => 455 [all_pv] => 460 [title] => 地铁2号线本周五开通载客试运营 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201904/51b8be0c84d0ab7da2e4d04323d29978.JPG ) [3] => Array ( [relateid] => 90294 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/90294.html [wapUrl] => http://m.fztvapp.zohi.tv/p/90294.html [published_timestamp] => 1558918475 [published] => 1558918475 [pv] => 227 [virtual_pv] => 413 [all_pv] => 227 [title] => 地铁2号线试运营满月成绩亮眼 运行图兑现率100% [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201905/a69bbaf648db1d929e2c2fcfad025bd5.jpeg ) [4] => Array ( [relateid] => 71610 [appid] => 1 [pcUrl] => http://www.zohi.tv/p/71610.html [wapUrl] => http://m.fztvapp.zohi.tv/p/71610.html [published_timestamp] => 1551664015 [published] => 1551664015 [pv] => 91 [virtual_pv] => 406 [all_pv] => 91 [title] => 福州地铁2号线即将全线“跑图”!距载客试运营仅2个月 [has_thumb] => 1 [thumb] => http://www.zohi.tv/a/10001/201903/3039a3b8a65bf85a253298704d74ce50.jpeg ) ) [article_thumb] => http://www.zohi.tv/a/10001/202007/a9bb1bc3f8fa2a3c60932dcffe250e60.jpeg ) 1

福州地铁1号线二期试运营倒计时!途经……

2020-07-29 18:45   福视悦动  

距离福州地铁免费乘坐还有两天时间。

↓↓↓↓

重磅!福州地铁、公交车限时免费乘坐!

今天,福州地铁又有好消息啦!市城乡建设局发布了福州地铁最新建设进展,涉及1号线二期、4号线、5号线、6号线。

1号线二期已全部洞通 预计今年底试运营

距离地铁1号线一期开通不知不觉已经3年多了,不少小伙伴都留言问二期什么时候建好?

最新消息来了!目前,1号线二期已全部洞通,预计2020年底开通试运营。

根据规划,福州地铁1号线二期工程北起福州火车南站站,南至三江口站,线路全长4.924千米。共设四站四区间,途经安平、梁厝、下洋、三江口4座车站,其中,梁厝站、下洋站可与在建6号线换乘。

4号线一期2022年底试运营

福州地铁4号线车站已全面开工建设,其中4座已完成结构封顶,2个区间双向贯通,预计一期工程2022年底建成试运营。

4号线一期工程线路起于半洲站,止于浦口站,全长约28.4千米,全部为地下线。

途经金山片区、鼓台、晋安、仓山、义序片区等组团,连接中央CBD、福州海峡国际会展中心、鼓台中心商业区等重要节点,共设置23座车站,全部为地下车站。

5号线计划2021年底试运营

5号线14座车站主体结构完成封顶,5个区间双向贯通,4个区间单向贯通,计划于2021年底开通试运营。

5号线一期工程线路起于荆溪新城站,止于福州火车南站站,大致呈东西走向,全长约27.7千米,全部为地下线。

共设置20座车站,途经荆溪新城、金山片区、义序片区、南台岛东部片区等组团,连接福州海峡奥林匹克体育中心、福州南站等重要节点。

6号线计划分两期开通试运营

近日,作为6号线唯一的高架站,营前站附属人行天桥钢结构工程也顺利完成吊装。

目前,6号线车站已全部封顶盾构区间完成98%,计划分两期开通试运营。

长乐段(营前站至万寿站)计划于2021年1月30日完成消防验收,仓山段(潘墩站至营前站)计划于2021年7月30日完成消防验收。

6号线东延段

6号线起于潘墩站,止于国际学校站(工程名),大致呈东西走向,全长约36.5千米。

途经仓山区、长乐区,连接三江口、长乐、滨海新城等组团,共设置22座车站,包括地下站21座、高架站1座。其中,梁厝站和下洋站为1号线二期和6号线换乘站。

营前站效果图

2号线东延线规划方案公布

日前,国家发改委官网发布《关于调整福州市城市轨道交通第二期建设规划方案的批复》,同意对《福州市城市轨道交通第二期建设规划(2015-2021年)》方案进行适当调整。

方案中优化调整了2号线,原先的“福州地铁2号线马尾延伸段”改名为“福州地铁2号线东延线”。

2号线东延线由鼓山站延伸至马尾港站。在站点规划上也发生了变化,最为明显的是原先的“东方名城站”并未体现,只保留“魁岐站”。


目前,2号线船政文化城站正在施工中,预计今年年底,船政文化城站可完成地下连续墙施工。马尾地铁建设又向前迈进了一步!

看了这个时间表,2020年至2023年福州是每年新开通一条地铁线路的节奏,你最期待哪条线路通车?


来源:福州市城乡建设局、福州地铁、最美长乐、马尾的事儿、海西房产网等
编辑:强婕宁 责编:林真贞